Waimea Community Dam Update
17 December 2019
Waimea Water
Waimea Water Ltd 17/12/2019 1
Update 17 December 2019 Waimea Water 17/12/2019 Waimea Water Ltd - - PowerPoint PPT Presentation
Waimea Community Dam Update 17 December 2019 Waimea Water 17/12/2019 Waimea Water Ltd 1 Agenda Design Construction Environmental 2009: 5-9 2012: 10-14 Cost and schedule 2017: 15-17 17/12/2019 Waimea Water Ltd 2 Waimea
Waimea Water Ltd 17/12/2019 1
Waimea Water Ltd 2
2009: 5-9 2012: 10-14 2017: 15-17
17/12/2019
Ground Breaking Ceremony 9 August 2019
Waimea Water Ltd 3 17/12/2019
Waimea Water Ltd 4
2009: 5-9 2012: 10-14 2017: 15-17
17/12/2019
❖ Expect less harder class-1 material ❖ Experiencing more fines Increase drainage layers with Processed (screened) out fines
Waimea Water Ltd 5
2009: 5-9 2012: 10-14 2017: 15-17
17/12/2019
Considering replacing concrete face with Geosynthetic membrane Improved resilience to settlement and seismic (elasticity) Cost and schedule savings CO2 reductions Performance warranty Carpi Ltd: Installed
Waimea Water Ltd 6
2009: 5-9 2012: 10-14 2017: 15-17
17/12/2019
Water quality and temp control
Environmental to flushing flows
Waimea Water Ltd 7
2009: 5-9 2012: 10-14 2017: 15-17
17/12/2019
Waimea Water Ltd 8 17/12/2019
▪ ~80/160m of culvert cut excavated and pouring blinding concrete poured to 60/160m ▪ Construction of 160m long 5x4m culvert commenced Nov-2019. Poured 2 X 10m floor sections ▪ Divert river May-2020. Exploring options to expedite
Waimea Water Ltd 9 17/12/2019
Waimea Water Ltd 10 17/12/2019
Waimea Water Ltd 11 17/12/2019
Waimea Water Ltd 12 17/12/2019
Waimea Water Ltd 13 02/12/2019
Flood Level
2 December: 102 m3/s (1:50 = 250 m3/s; 12 May 2019)
➢Cofferdam protecting embankment ➢Downstream reinforced mesh dam
Onsite
Offsite
Waimea Water Ltd 14 17/12/2019
Waimea Water Ltd 15 17/12/2019
Waimea Water Ltd 16
Funding and Spend Forecast cost & schedule to complete Spent $32m $6m behind Spent $32m $6m behind
17/12/2019
Waimea Water Ltd 17
Risk Management: 22% of Project Budget at Risk
Risk Heat Map
High Risks:
1 3 3 6 -
Medium1 4 6 3 1
LowThreat Likelihood
Mitigating Actions: ➢ Rezoning, trials, bores ➢ New grout & plinth design ➢ Spillway design ➢ Assessing ➢ Optimising (1 pipe)
17/12/2019
Waimea Water Ltd 18 17/12/2019
Waimea Water Ltd
Waimea Water Ltd 19
➢ ~ 2 months behind with late start: Pursuing opportunities to recover ➢ So far, have not encountered anything that exceeds funding envelope
➢ Early days, and significant geological and topographical risks exist ➢ Expect to have better understanding on cost & schedule mid-2020
17/12/2019
▪ Concrete Faced Rockfill Dam; most robust to seismic loads and uses indigenous material ▪ 13 Mm3 (13 billion litre) reservoir; 53m high; 220m crest length; 430,000 m3 rock ▪ Earthquake: Operating basis 1:150 AEP (years); Seismic evaluation basis 1:10,000 AEP (years) ▪ Flood: Probable max: 1094 m3/s (100 yr 375 m3/s). 12 May 2019 1:50 year 250 m3/s (47 mm/hr)
Waimea Water Ltd 20
Turitea Concrete Faced Rockfill dam. Palmerston North Constructed 1907, 1912, 1996 3-D model overlaying existing site topography
17/12/2019