Los Gatos Creek Bridge Replacement Project Oct 18. 2017
Agenda I. Project Description II. Project Benefits III. Challenges IV. Construction Update
Project Location Located along Caltrain line • In the City of San Jose • Bounded by Park Avenue to the north and Interstate 280 to the south
Los Gatos Creek Bridge • Owned by the Peninsula Corridor Joint Powers Board • MT1 owned by UPRR Built in 1935 Does not meet existing current seismic safety standards Has structural deficiencies Southern timber span was damaged by fire Recent Flooding has caused significant scour
Project Elements • Demolish existing two-track bridge • Replace existing bridge with three new single track bridges Meet current safety and seismic codes Include a tail track to maintain rail operations throughout construction • Build a Retaining Wall Widen Creek Channel Facilitate City of San Jose future bike trail
Project Benefits
Project Benefits • Safe rail operations • Improves operations at the San Jose Diridon Station • Addition of Tail Track
Construction Challenges
Construction Phases • Phase I • Pre June 1 Work • Staging, fencing, temporary access roads, signal work, tail track abutment work, and retaining wall work • Phase II – Dry Season Window • June 2017 – Aug. 2017 – Single Tracking on MT1 • Tail track bridge construction, includes bridge foundation and abutment work, pre-cast superstructure crane-in • Aug. 2017 – Oct. 2017 – Single Tracking on Tail Track • Existing bridge demolition, new Main Track 1 & 2 bridge construction and in-creek site mitigation • Phase II -- Post Oct 2017 • Main Track 1 & 2 track and signal work, out-of-creek site mitigation, and site clean-up.
Construction Staging -- In Creek
Unforeseen Conditions
Water Diversion Creek Water Diversion & Fish Relocation
Limited Access
Construction Status
Progress in Field – Shoofly
Progress in Field – MT 1 and MT2
MT1 Bridge Construction
Building Bents
MT1 and MT2 Bridges
Questions
Los Gatos Creek Bridge Replacement / South Terminal Phase III Project
DEEP CREEK BRIDGE REPLACEMENT PROJECT OVERVIEW COL Patrick V. Kinsman P.E.
Deep Creek Bridge Replacement Over the Intracoastal Waterway The project is
White Creek Rd over Little White Creek Bridge Replacement Project Public
Design Project #1 Replacement of Vehicle Bridge over Spring Creek Centre
Design Project #1 Replacement of Vehicle Bridge over Spring Creek Centre
Cedar Party Creek Bridge Replacement Community Consultation Slides
County of Santa Clara Parks and Recreation Los Gatos Creek Trail November 7,
Public Involvement WIS 79 Coon Creek Bridge (B-17-0368) & Clack Creek
40TH AVENUE NE BRIDGE REPLACEMENT 40TH AVENUE NE BRIDGE REPLACEMENT Where to
Pedestrian Bridge and Connecting Trail Over Arizona Avenue, NW Public Meeting
SR 73 Loudon County Bridge SR73 Bridge History Several alternates were
STUDY OF PARAMETERS THAT INFLUENCE I-GIRDER BRIDGE BEHAVIOR DURING FIRE
IOWA ACCELERATED BRIDGE CONSTRUCTION Norm McDonald, PE 2014 ASCE
The 4 th International Conference on Rehabilitation and Maintenance in Civil
KINGFIELD CENTENNIAL BRIDGE #5852 WEARING SURFACE REPLACEM ENT Public Meeting
Sylvester Powers Bridge Schedule B Municipal Class Environmental Assessment
Waimea Community Dam Update 25 September 2019 Waimea Water; Damwatch
An Awrel Case Presentation: Opportunity Cost and Value Chain for Fabrication
SH16 St Lukes / Great North Road Upgrade Project Overview for the Community
Acceptance and Acceptance and Commitment Therapy Commitment Therapy (ACT)
3/11/2013 Brief Interventions for Radical Change: The Practice of Focused