twi background current status summary january 2018 page 1
play

TWI Background & Current Status Summary January 2018 Page - 1 - PowerPoint PPT Presentation

CPAC Meeting Bay View WWTP January 22, 2018 TWI Background & Current Status Summary January 2018 Page - 1 4/27/2015 Toledo Waterways Initiative TWI Toledos Wet-Weather Program Federal consent decree mandate in 2002 Reduce


  1. CPAC Meeting Bay View WWTP January 22, 2018 TWI Background & Current Status Summary January 2018 Page - 1 4/27/2015

  2. Toledo Waterways Initiative – TWI Toledo’s Wet-Weather Program  Federal consent decree mandate in 2002  Reduce pollution impacts on area waterways from WWTP and sewers due to heavy rains  Three action components to complete by 2020:  Eliminate WWTP Bypasses  Eliminate Known Sanitary Sewer Discharges  Reduce and Control Combined Sewer Overflows B&V - 2 4/25/14

  3. TOLEDO WASTEWATER SYSTEM B&V | Harbron | Toledo's Wet Weather Treatment Facility | Lake Erie BAY VIEW WWTP • Service Population 320,000 • Service Area over 100 Sq. Miles • Combined Sewer Area (green) • Bay View WWTP

  4. TWI Component Approaches 1. Eliminate WWTP Bypasses Double capacity of plant to 400 mgd by building new wet weather treatment (WWT) facilities using HRC 2. Eliminate Known Sanitary Sewer Discharges Remove I&I, build relief sewers & build storage 3. Control Combined Sewer Overflows Develop & implement a CSO LTCP - I&I Removal, Sewer Separation, Regulator Improvements; & Pipeline, Tunnel and Basin Storage B&V - 4 4/25/14

  5. TWI Component Approaches 1. Eliminate WWTP Bypasses Double capacity of plant to 400 mgd by building new wet weather treatment (WWT) facilities B&V - 5 4/25/14

  6. 1. Eliminate WWTP Bypasses Wet Weather Treatment Facilities at Bay View Page - 6

  7. 1. Eliminate WWTP Bypasses High Rate Clarification (HRC) and EQ Basin Page - 7

  8. 1. Eliminate WWTP Bypasses High Rate Clarification (HRC) Facility Page - 8 February 29, 2008

  9. 1. Eliminate WWTP Bypasses HRC Piping Gallery & Sludge Pumps Page - 9 February 29, 2008

  10. 1. Eliminate WWTP Bypasses So where are we at today!  12 projects at a cost of $135 M  Done! Zero bypasses since October 2006.  144 MG/year in average year - eliminated  Wet weather facilities are used 4-8 times/year  With 25 MG of storage provided, HRC discharges only 1-3 times/year B&V - 10 4/25/14

  11. TWI Component Approaches 2. Eliminate Known Sanitary Sewer Discharges Remove I&I, build relief sewers & build storage B&V - 11 4/25/14

  12. TOLEDO WASTEWATER SYSTEM B&V | Harbron | Toledo's Wet Weather Treatment Facility | Lake Erie BAY VIEW WWTP • Service Population 320,000 • Service Area over 100 Sq. Miles • Combined Sewer Area (green) • Bay View WWTP

  13. 2. Eliminate Sanitary Sewer Discharges Eliminated 10 SSDs to date: • Point Place (3) • River Road (3) • Detroit Avenue (1) • Wyndhurst (1) • Parkside (1) • Fernhill (1)

  14. 2. Eliminate Sanitary Sewer Discharges Point Place SSD Elimination

  15. 2. Eliminate Sanitary Sewer Discharges Where are we today?  8 total projects at a cost of $71 M  3 basins built – 14 MG of storage  Brookford Park, Parkside & Detroit  Relief sewers and I&I removal  Original list of Ten eliminated 2014, 2 more ID’d  The last two Arlington & Heatherdowns - 2017  36 MG/year in average year – eliminated B&V - 15 4/25/14

  16. TWI Component Approaches 3. Control Combined Sewer Overflows Develop & implement a CSO LTCP - I&I Removal, Sewer Separation, Regulator Improvements; & Pipeline, Tunnel and Basin Storage B&V - 16 4/25/14

  17. 3. Control Combined Sewer Overflows CSO Long Term Control Plan - LTCP  Goals & Targets  Reduce Overflow Locations from 32 to 24  Reduce Annual Overflow Frequencies from 30+ to under 4  Reduce Overflow Volumes by 77%  Reduce Pollutant Discharges by 89%  Improve Water Quality & Preserve Resource for Future Generations B&V - 17 July 18-20

  18. 3. Control Combined Sewer Overflows LTCP Progress Status Summary – Jan 2018 Page - 18 4/27/2015

  19. 3. Control Combined Sewer Overflows Map of TWI CSO Projects in Construction Ottawa River Storage Facility Swan Creek North Sewer Separation Downtown Storage Basin International Park Storage Basin Page - 19 4/27/2015

