US 150 Eastbound (McClugage Bridge) over the Illinois River PRE-BID - - PowerPoint PPT Presentation

us 150 eastbound mcclugage bridge over the illinois river
SMART_READER_LITE
LIVE PREVIEW

US 150 Eastbound (McClugage Bridge) over the Illinois River PRE-BID - - PowerPoint PPT Presentation

US 150 Eastbound (McClugage Bridge) over the Illinois River PRE-BID MEETING www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project Meeting Agenda Introduction US 150 Corridor Construction Sequence Permits


slide-1
SLIDE 1

www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

US 150 Eastbound (McClugage Bridge)

  • ver the Illinois River

PRE-BID MEETING

slide-2
SLIDE 2

www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

Meeting Agenda

  • Introduction
  • US 150 Corridor
  • Construction Sequence
  • Permits
  • Commitments
  • Environmental Key Elements
  • Additional Key Elements
  • Questions/Discussion
slide-3
SLIDE 3

www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

Project Aerial Photo

Eastbound US 150 – 1.55 mi. IL Route 29 - 0.24 mi. SB IL 116/US 24 - 0.59 mi

slide-4
SLIDE 4

www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

Construction Sequence – July 2019 thru March 2020

Earthwork/Route 29 Bridge Half Construction Foundations, Piers Earthwork EB US150 and SW Ramp Pavement Widening

slide-5
SLIDE 5

www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

Construction Sequence – April 2020 thru March 2021

No Work * Foundations, Piers No Work * No Work * Earthwork

* No Lane Closures or Lane Reductions April 1 thru November 30

slide-6
SLIDE 6

www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

Construction Sequence – April 2021 thru March 2022

Interchange Ramp E Approach Span and Main Span Construction New Ramp Paving Finalize Work Mainline Paving

slide-7
SLIDE 7

www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

Construction Sequence – April 2022 thru March 2023

Final Interchange Construction IL 29 Bridge Remaining Construction Traffic on New Bridge (April 1, 2022) – *Begin Bridge Removal Final Ramp Construction Work Complete

*Final Bridge Removal and Project Restoration March 31, 2023 Completion

slide-8
SLIDE 8

www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

Construction Key Items

  • Summer 2019 Start
  • Approximate 3-3/4 year schedule
  • Completion Date – March 31, 2023
  • No lane closures or lane reductions in

2020

  • Cooperation with other contracts
slide-9
SLIDE 9

www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

Construction Key Items

Cooperation with other contracts

Contract 68D85 (Bridge Deck Rehab) Contract 68D22 (Resurface) Contract 89723 (RR Bridge Rehab)

slide-10
SLIDE 10

www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

Permits

  • IDNR Permit
  • IL EPA 401 Water Quality Permit
  • ACOE 404/Section 10 and 408 Permit
  • US Coast Guard Section 9 Permit
  • RELATED ITEMS

– Removal and Disposal of Regulated Substances – River Sediment Management – Wetlands

slide-11
SLIDE 11

www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

Permits

  • IDNR Permit

– Approved based on determination that the project will neither restrict the river’s flood carrying capacity nor adversely impact the public’s interests in the public body of water. – One special condition: bridge removal shall be conducted such that it will not unnecessarily interfere with navigation or create a hazard to boating safety.

slide-12
SLIDE 12

www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

Permits

  • IL EPA 401 Water Quality Certification

Condition

– Maintain water quality standards, prevent water pollution, prevent excavated or dredged material from returning back to the waterway

  • r beneath normal flooding levels, implement

BMPs and erosion control measures both on land and in the river such as using floating silt curtains.

slide-13
SLIDE 13

www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

Permits

  • ACOE 404/Section 10 and 408 Permit

Conditions

– Consultation with IDNR on potential impacts to listed species and aquatic habitat once the method of bridge demolition is selected – Notify the Corps Illinois Waterway Project Office 72 hours prior to the commencement of work – Procedures to follow for unanticipated discoveries of historic, archaeological, or human remains during construction.

slide-14
SLIDE 14

www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

Permits

  • US Coast Guard Section 9 Permit

– No falsework will be used in the navigation channel and no more than 48 hours will be allowed for navigational channel closures; – In order to facilitate times needed for a temporary navigation construction clearance of 315 feet, a tug with a minimum 1200 horsepower will be provided to assist vessels through the bridge

  • n demand.

– The existing piers will be removed to at least two feet below existing ground, with the exception of the piers adjacent to the nav channel, which will be removed to 12 feet below normal pool elevation. – Any material accidently falling into the river will be removed and disposed out of the waterway.

slide-15
SLIDE 15

www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

Related Items

  • Removal and Disposal of Regulated Substances

– Areas listed in the plans and specifications shall be managed as specified.

  • River Sediment Management

– Because the depth of the Illinois River is shallow, a temporary causeway and/or dredging of the river sediment, or other access measures, may be required to allow access to construct the

  • bridge. The means and methods are up to the contractor, but a

dredging and causeway construction has been estimated for the permit applications. – If dredging is proposed, the method is assumed to be by mechanical removal. Placement locations are assumed to be either certified disposal locations, as specified in the specifications, or possible upland beneficial re-use areas, which would need to be approved by the Department and Illinois EPA.

slide-16
SLIDE 16

www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

Related Items

Wetlands

Sites 7, 8 and 11 have been delineated

slide-17
SLIDE 17

www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

Commitments

  • Tri County Search and Rescue – River

Access

Peoria County Tazewell County

slide-18
SLIDE 18

www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

Commitments

Illinois American Water Co.

– Sludge and Potable Water Pipelines

slide-19
SLIDE 19

www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

Commitments

Lorentz Avenue Pleasure Parkway

slide-20
SLIDE 20

www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

Environmental Key Elements

  • Endangered Species Protection (Decurrent

False Aster)

slide-21
SLIDE 21

www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

Environmental Key Elements

  • Falcon Protective Netting
slide-22
SLIDE 22

www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

Additional Key Elements

  • Contractor Staging Area
slide-23
SLIDE 23

www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project

Additional Key Elements

Parking Lots and Parks

Peoria County Tazewell County

slide-24
SLIDE 24

US 150 McClugage Bridge Project

Thank You

Questions/Discussion