Clinton Street Bridge over the Maumee River ODOT Project - - PowerPoint PPT Presentation

clinton street bridge over the maumee river
SMART_READER_LITE
LIVE PREVIEW

Clinton Street Bridge over the Maumee River ODOT Project - - PowerPoint PPT Presentation

Clinton Street Bridge over the Maumee River ODOT Project DEF-15-14.77 December 2, 2014 Stakeholders Meeting Purpose of Stakeholder Meeting Discuss the project and why its happening Describe the process thats used to determine


slide-1
SLIDE 1

Clinton Street Bridge over the Maumee River

ODOT Project DEF-15-14.77 December 2, 2014 Stakeholder’s Meeting

slide-2
SLIDE 2

 Discuss the project and why it’s happening  Describe the process that’s used to determine what gets built  Share factors that will influence the proposed design  Identify stakeholder concerns  Obtain stakeholder input

Purpose of Stakeholder Meeting

slide-3
SLIDE 3

 Address deteriorated condition of existing bridge  Existing bridge is safe, but has some things that need addressed as part of this project  Existing bridge deck (what traffic travels on) and superstructure (what supports the deck) have deteriorated  Existing abutments (ends of the bridge) and piers (middle sections of the bridge) support the superstructure and have also deteriorated to varying degrees

Project Purpose

slide-4
SLIDE 4

Existing Bridge Deck – North End

Cracked asphalt is porous. Deicing chemicals leak through to whatever is below it.

slide-5
SLIDE 5

Existing Bridge Deck – South End

Holes in asphalt at south end of bridge.

slide-6
SLIDE 6

Underside of Existing Bridge Superstructure (at curb line)

Note concrete cracking. This is caused by reinforcing steel and prestressing strands that are corroding.

slide-7
SLIDE 7

Underside of Existing Superstructure (End Span, South End)

Eventually the concrete breaks away completely, exposing the corroded strands, which can then fail and break away themselves.

slide-8
SLIDE 8

Underside of Existing Superstructure (Mid Span)

Another failed strand towards the middle of the bridge

slide-9
SLIDE 9

Underside of Existing Bridge Superstructure (End Span – North End)

Concrete has cracked and broken away at other bridge locations as

  • well. Cause for this cracking?

Same as other areas on bridge - reinforcing steel and strands that are corroding.

slide-10
SLIDE 10

South Abutment

Note deteriorated concrete. Caused by deicing chemical leakage from bridge deck.

slide-11
SLIDE 11

Existing Pier

Note concrete deterioration at sidewalk curb line.

slide-12
SLIDE 12

 Was originally built in 1932

 Six spans, total length approximately 489 feet

 Rehabilitated in 1980

 New superstructure  Existing piers and abutments remained and were repaired  48 feet face to face of curb (4-12 ft. lanes)  5 ft. 6 in. sidewalks

Existing Bridge

slide-13
SLIDE 13

 Includes the bridge and the next two intersections north and south of bridge

 Clinton Street intersections with High Street, River Drive, Fort Street and First Street

 Engineering and environmental studies are performed within the study area  Larger than the actual project work limits

 Why? Actual project work limits have not yet been determined.

Study Area

slide-14
SLIDE 14

Study Area (Yellow Outline)

slide-15
SLIDE 15

 Circle K Gas Station  Former gas tanks along Clinton Street  Pontiac and Fort Defiance Parks  Maumee River and mussels  Several structures over 50 years old (none eligible for the National Register of Historic Places)  One archaeological site (southwest corner; destroyed according to State Historic Preservation Office)

Environmental Concerns on the Project

slide-16
SLIDE 16

 Engineering and environmental studies are conducted to help determine feasible alternatives and pros/cons associated with them.  Alternative evaluation concludes with a Feasibility Study, which identifies a Preferred Alternative  Feasibility Study to be submitted to ODOT later this month

Alternatives Evaluation

slide-17
SLIDE 17

 New four lane bridge on existing piers (similar to existing bridge)  New five lane bridge on existing piers

 Allows southbound left turn from Clinton Street to River Drive.

 New four (or five) lane bridge on new piers  All alternatives have wider bridge sidewalks and dedicated bike lanes on bridge.

DEF-15-14.77 Alternatives

slide-18
SLIDE 18

Bridge Concept

Actual appearance to be determined later in design process

slide-19
SLIDE 19

 Construction cost  Traffic safety/congestion  Maintenance of traffic during construction  Environmental impacts  Adjacent property impacts (public and private)  Utility impacts  Future maintenance costs  Inspection of existing bridge piers in November 2014 will determine if their reuse is feasible and cost-effective

Factors Affecting Alternative Evaluation

slide-20
SLIDE 20

 Actual appearance of new bridge is determined in the next phase of design.  City preference is current bridge lighting  Existing pier reuse will affect aesthetics  Stakeholder and public comments will be considered when deciding how the new bridge will look.

Bridge Aesthetics (How bridge will look)

slide-21
SLIDE 21

Existing Bridge Lighting

slide-22
SLIDE 22

 Detrimental effects of traffic detours are understood.  Goal is to maintain at least local traffic during construction.  Local traffic – a trip that begins or ends in Defiance  How well the alternatives studied meet this goal will be part of the Feasibility Study.

Maintaining Traffic During Construction

slide-23
SLIDE 23

 Improve access to be consistent with Americans with Disabilities Act (ADA) guidelines  Improve pedestrian safety on bridge

 Current standards call for 8’- 0” minimum sidewalk width in commercial areas

 Incorporate bicycle accommodations into project design

 Proposing 5’- 0” dedicated bike lanes on bridge adjacent to each sidewalk

Other Project Goals

slide-24
SLIDE 24
slide-25
SLIDE 25

Existing Sidewalk and Curb Ramp – Southwest Corner

slide-26
SLIDE 26

Existing Sidewalk – Southeast Corner

slide-27
SLIDE 27

Existing Bridge – Not much room for bikes

slide-28
SLIDE 28

 Construction in 2019 (preliminary estimate)  Depends on funding, environmental concerns, right-

  • f-way acquisition, and completion of construction

plans  Project schedule updates will be provided as changes in the schedule are known.

Current Project Schedule

slide-29
SLIDE 29

 Funding will be secured when Preferred Alternative is known.  ODOT has several funding options.  Funds used will be suited to the type of project being constructed.  Right-of-way acquisition anticipated to begin in 2016

  • r 2017.

Project Funding

slide-30
SLIDE 30

 This meeting is the first in the public involvement process  Additional stakeholder meetings will be held  Public involvement meetings to be held as well  Comments, concerns, or any information you can provide are appreciated!

Stakeholder Concerns/Input

slide-31
SLIDE 31

 Comments after the meeting should go to:

 Jenn Gasser, ODOT District 1, (419) 999-6871, jennifer.gasser@dot.state.oh.us or  Jeff Griffin, Burgess & Niple, (614) 459-2050, jeff.griffin@burgessniple.com

 Future project information – go to District 1 website, Construction Projects & click on DEF SR 15 Clinton Street Bridge (http://www.dot.state.oh.us/districts/D01/PlanningProgra ms/Projects/defiance15/Pages/default.aspx)

Stakeholder Concerns/Input

slide-32
SLIDE 32

Study Area (Yellow Outline)