  20. 3. Control Combined Sewer Overflows Project Highlight : Ottawa River Storage Facility (ORSF) • Our largest single TWI project @ $70 M • Located in Joe E. Brown Park • 36 MG of underground storage • 212 MGD capacity influent pumping station • 450,000 cubic yards of excavation • 50,000 cubic yards of concrete

  21. Ottawa River Storage Facility Underground Basin & Pumping Station Exposed

  22. Ottawa River Storage Facility Pumping Station Section View

  23. Ottawa River Storage Facility – DEC 2015 North End Basin Mass Excavation – Cells 2 and 1 Page - 23 4/27/15

  24. Ottawa River Storage Facility – JUL 2016 Left - Basin Top Deck Complete Middle - Under Construction Right - Open Basin to Bottom Slab Page - 24 4/27/15

  25. Ottawa River Storage Facility – JUL 2016 Basin Cell 2 and Cell 1 & PS Far Right Page - 25 4/27/15

  26. Ottawa River Storage Facility – Mar 2017 Basin Cell 1 Top Deck and Pumping Station Page - 26 4/27/15

  27. Ottawa River Storage Facility – May 2017 Pumping Station Block Walls – View NW Page - 27 4/27/15

  28. Ottawa River Storage Facility – May 2017 Pumping Station South Wall Page - 28 4/27/15

  29. Ottawa River Storage Facility – August 2017 Influent Pumping Station Page - 29 4/27/15

  30. Ottawa River Storage Facility – November 2017 Interceptor Relief Pipe to Pump Station Page - 30 4/27/15

  31. Ottawa River Storage Facility Planned Park Restoration

  32. Ottawa River Storage Facility – September 2017 Sitework Progress – Tennis Courts Page - 32 4/27/15

  33. Ottawa River Storage Facility – September 2017 Sitework Progress – Playground Equipment Page - 33 4/27/15

  34. Ottawa River Storage Facility - November 2017 Site Restoration – New Trees along Manhattan Page - 34 4/27/15

  35. Ottawa River Storage Facility - November 2017 Parking Lot Restoration – Manhattan & Franklin Page - 35 4/27/15

  36. International Park Storage Basin – December 2017 Tunnel Launch Shaft - Park Entrance Page - 36 4/27/15

  37. International Park Storage Basin – December 2017 Pouring Concrete - Basin Bottom Slab Page - 37 4/27/15

  38. International Park Storage Basin – December 2017 Formwork & Rebar – North End Deck Slab Page - 38 4/27/15

  39. International Park Storage Basin – December 2017 Sheeting Removal – North End of Basin Page - 39 4/27/15

  40. International Park Storage Basin – December 2017 84” Influent Pipe – East Side of Basin Page - 40 4/27/15

  41. International Park Storage Basin – December 2017 Sheeting Removal – Nevada Diversion Chamber Page - 41 4/27/15

  42. Downtown Storage Basin – December 2017 Crane Driving H-piles – West Side of Basin Page - 42 4/27/15

  43. Downtown Storage Basin – December 2017 Driving H-piles – South Side of Basin Page - 43 4/27/15

  44. Downtown Storage Basin – December 2017 Wood Lagging Shoring – North Side of Basin Page - 44 4/27/15

  45. Downtown Storage Basin – December 2017 Wood Lagging Shoring – East Side of Basin Page - 45 4/27/15

  46. Downtown Storage Basin – December 2017 Dewatering Well – South Side of Basin Page - 46 4/27/15

  47. Downtown Storage Basin – December 2017 Piezometer Installation for Tunnel – Water St. Page - 47 4/27/15

  48. 3. Control Combined Sewer Overflows Where are we today? CSO Storage in the System will be significant!  95 MG Combined Sewer System storage at completion  20 MG of tunnel storage completed in 1990s  15 MG of storage in 5 projects completed in last 5 years  36 MG of storage recently put-in-service – Ottawa (Joe E. Brown)  24 MG of storage in construction – Int’l Park & Downtown B&V - 48 4/25/14

  49. 3. Control Combined Sewer Overflows Where are we today?  Design 100% complete & Construction 70% complete  7 of 8 CSO outfalls eliminated….1 to go  470 MG /year on average will be eliminated when complete  8 Inflow reduction & sewer separation projects complete  3 Optimization projects for ex. CSO Storage Tunnels complete  6 Storage/conveyance projects complete  2 Storage projects & 1 sewer separation under construction  2 Regulator projects in design B&V - 49 4/25/14

  50. TWI – Total Program… Where are we today? We are over 84 % program complete & on schedule:  All 146 Consent Decree milestones to date have been met  66 on Phase 1 and 80 on Phase 2 Out of 45+ projects, 5 remain:  3 under construction  Final 2 in design B&V - 50 4/25/14

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend