public involvement
play

Public Involvement WIS 79 Coon Creek Bridge (B-17-0368) & Clack - PowerPoint PPT Presentation

Public Involvement WIS 79 Coon Creek Bridge (B-17-0368) & Clack Creek Bridge (B-17-0369) Town of Sherman Dunn County July 22, 2020 Project Team WisDOT Northwest Region Tyler Rongstad, P.E. Project Manager MSA Professional


  1. Public Involvement WIS 79 Coon Creek Bridge (B-17-0368) & Clack Creek Bridge (B-17-0369) Town of Sherman Dunn County July 22, 2020

  2. Project Team • WisDOT Northwest Region  Tyler Rongstad, P.E. – Project Manager • MSA Professional Services, Inc.  James Watters, P.E. – Consultant Designer

  3. Event Objectives • Project Information • Project Location • Purpose and Need • Proposed Improvements • Construction Staging • Real Estate Needs • Access Modification • Current Project Schedule • Questions and Input

  4. Project Information • WIS 79 is a rural minor arterial highway that provides a north/south route for the Dunn County communities of Connorsville , Boyceville and Sherman . • Average of 1,800 vehicles per day. • WIS 79 crosses over Coon and Clack creeks between the village of Boyceville and its terminus with US 12. • Existing structures were constructed in 1936. • Structures are made of concrete decking supported by steel beams and a timber-pile substructure. • Last significant bridge repair was done in 1987.

  5. Project Location

  6. Purpose and Need • The purpose of this project is to address the deteriorating structural elements of both bridges . • The need for this project is to address the following: • Bridge deck deterioration • Structural support deterioration • Substandard bridge railing

  7. Purpose and Need • Bridge deck and steel beam deterioration • Clack Creek Bridge, B-17-0369, typical • Coon Creek Bridge, B-17-0368, spalling at concrete soffit. deteriorated steel girder and timber pile substructure view.

  8. Purpose and Need • Timber-pile structural support deterioration • Typical condition of timber-pile supports found at both bridges.

  9. Purpose and Need • Substandard bridge railing. • Typical railing design found at both structures.

  10. Proposed Improvements 1. Bridge – construct new bridge consisting of a concrete deck and structural support elements. a. Railing will be solid concrete parapet wall. b. Width of bridge will be widened by 4 feet. 2. Roadway – reconstruct asphalt roadway approaches to each bridge, replace existing guardrail, replace pavement markings and signs. a. Roadway alignment will match existing. b. Change in roadway vertical profile is anticipated: i. Raise of approximately 1.5 feet at Coon Creek crossing. ii. Raise of approximately 2 feet at Clack Creek crossing. iii. Change in elevation needed to install standard concrete railing.

  11. Proposed Improvements Coon Creek Bridge – Estimated Construction Limits N 350’ 550’

  12. Proposed Improvements Clack Creek Bridge – Estimated Construction Limits N 325’ 575’

  13. Construction Staging • WIS 79 will be closed to through traffic, and a detour route will be implemented. • Detour route will utilize US 12, WIS 25 and WIS 170. • Residents on 750 th Ave., 390 th St. and 770 th Ave. can access the detour route via County J. • Anticipated closure duration is one construction season.

  14. Detour Route ` NORTH TERMINUS SOUTH TERMINUS

  15. Access Modifications • No permanent change to existing accesses on WIS 79 is proposed. • Access to adjacent properties will be maintained at all times. • Some driveway accesses near these bridges will need to be raised to match raised centerline elevation of WIS 79.

  16. Real Estate Needs • Coon Creek Bridge N (B-17-0368) • Permanent right of way along the west side of WIS 79 for grading and embankment construction. • Temporary easements along the right of way for grading and tying in slopes.

  17. Real Estate Needs • Clack Creek Bridge N (B-17-0369) • Permanent right of way along the west and east side of the highway right of way. • Temporary easements along the right of way for grading and tying in slopes.

  18. Real Estate Needs • Acquisition process • WisDOT will acquire real estate. • Individual property owner meetings will be held. • Real estate acquisitions will begin in 2021. • Landowner rights brochure on the project website.

  19. Current Project Schedule • Surveys and initial agency coordination– Late 2018-19 • Local official meetings – May 2020 • Public involvement – July 2020 • Final environmental document – September/October 2020 • Final right of way plat – November 2020 • Right-of-way acquisition – Winter 2020 through 2021 • Final plans – May 2022 • Construction – As early as spring/summer 2023; currently scheduled for 2025

  20. Project Website & Input Visit: https://wisconsindot.gov/Pages/projects/by-region/nw/wis79dunn/default.aspx

  21. Thank You WIS 79 Coon Creek Bridge (B-17-0368) & Clack Creek Bridge (B-17-0369) Town of Sherman Dunn County

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend