www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
US 150 Eastbound (McClugage Bridge)
- ver the Illinois River
US 150 Eastbound (McClugage Bridge) over the Illinois River PRE-BID - - PowerPoint PPT Presentation
US 150 Eastbound (McClugage Bridge) over the Illinois River PRE-BID MEETING www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project Meeting Agenda Introduction US 150 Corridor Construction Sequence Permits
www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
Eastbound US 150 – 1.55 mi. IL Route 29 - 0.24 mi. SB IL 116/US 24 - 0.59 mi
www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
Earthwork/Route 29 Bridge Half Construction Foundations, Piers Earthwork EB US150 and SW Ramp Pavement Widening
www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
No Work * Foundations, Piers No Work * No Work * Earthwork
* No Lane Closures or Lane Reductions April 1 thru November 30
www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
Interchange Ramp E Approach Span and Main Span Construction New Ramp Paving Finalize Work Mainline Paving
www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
Final Interchange Construction IL 29 Bridge Remaining Construction Traffic on New Bridge (April 1, 2022) – *Begin Bridge Removal Final Ramp Construction Work Complete
*Final Bridge Removal and Project Restoration March 31, 2023 Completion
www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
Contract 68D85 (Bridge Deck Rehab) Contract 68D22 (Resurface) Contract 89723 (RR Bridge Rehab)
www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
– No falsework will be used in the navigation channel and no more than 48 hours will be allowed for navigational channel closures; – In order to facilitate times needed for a temporary navigation construction clearance of 315 feet, a tug with a minimum 1200 horsepower will be provided to assist vessels through the bridge
– The existing piers will be removed to at least two feet below existing ground, with the exception of the piers adjacent to the nav channel, which will be removed to 12 feet below normal pool elevation. – Any material accidently falling into the river will be removed and disposed out of the waterway.
www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
– Areas listed in the plans and specifications shall be managed as specified.
– Because the depth of the Illinois River is shallow, a temporary causeway and/or dredging of the river sediment, or other access measures, may be required to allow access to construct the
dredging and causeway construction has been estimated for the permit applications. – If dredging is proposed, the method is assumed to be by mechanical removal. Placement locations are assumed to be either certified disposal locations, as specified in the specifications, or possible upland beneficial re-use areas, which would need to be approved by the Department and Illinois EPA.
www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
Sites 7, 8 and 11 have been delineated
www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
www.mcclugagebridgeproject.com/ US 150 McClugage Bridge Project
US 150 McClugage Bridge Project