Status of Sustainable Groundwater Management Act Implementation
January 6, 2020
Status of Sustainable Groundwater January 6, 2020 Management Act - - PowerPoint PPT Presentation
Status of Sustainable Groundwater January 6, 2020 Management Act Implementation Technical Data Management System Groundwater Dependent Ecosystems Field Work Recent Key Hydrogeologic Conceptual Model Accomplishments
January 6, 2020
Stakeholder Advisory Committee Stakeholder Communication and Engagement Plan
both GSI Water Solutions Inc. and CV Strategies Data Review and Assessment Hydrogeological Conceptual Model Groundwater Model Update and Readiness Groundwater Surface Water Interconnection Water Budget Development Sustainable Management Criteria Projects and Management Actions Preparation of the Groundwater Sustainability Plan
Data Review and Assessment
assessment, data gaps, recommendations for GW monitoring, Sampling and Analysis Plan Hydrogeological Conceptual Model
technical memorandum. HCM specific workshop Groundwater Model Update and Readiness
documentation prepared for R2 Grant
Groundwater Surface Water Interconnection
installation of six piezometers and up to 40 temperature probes Water Budget Development
water budget. Round 3 Grant
agreement, additional consultant work
Technical memo on Groundwater Dependent Ecosystems took more time than expected. Site access agreements. Some delays but good progress being made on multiple fronts now (private land, City, County). Delays do not affect overall schedule, but can delay collection of new data. Currently mitigated by using water level data from shallow wells and use of groundwater flowmodel to examine predicted changes in groundwater conditions.
Anticipate using contingency funds for up to 2 additional workshops in FY 20/21. During FY 20/21 budget process, we will propose moving approved contingency funds into contracts to cover this effort. Round 3 Grant- if awarded some scope and budget changes to contracts will be necessary to reflect additional funds for installation of data loggers and other work.
mitigated.
means significant new work will take place.
technical work and workshops.
Task # Description of Task
Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Task 2 Data Review and Assessment Task 6 Hydrogeologic Conceptual Model Task 3 Groundwater Model Update and Readiness Task 4 Groundwater/Surface Water Interconnection and Sustainability Criteria for GDE's Task 4 Public Workshop Cycle Task 5 Water Budget Development Task 5 Public Workshop Cycle Task 7 Development of Sustainable Management Criteria Task 7 Public Workshop Cycle Task 8 Projects and Management Actions and Implementation Plan Task 8 Public Workshop Cycle Task 9 GSP Document Preparation Task 9 Public Workshop Cycle Workshop Cycle Workshop Cycle Workshop Cycle Workshop Cycle TASK 7 TASK 8 TASK 9
Calendar Year 2021
SCV GSP Development Schedule (12‐18‐19) TASK 4 TASK 2 TASK 5
Calendar Year 2019 Calendar Year 2020
TASK 6 Workshop Cycle TASK 3