tdc council
play

TDC Council 25 June 2020 Waimea Water 25/06/2020 Waimea Water Ltd - PowerPoint PPT Presentation

Waimea Community Dam TDC Council 25 June 2020 Waimea Water 25/06/2020 Waimea Water Ltd 1 Agenda 1. Covid-19 impact 2. Funding and expenditure 3. Expenditure and progress 4. Safety 5. Environmental 6. Rockfill: The geology challenge 7.


  1. Waimea Community Dam TDC Council 25 June 2020 Waimea Water 25/06/2020 Waimea Water Ltd 1

  2. Agenda 1. Covid-19 impact 2. Funding and expenditure 3. Expenditure and progress 4. Safety 5. Environmental 6. Rockfill: The geology challenge 7. Design update 8. Construction update (video) 9. Questions 25/06/2020 Waimea Water Ltd 2

  3. Meet the WWL Team • Designer (PS-1, PS-4) Damwatch Engineering • Reviewer (PS-2) GHD Engineering • Engineer to Contract Stantec • Contractor (PS-3) Fulton Hogan Taylors • Quantity Surveyor Rawlinsons • Contract Law Anderson Lloyd • Programme CCCL • Safety Impac; Intesafety • Accountant Findex • Banker ANZ • Auditor Audit NZ 25/06/2020 Waimea Water Ltd 3

  4. COVID-19 ❖ WWL incurs cost of 5-week Suspension and further delay (no Force Majeure provision in NZ3910) ➢ Further week delay to remobilize and implement facilities ➢ Not covered by insurance ❖ Productivity impacted on resumption with level-3 / level-2 protocols ➢ NZ Construction Industry Standards ❖ Supply chain constrained and likely to slow project: Spares, parts, equipment ➢ Uncertain how international supply chain recovers ❖ Cost of suspension and recovery to yet be determined ➢ Looking to NZ Construction Industry. No precedents ➢ Impact of COVID-19 to be determined during 2020/21 year per Final SOI 25/06/2020 Waimea Water Ltd 4

  5. Funding and expenditure: 31 May 2020 Funding and Spend Forecast cost & schedule to complete 140 $129.4m Excludes Cost of COVID-19 120 August 2021 100 80 $ millions July 2020 60 $50.2m 40 20 - Dec-2018 Dec-2019 Dec-2020 Dec-2021 Budget New forecast (SoI) Actual 25/06/2020 Waimea Water Ltd 5

  6. Expenditure and progress Progress 16 months Months 37mths 40mths Excludes Cost of COVID-19 $ $50m Expenditure $104.4m $129.4m 0% 25% 50% 75% 100% ECI Costs During Construction Construction Variations Remain Original Budget Revised Forecast 25/06/2020 Waimea Water Ltd 6

  7. Context (SOI) Excludes Cost of COVID-19 25/06/2020 Waimea Water Ltd 7

  8. Programme: + 6 months = +1 season ❖ Currently expect 6 month delay to programme with further risk of slippage ❖ Exploring and pursuing recovery programme (shift work; defer works) 21/04/2020 Waimea Water Ltd 8

  9. Safety: No injuries to date Leading: Contractor Audit and Inspection 35 30 25 20 15 10 5 0 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Lead OFI Low Potential Med Potential High Potential Lagging: Accidents, Harm, HPI 5 1 LTI Number of incidents Incident Frequency ratios LTIFR / MTIFR / TRIFR 4 MTI 3 FAI HPI 2 Celebrating 500 days injury free MTIFR 1 TRIFR 0 0 25/06/2020 Waimea Water Ltd 9

  10. Environmental: Full compliance with consent Lead: Audit, Inspection and Water Quality monitoring 14 12 No. Audits per month 10 8 6 4 2 0 Apr-19 May-19 Jun-19 Jul-19 Aug-19 Sep-19 Oct-19 Nov-19 Dec-19 Jan-20 Feb-20 Mar-20 Apr-20 May-20 Jun-20 TDC Compliance Contractor Weekly Audit Contractor Monthly Audit FHTJV HO Env Visit Environmental Control Inspection Environmental Follow Up Audit Southern Skies ESC Inspection SLR Water Quality Visit #42 River Health Indicator: Quantitative Macroinvertebrate Community Index 8.5 • Approved 5 Environmental Management Plans QMCI Index (clipped to show QMCI Upstream 8 ✓ Verified 7.5 QMCI Downstream detail) 7 • Approved 9 SCEMPs 6.5 20% below average ✓ Verified pre-construction 6 U/S QMCI 5.5 Pre- Construction During Construction  All required plans for current works in place, 5 6/03/2017 22/09/2017 10/04/2018 27/10/2018 15/05/2019 1/12/2019 certified, verified and functioning 25/06/2020 Waimea Water Ltd 10

  11. Environmental: Full compliance with consent Independent ecologist #45 River Health Indicator: pH verifies river health indicators 12 10 8 pH Upstream pH 6 pH Downstream 4 Lower Limit 2 Upper Limit 0 #44 River Health Indicator: Deposited Fine Sediment 50 % of river bed with fine sediment 45 40 35 30 deposits 25 Upstream 20 Downstream 15 Downstream Threshold 10 5 0 25/06/2020 Waimea Water Ltd 11

