Clinton Street Bridge over the Maumee River ODOT Project DEF-15-14.77 September 13, 2016 Public Meeting Purpose of Public Meeting Review project and developments since the last public meeting in May 2015 Discuss how traffic should be


slide-1
SLIDE 1

Clinton Street Bridge over the Maumee River

ODOT Project DEF-15-14.77 September 13, 2016 Public Meeting

slide-2
SLIDE 2

 Review project and developments since the last public meeting in May 2015  Discuss how traffic should be maintained during construction  Identify concerns and get public comments

Purpose of Public Meeting

slide-3
SLIDE 3

 Replace the deteriorated bridge  Improve pedestrian access and bicycle accommodations

Project Purpose

slide-4
SLIDE 4

Deteriorated condition of existing bridge

slide-5
SLIDE 5

Improve Pedestrian Access

slide-6
SLIDE 6

Improve Bicycle Accommodations

slide-7
SLIDE 7

Connectivity with Local Bike Plans

slide-8
SLIDE 8

 Bridge cross section view

Proposed Clinton Street Bridge Section

slide-9
SLIDE 9

 ODOT, the City of Defiance and Burgess & Niple have worked together to choose bridge aesthetics

 Funding will be a combination of ODOT bridge funding, ODOT Transportation Alternatives Program funds, and contributions from the City of Defiance.  Plans includes lighting, decorative piers and railing, and lookouts

Bridge Aesthetics (How the new bridge will look)

slide-10
SLIDE 10

Proposed Clinton Street Bridge

slide-11
SLIDE 11

Proposed Clinton Street Bridge

slide-12
SLIDE 12

Proposed Clinton Street Bridge

slide-13
SLIDE 13

Two options:  Full Closure - Bridge can be closed during construction and traffic can utilize other river crossings  Part-width - Traffic can cross the bridge using one lane of traffic in each direction while the other half of the bridge is being constructed.

Options for Maintaining Traffic During Construction

slide-14
SLIDE 14

 Full Closure – Faster construction

 Allows work to happen on the entire bridge at one time.

 Part- width – Slower construction

 Requires the bridge to be built in two separate halves at two separate times and then connected.

Speed of Construction

slide-15
SLIDE 15

 Full Closure – Detour required

 Traffic will not be able to cross bridge

 Part-width - No detour required

 Traffic will be able to cross the bridge with one lane in each direction for the duration of the project

Detour

slide-16
SLIDE 16

 Full Closure

 No plans to maintain access across the river

 Part - width

 One sidewalk (minimum 5 feet wide) will remain available to cross river

Pedestrian/Bicycle Access

slide-17
SLIDE 17

 Full Closure

 Safety services utilize other crossings  Hospitals on both sides of Maumee River

 Part - width

 Safety services can cross bridge

Safety Service & Hospital Access

slide-18
SLIDE 18

 Full Closure

 Traffic cannot cross the bridge  Less downtown traffic  Traffic management plan to be developed with City

 Part - width

 Traffic can cross the bridge but with fewer lanes  More downtown congestion and delays possible  Traffic management plan to be developed with City

Traffic Impacts Downtown

slide-19
SLIDE 19

 Full Closure

 Traffic wanting to cross river will use SR 281 and US 24 river crossings  State route traffic will have a signed detour

 Part - width

 Traffic can cross the bridge but with fewer lanes  Some traffic will choose to use other crossings

Traffic Impacts on Other Roadways

slide-20
SLIDE 20

Traffic Impacts

slide-21
SLIDE 21

 Full Closure

 Less temporary right-of-way required

 Part - width

 More temporary right-of-way required

R/W Impacts

slide-22
SLIDE 22

 Full Closure

 College – Students south of bridge need to detour to get to campus  City Schools – Bus routes need to change to account for detour

 Part - width

 College – Students south of bridge can still cross river on Clinton Street to get to campus  City Schools – Bus routes can stay the same

Defiance College and Defiance City Schools

slide-23
SLIDE 23

 Construction in 2019  Right-of-way acquisition anticipated to begin in 2017  Project schedule updates will be provided as changes in the schedule are known

Current Project Schedule

slide-24
SLIDE 24

 Written comments due October 13, 2016  Decision on what to do with traffic during construction: October 20, 2016  Decision announced through media and website

Next Steps

slide-25
SLIDE 25

 Comments, concerns, or any information you can provide are appreciated!  Comments after the meeting should go to:

 Jenn Gasser, ODOT District 1, (419) 999-6871, jennifer.gasser@dot.ohio.gov or  Jeff Griffin, Burgess & Niple, (614) 459-2050, jeff.griffin@burgessniple.com

 Future project information – go to District 1 website, Construction Projects & click on DEF SR 15 Clinton Street Bridge www.transportation.ohio.gov/dist1

Public Meeting Concerns/Input