Turitea wind farm
Community Liaison Group
1 August 2019
Turitea wind farm Community Liaison Group 1 August 2019 AGENDA 1. - - PowerPoint PPT Presentation
Turitea wind farm Community Liaison Group 1 August 2019 AGENDA 1. Introductions; health and safety 2. Project update 3. Follow ups to previous meeting WHAT WELL DISCUSS TONIGHT 2 PROJECT UPDATE > Transmission line design
1 August 2019
AGENDA
WHAT WE’LL DISCUSS TONIGHT 2
1. Introductions; health and safety 2. Project update 3. Follow ups to previous meeting
PROJECT UPDATE
WHAT’S HAPPENING IN THE NEXT EIGHT WEEKS 3
> Transmission line design finalised, with a reduction in the number of structures ▪ Reduces the number of access tracks ▪ Reduces traffic volumes ▪ Reduces materials required ▪ Reduces vegetation clearing requirements > Wind farm – successful Safety in Design and Preliminary Design Review completed > Mercury’s Palmerston North office is in operation > Ongoing engagement with Rangitaane o Manawatu and Rangitaane o Tamaki Nui a Rua
HIGH LEVEL SCHEDULING
WHAT’S HAPPENING IN THE NEXT EIGHT WEEKS 4
Wind Farm
> Site village being established adjacent to South Range Road > Formation of the new South Range Rd entrance commencing > Site mobilisation
Transmission Line
> Transmission line set out > Geotechnical investigations > Upgrade of Greens Road
Linton Substation
> Fabrication of Electrical fittings > Issue of substation tender package
CONSTRUCTION NOISE MANAGEMENT PLANS
5
Construction Noise Limits
CLICK TO ADD FOOTER
6 Modelled Worst Case Construction Noise
Clearance and Vegetation Removal
CLICK TO ADD FOOTER
7 17 and 18 are closest helicoptered structures to dwellings
CLICK TO ADD FOOTER
8 Poles 17 and 18 modelled 70dBA contour (helicopter)
CLICK TO ADD FOOTER
9 Erosion and Sediment Control Plans
CONTRACTORS’ UPDATES – WIND FARM AND ROADING
WIND FARM 10
Completed Activities
> Geotechnical investigation at most Wind Turbine sites completed > Facilitated Safety in Design workshop completed > Preliminary Design Review completed
Planned Activities
> Site offices establishment > Formation of the new South Range Rd entrance > Site mobilisation > Establish site environmental controls
PROJECT UPDATE
VESTAS UPDATE 11
turn at the top of Pahiatua Track highway.
designated turning bay into the Construction Site and ensure Community and Public have safe travel through.
Construction Personnel, Community and Public while this activity is being undertaken.
Pahiatua track road at the bottom of the range. This access point is primarily for the delivery of blades to the project. 55metres in length and transport/construction vehicles travelling in a East to West direction. (Napier to Palmerston North) This will be gated/locked construction access road to prevent unauthorised vehicles entering and exiting.
12
CLICK TO ADD FOOTER
13
PROJECT UPDATE
SOUTH RANGE ROAD 14
South Range Road Upgrade:
turbines are predominantly from this road.
for transport of major equipment to project from new access road/s to approximately 1km past the gate into the Turitea reserve.
will also be a safer public road access road for community at completion of construction.
15
16
CLICK TO ADD FOOTER
17 Wind Farm Preliminary Design Layout
CONTRACTORS UPDATE - TRANSMISSION LINE
TRANSMISSION LINE 18
Completed Activities
> Transmission line design and route completed > Pole and Hardware designs completed > Access track plans completed
Planned Activities
> Transmission line set out – Survey pegs placed > Geotechnical investigations > Foundation design > Formation of access tracks & laydown areas > Upgrade of Greens Road
19
WORKS ON GREENS ROAD
Greens Road is used to access poles 9 onward, the Browns Flat staging area and most of the
The upgrades require engineering design, a report to council, then the upgrade works can
Local companies GHD and Stringfellows will be completing the design and build work and will be engaged to ensure the road is kept swept and any ongoing maintenance is identified. – Road condition survey - complete – Engineering design - underway – Traffic management plan – underway – inputs please – Boundary survey - August – Kahuterawa Rd (line of sight improvements) - August/September – Tree removal (Greens Rd) - September – Earthworks - September – Sealing and culverts - September weather permitting
CLICK TO ADD FOOTER
20
Construction Process > Preparation Works
CLICK TO ADD FOOTER
21
Construction Process > Foundations
TRANSMISSION LINE
22
Construction Process > Getting everything straight and true
TRANSMISSION LINE
23
Construction Process > Flying in concrete
CLICK TO ADD FOOTER
24
Construction Process > Poles installed in only a few lifts
25
HELICOPTER WORK
We will be using helicopter during the project for: lifting heavy equipment concrete pole erection (9,10,17,18) tower erection (26-30 and 33-35) stringing Potentially using a Blackhawk helicopter for some work
CONTRACTORS UPDATE – LINTON SUBSTATION
LINTON SUBSTATION 26
Completed Activities
> Site geotechnical investigations > Protection systems design > Control room layout of additional equipment > Multiparty facilitated safety workshop
Planned Activities
> Fabrication of Electrical fittings > Issue of substation tender package > Awarding civil works > Begin Mobilising to site
CLICK TO ADD FOOTER
27
PUBLIC FEEDBACK ON TRAFFIC MANAGEMENT PLAN
> Drivers should be aware that Turitea road is part of the Te Araroa Trail and is heavily used by walkers, runners and cyclists. > The first 2kms includes a short steep narrow set of sharp bends where there is no footpath, pavement, hard shoulder, soft shoulder or space of any kind, plus a one-way bridge. > Request to include some building work to provide new cycle and walking path so drivers are not sharing that bit of narrow road with those on foot or bike. > A couple of mirrors on the tight bends on Turitea Road would provide improved visibility. Feedback passed on to PNCC's Traffic Management Consultant for consideration as part of Plan review and certification.
FOLLOW UPS TO PREVIOUS MEETING
ACTIONS TAKEN AFTER LAST MEETING 28
1. Summary of previous meeting sent out by email (with links to website) 2. Feedback received via website/email and actioned 3. Dates for next meetings
FOR FURTHER INFORMATION > TURITEAWINDFARM@MERCURY.CO.NZ