  12. Rockfill: The Geology Challenge ▪ Embankment trials late December 2019 and early January 2020 identified Rock degradation Discovered Expected and Needed Heavily broken down – Not free draining Less broken down – Free draining 25/06/2020 Waimea Water Ltd 12

  13. Rockfill: The Geology Challenge ▪ Discovering more argillite (mud / siltstone) (~70%) and less greywacke (sandstone) than expected ▪ Greywacke (sandstone) dispersed amongst predominant argillite. Difficult to salvage. (VIDEO) ▪ Fissile argillite showing tendency to break along insipient foliations ➢ Spillway Excavation: “May yield a minimum of 350,000 m3 of rock that will consist of slightly weathered to weathered (Class 1 & 2) greywacke.” (2014). Predominantly fissile argillite ➢ Need to find suitable drainage material from alternative sources (cost) 25/06/2020 Waimea Water Ltd 13

  14. Design: Rezoning embankment to manage geology ❖ Expect less harder class-1 material ❖ Testing in early 2020 identified breakdown on compaction  Increase drainage layers Free Draining  Alternatively source drainage rock Not Free Draining Drainage 25/06/2020 Waimea Water Ltd 14

  15. Design: Spillway modified for improved resilience Design modifications due to recent learnings from international spillway incidents (international standards)  Oroville (right) failure due to poor drainage and anchoring detailing (pressure beneath fn velocity)  Whaley Bridge (UK) no drainage and poor slab detailing combined with poor maintenance 2009: 5-9 Modifications for resilience (requested by CIIL): 2012: 10-14  Drainage reviewed and upgraded 2017: 15-17  Anchoring design reviewed and upgraded Additional modifications driven by topography and encountered geology. 25/06/2020 Waimea Water Ltd 15

  16. Design Update ✓ Spillway: ▪ Redesigned with vertical walls to mitigate topography / geology risks RHS ▪ Increased drainage per recent standard ▪ Completed and peer reviewed 25/06/2020 Waimea Water Ltd 16

  17. Design Update: Other items Mechanical and Electrical ❖ Not designed or priced at commencement of work  Provision Sum challenged  To be priced ~3 rd Quarter 2020 2009: 5-9 2012: 10-14 ▪ Progressing detailed design 2017: 15-17  Switch to single outlet pipe aiming to realise cost savings  Modifications for future hydropower installation 25/06/2020 Waimea Water Ltd 17

  18. Power Generation: Opportunity Enlarge Reservoir / Powergen ▪ Fuse Gate to utilise 2.3m / 5m of flood reservoir ▪ Activate in event of large flood say 1:10,000 yr AEP (55% - 70% of PMF 1094 m3/s) + 1.5Mm 3 storage to ~15Mm 3 (15%) ▪  Storage increases powergen utilisation  Increase resilience to droughts / growth / demand 25/06/2020 Waimea Water Ltd 18

  19. Agenda 1. Covid-19 impact 2. Funding and expenditure 3. Expenditure and progress 4. Safety 5. Environmental 6. Rockfill: The geology challenge 7. Design update 8. Construction update (video) 9. Questions 25/06/2020 Waimea Water Ltd 19

  20. Construction Update RHS Plinth Spillway Culvert LHS Plinth 25/06/2020 Waimea Water Ltd 20

  21. Diversion Culvert: ~80% complete ✓ Completed Floor ✓ 12/17 wall & roof sections completed ➢ Expect to complete by Aug and divert river September 2020 25/06/2020 Waimea Water Ltd 21

  22. Construction Update: Forming LHS Plinth ✓ Foundation treated and site blinding concrete complete ✓ Commenced forming plinth 25/06/2020 Waimea Water Ltd 22

  23. Construction Update: Preparing RHS Plinth ✓ Foundation treatment and treatment underway 25/06/2020 Waimea Water Ltd 23

  24. Construction Update: Spillway ▪ Spillway cut underway ➢ Exposed first 20 m section of foundation ❖ Uncovering significantly weathered foundation that will require treatment ▪ Close to cliff edge ✓ Supports change in design to self-supporting vertical walls, rather than a liner ▪ Will evaluate extent of any edge support 25/06/2020 Waimea Water Ltd 24

  25. Construction Issues: Unexpected Voids ❖ >1000 m3 concrete ✓ LHS & Culvert done ❖ RHS, Spillway and starter dam to do 21/04/2020 Waimea Water Ltd 25

  26. Closing: By the numbers Task Total Quantity Unit Vegetation Clearance 85 Hectare m 3 Excavation 633,000 m 3 Fill 430,000 m 3 Cut to Waste 311,000 m 3 Material Processing 120,000 m 3 Concrete 22,000 Reo Steel (bars) 3,900 t m 2 Reo Steel (mesh) 10,000 Anchors 4,200 No. m 2 Concrete Face 10,000 25/06/2020 Waimea Water Ltd 26

  27. More Information 25/06/2020 Waimea Water Ltd 27

  28. 17 Dec 2019: Rezoning embankment to manage geology ❖ Expect less harder class-1 material ❖ Experiencing more fines  Increase drainage layers with  Processed (screened) out fines 2009: 5-9 2012: 10-14 2017: 15-17 02/12/2019 Waimea Water Ltd 28

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend