update
play

Update 17 December 2019 Waimea Water 17/12/2019 Waimea Water Ltd - PowerPoint PPT Presentation

Waimea Community Dam Update 17 December 2019 Waimea Water 17/12/2019 Waimea Water Ltd 1 Agenda Design Construction Environmental 2009: 5-9 2012: 10-14 Cost and schedule 2017: 15-17 17/12/2019 Waimea Water Ltd 2 Waimea


  1. Waimea Community Dam Update 17 December 2019 Waimea Water 17/12/2019 Waimea Water Ltd 1

  2. Agenda • Design • Construction • Environmental 2009: 5-9 2012: 10-14 • Cost and schedule 2017: 15-17 17/12/2019 Waimea Water Ltd 2

  3. Waimea Dam is underway and progressing well Ground Breaking Ceremony 9 August 2019 17/12/2019 Waimea Water Ltd 3

  4. Design Update • Rezoning : Flexibility / robustness to geology • Spillway : De-risk construction, topography • Plinth : Optimised. Updated grout curtain 2009: 5-9 • Membrane : Enhance resilience. Savings 2012: 10-14 2017: 15-17 • MechElect : Progressing optimised design. • Bridges : Remove upper-spillway. Savings 17/12/2019 Waimea Water Ltd 4

  5. Design: Rezoning embankment to manage geology ❖ Expect less harder class-1 material ❖ Experiencing more fines  Increase drainage layers with  Processed (screened) out fines 2009: 5-9 2012: 10-14 2017: 15-17 17/12/2019 Waimea Water Ltd 5

  6. Design: Geosynthetic membrane Considering replacing concrete face with Geosynthetic membrane  Improved resilience to settlement and seismic (elasticity)  Cost and schedule savings  CO2 reductions 2009: 5-9 2012: 10-14  Performance warranty 2017: 15-17 Carpi Ltd: Installed • 54 New Dams since 1988 (26 larger than Waimea) • 142 Retrofitted Dams since 1970 (63 since 2010) 17/12/2019 Waimea Water Ltd 6

  7. Design: Mechanical design completed • Low and mid-level GRP draw off  Water quality and temp control • Single pipe through 160 m culvert • 3 nozzles at outlet 2009: 5-9  Environmental to flushing flows 2012: 10-14 2017: 15-17 • Powergen compatible 17/12/2019 Waimea Water Ltd 7

  8. Construction: Proceeding as planned 17/12/2019 Waimea Water Ltd 8

  9. Construction: Culvert Construction ▪ ~80/160m of culvert cut excavated and pouring blinding concrete poured to 60/160m ▪ Construction of 160m long 5x4m culvert commenced Nov-2019. Poured 2 X 10m floor sections ▪ Divert river May-2020. Exploring options to expedite 17/12/2019 Waimea Water Ltd 9

  10. Construction: Preparing for LHS Plinth. As expected 17/12/2019 Waimea Water Ltd 10

  11. Construction: Clearing RHS Abutment. As expected 17/12/2019 Waimea Water Ltd 11

  12. Construction: Permanent Slope Protection progressing 17/12/2019 Waimea Water Ltd 12

  13. Construction: Flood risk is very real 2 December: 102 m3/s (1:50 = 250 m3/s; 12 May 2019) • Temporary works designed to overtop Flood Level ➢ Cofferdam protecting embankment ➢ Downstream reinforced mesh dam • Expect >8 flood events 02/12/2019 Waimea Water Ltd 13

  14. Environment and Sustainability • 164 Resource Consent conditions; Working 99 action items • Biodiversity Management Plan approved with 8 plans. BTAG Onsite • 7/9 SCEMPS approved, implemented and being monitored • 6 Sediment Retention Ponds & 7 Decanting Bunds operating • Hydroseeding & mulching mitigates erosion and sedimentation • Fortnightly independent water quality monitoring complies • Continuous turbidity monitors guides river works • 3/4 rare plant species removed for propagation (BMP #2) Offsite • Ordered 11,000 plants and weed control for Rough Island 17/12/2019 Waimea Water Ltd 14

  15. ~ 2months behind; seeking opportunities to recover 17/12/2019 Waimea Water Ltd 15

  16. Funding and expenditure Funding and Spend Forecast cost & schedule to complete $6m behind $6m behind Spent $32m Spent $32m 17/12/2019 Waimea Water Ltd 16

  17. Managing key risks Risk Management: 22% of Project Budget at Risk Risk Heat Map Threat Very Low Low Medium High Very High - 1 - - - Very High 1 3 3 6 - High Likelihood 1 4 6 3 1 Medium Low - 1 3 - - Very Low - - - 1 - Very Low Low Medium High Very High High Risks: Mitigating Actions: • ➢ Rezoning, trials, bores Rock fill into embankment • ➢ New grout & plinth design Grout subsurface • ➢ Spillway design Topography on Spillway • ➢ Assessing Slope stability • ➢ Optimising (1 pipe) M & E Design 17/12/2019 Waimea Water Ltd 17

  18. More Information 17/12/2019 Waimea Water Ltd 18

  19. Questions? ➢ ~ 2 months behind with late start: Pursuing opportunities to recover ➢ So far, have not encountered anything that exceeds funding envelope BUT (health warning) ➢ Early days, and significant geological and topographical risks exist ➢ Expect to have better understanding on cost & schedule mid-2020 Waimea Water Ltd 17/12/2019 Waimea Water Ltd 19

  20. Design: Highest category (NZSOLD / ANCOLD / ICOLD) ▪ Concrete Faced Rockfill Dam; most robust to seismic loads and uses indigenous material 13 Mm 3 (13 billion litre) reservoir; 53m high; 220m crest length; 430,000 m 3 rock ▪ ▪ Earthquake: Operating basis 1:150 AEP (years); Seismic evaluation basis 1:10,000 AEP (years) ▪ Flood: Probable max: 1094 m3/s (100 yr 375 m3/s). 12 May 2019 1:50 year 250 m3/s (47 mm/hr) Turitea Concrete Faced Rockfill dam. Palmerston North 3-D model overlaying existing site topography Constructed 1907, 1912, 1996 17/12/2019 Waimea Water Ltd 20

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend