ACCESSING THE ACCESSING THE FAR SHORE WIND FARM C. Cockburn S St - - PowerPoint PPT Presentation

accessing the accessing the far shore wind farm
SMART_READER_LITE
LIVE PREVIEW

ACCESSING THE ACCESSING THE FAR SHORE WIND FARM C. Cockburn S St - - PowerPoint PPT Presentation

ACCESSING THE ACCESSING THE FAR SHORE WIND FARM C. Cockburn S St S. Stevens E. Dudson ACCESSING THE FAR SHORE WIND FARM ACCESSING THE FAR SHORE WIND FARM SUMMARY SUMMARY Operation and maintenance of offshore wind farms Current


slide-1
SLIDE 1

ACCESSING THE ACCESSING THE FAR SHORE WIND FARM

  • C. Cockburn

S St

  • S. Stevens
  • E. Dudson
slide-2
SLIDE 2

ACCESSING THE FAR SHORE WIND FARM ACCESSING THE FAR SHORE WIND FARM

SUMMARY

  • Operation and maintenance of offshore wind farms
  • Current wind farms are relatively small and positioned close to shore

SUMMARY

  • Round 2 and 3 sites will be significantly further offshore
  • Rougher seas and longer transits
  • Requires a change in the current regulations and vessel designs

This presentation aims to:-

  • Assess the likely availability and operability of wind farm support vessels
  • Assess the likely requirements for future vessels

This presentation aims to:- Assess the likely requirements for future vessels

  • Suggest a forward looking strategy to meet the predetermined service

requirements

ACCESSING THE FAR SHORE WIND FARM

slide-3
SLIDE 3

INTRODUCTION INTRODUCTION

  • 25% of UK electricity supplied from
  • ffshore wind energy by 2020
  • Approximately 5,000 offshore units
  • A large number of vessels will be

required required

  • Finite time and number of ship yards
  • Current vessels inappropriate for

longer transits and increasing wave heights

ACCESSING THE FAR SHORE WIND FARM

slide-4
SLIDE 4

BACKGROUND BACKGROUND

AN EVOLUTION IN VESSEL DESIGN

  • First vessels were small work boats

and fishing boats

  • Dedicated vessels
  • Relatively fast
  • Aluminium
  • Catamarans
  • Custom bow fenders
  • Tailored power installations
  • Lengths of 15 metres to 20 metres,

increasing to 24 metres

  • Now bespoke arrangements
  • Now bespoke arrangements

ACCESSING THE FAR SHORE WIND FARM

slide-5
SLIDE 5

INTRODUCTION INTRODUCTION

AN EVOLUTION IN WIND ENERGY INDUSTRY

  • The UIK has adopted a highly

progressive policy of wind energy generation

  • After Round 1 – UK Total of ~400

Turbines, 1.3GW

  • After Round 2 – UK Total of ~2000

Turbines, 7.6GW

  • After Round 3 – UK Total of ~6000

Turbines, 32.2GW

  • Size of turbines

‘Offshore Wind - Round 3 Zones’ supplied b Th C E t t by The Crown Estate

ACCESSING THE FAR SHORE WIND FARM

slide-6
SLIDE 6

RELATIVE SIZE AND DISTANCE OFFSHORE OF UK WIND FARMS

1 2 3 4 5 6 Transit Time @ 20 kts (hours)

Dogger Bank 9.0 GW

1600 1800 2000 ATION LIMIT

Norfolk 7.2 GW

1200 1400 rbines Round 1 Zones ‐ Offshore Wind Round 2 Zones ‐ Offshore Wind Round 3 Zones ‐ Offshore Wind Round 3 Zone Extents EL CERTIFICA

Hornsea 4 0 GW Irish Sea 4.2 GW

800 1000 Number of Tu 60 NM Limit VESSE

Firth of Forth 3.5 GW 4.0 GW

200 400 600 0.0 20.0 40.0 60.0 80.0 100.0 120.0 Distance from shoreline (Nautical Miles)

ACCESSING THE FAR SHORE WIND FARM

slide-7
SLIDE 7

EXISTING FLEET CAPABILITY EXISTING FLEET CAPABILITY

  • MCA Small Commercial Vessels

DESIGN LIMITATIONS 60 nm

MCA Small Commercial Vessels Code

  • 60 nautical mile limit

40 nm 60 nm

  • 2 hour desirable transit time
  • Assuming an average transit

speed of 20 knots

  • Restricts the range to 40 nautical

miles

ACCESSING THE FAR SHORE WIND FARM

slide-8
SLIDE 8

60 nm 60 nm 40 nm ACCESSING THE FAR SHORE WIND FARM

slide-9
SLIDE 9

EXISTING FLEET CAPABILITY EXISTING FLEET CAPABILITY

VESSEL CAPABILITY

  • ISO 2361 Limits for 0.5, 1 and 2 hours, 10% MSI

D bl f t h i i d t t lli t

VESSEL CAPABILITY

  • Double for technicians more used to travelling at sea
  • Vertical accelerations averaged over head, bow quartering and beams seas
  • Possible to approximate the wave height at which the ISO limits are exceeded
  • Possible to approximate the wave height at which the ISO limits are exceeded

0.60 16 0.60 0.60 0.30 0.40 0.50

cal Acceleration (g)

16m 20m 24m 0.30 0.40 0.50

cal Acceleration (g)

16m 20m 24m 0.30 0.40 0.50

cal Acceleration (g)

16m 20m 24m 0.00 0.10 0.20 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5

Vetic Significant Wave Height (metres) 0.5 hours exposure 1 hour exposure 2 hour exposure

0.00 0.10 0.20 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5

Vetic Significant Wave Height (metres) 0.5 hours exposure 1 hour exposure 2 hour exposure

0.00 0.10 0.20 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5

Vetic Significant Wave Height (metres) 0.5 hours exposure 1 hour exposure 2 hour exposure

V ti l A l ti R t 16 K t V ti l A l ti R t 20 K t V ti l A l ti R t 24 K t Vertical Acceleration Response at 16 Knots Vertical Acceleration Response at 20 Knots Vertical Acceleration Response at 24 Knots

ACCESSING THE FAR SHORE WIND FARM

slide-10
SLIDE 10

0.60 16 0.50

)

16m 20m 24m 0.40

ration (g)

0.30

cal Accele

0 10 0.20

Vetic 0.5 hours exposure 1 hour exposure

0.00 0.10

2 hour exposure

Vertical Acceleration Response at 20 Knots

0.00 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5

Significant Wave Height (metres)

Vertical Acceleration Response at 20 Knots

ACCESSING THE FAR SHORE WIND FARM

slide-11
SLIDE 11

APPLICATION TO WIND FARMS APPLICATION TO WIND FARMS

WAVE ENVIRONMENT

  • Based on data from BMT ARGOSS

WAVE ENVIRONMENT

  • 53° 00'N, 2° 30'E
  • Northern end of the Norfolk site

42% 41% 30% 40% 50% nce 13% 3% 1% 0% 10% 20% Occure 0% 0‐1 1‐2 2‐3 3‐4 4‐5 5‐6 Wave Height (metres)

ACCESSING THE FAR SHORE WIND FARM

slide-12
SLIDE 12

APPLICATION TO WIND FARMS APPLICATION TO WIND FARMS

WAVE ENVIRONMENT WAVE ENVIRONMENT

90% 100% 70% 80% 90% eeding Hs 40% 50% 60%

  • f Time Exce

10% 20% 30% Percent 0% 1 2 3 4 5 Significant Wave Height (m)

ACCESSING THE FAR SHORE WIND FARM

slide-13
SLIDE 13

APPLICATION TO WIND FARM SITES APPLICATION TO WIND FARM SITES

R d 3 Sit N f lk

  • 1440 turbines

30 di t ff h Round 3 Site - Norfolk

  • 30 nm average distance offshore
  • Calculated duration based on speed
  • Estimated wave height limit for each
  • Estimated wave height limit for each

length of vessel at each speed

  • Seem low but driven by increased

d ti d f ff h duration and use of offshore spectrum for entire transit

Speed Duration Max Wave Height Kts hrs 16m 20m 24m 16 1.88 0.59 0.70 0.86 20 1.50 0.55 0.65 0.78 24 1.25 0.54 0.63 0.73

ACCESSING THE FAR SHORE WIND FARM

slide-14
SLIDE 14

APPLICATION TO WIND FARMS APPLICATION TO WIND FARMS

OPERABILITY

  • Using the wave statistics and

motions analysis Speed Availability (%) Kts 16m 20m 24m 16 25 29 36

OPERABILITY

motions analysis

  • Determine the percentage that

the sea state exceeds the derived limits 16 25 29 36 20 23 27 32 24 22 26 30 derived limits

  • Increase in length increases

availability

  • Increase in speed, reduces

availability

  • Lower speeds will induce higher
  • Lower speeds will induce higher

durations and reduce the acceptable ISO limits

ACCESSING THE FAR SHORE WIND FARM

slide-15
SLIDE 15

APPLICATION TO WIND FARMS APPLICATION TO WIND FARMS

MAINTENANCE REGIMES

  • Norfolk site – 1440 turbines

1 t bi t k 3 t h i i 5

16 metre V l 20 metre l 24 metre l

MAINTENANCE REGIMES

  • 1 turbine takes 3 technicians 5

days (15 man days)

  • 12 technicians per boat, 4 turbines

Vessel vessel vessel 16 knots 21 17 14 20 knots 22 19 16 24 knots 22 19 17

per boat

  • Calculate the required number of

vessels based on the availability vessels based on the availability

  • Unscheduled maintenance not

accounted for

ACCESSING THE FAR SHORE WIND FARM

slide-16
SLIDE 16

APPLICATION TO WIND FARMS APPLICATION TO WIND FARMS

IMPROVING OPERABILITY

  • Example of the 24 metre @ 20

knots

IMPROVING OPERABILITY

knots

  • Increase sea keeping ability,

increases operability and il bilit availability

  • Increased availability reduces

number of required boats

  • Reduces number of technicians
  • Reduces time of boats and crew

t db

Wave Height Vessels Technicians Availability (metres) (#) (#) (%) 0 78 16 192 32

  • n standby

0.78 16 192 32 1 12 144 42 1.5 8 96 62 2 6 72 83

ACCESSING THE FAR SHORE WIND FARM

slide-17
SLIDE 17

IMPROVING OPERABILITY IMPROVING OPERABILITY

RIDE CONTROL SYSTEMS

  • Potentially allow for 20%

increase in wave height

RIDE CONTROL SYSTEMS

increase in wave height

  • Increase in cost
  • Control Systems

y

  • Foils
  • Fins
  • Gyros
  • Ballast tanks

ACCESSING THE FAR SHORE WIND FARM

slide-18
SLIDE 18

IMPROVING OPERABILITY IMPROVING OPERABILITY

LONGER VESSELS

  • Increase above 24 metres in length
  • Increase construction costs, fuel

LONGER VESSELS

Increase construction costs, fuel costs, etc.

  • Require a change in the MCA

regulations regulations

  • Potentially could take more

technicians

  • More technicians would service

more turbines per boat reducing the required number of boats further

BMT Nigel Gee MODCat 50m Crewboat

ACCESSING THE FAR SHORE WIND FARM

slide-19
SLIDE 19

IMPROVING OPERABILITY IMPROVING OPERABILITY

SMALL WATER PLANE AREA TWIN HULL (SWATH) HULL FORMS

  • Significant reduction in ship motions

SMALL WATER-PLANE AREA TWIN HULL (SWATH) HULL FORMS

  • Much more costly to build and operate
  • Considerable increase in availability would

significantly reduce the number of vessels required significantly reduce the number of vessels required

ACCESSING THE FAR SHORE WIND FARM

slide-20
SLIDE 20

Mothership Technology Mothership Technology

P D t i it bl H ll F f Off h A d ti M d l

  • Define Requirements

C t D i Purpose : Determine a suitable Hull Form for Offshore Accommodation Module

  • Concept Design
  • 80-100m OSV
  • 50-70m SWATH
  • Regulatory Review
  • Seakeeping

Calculations

  • Launch and Recovery

Discussions

slide-21
SLIDE 21

CONCLUSION CONCLUSION

  • Current wind farm vessels are inappropriate
  • The increases in wave height will result in low availability due to increased

exposure times and high vertical accelerations Th i f fl t i d t d t th d ti i l il bilit i

  • The size of fleet required to accommodate the reduction in vessel availability is

not in economically practical

  • More effort is clearly required to increase the operability
  • In order to improve the operability different technology from the currently

accepted wind farm support vessel will be required

ACCESSING THE FAR SHORE WIND FARM

slide-22
SLIDE 22

Mothership Technology Mothership Technology

Effi i d S k i 90m Monohull 60 SWATH Efficiency and Seakeeping

3000 Monohull NG733 - Project Description Curves of Brake Power vs Speed

Notes
  • 1. Propeller efficiency 0.60
  • 2. Powering estimations based on model testing of similar
hull forms
  • 3. No ride control systems fitted

60m SWATH

2500 Monohull SWATH 1500 2000 PB (kW) 500 1000 500 6 7 8 9 10 11 12 13 14 15 Speed (knots)

slide-23
SLIDE 23

Mothership Technology Mothership Technology

Effi i d S k i 90m Monohull 60 SWATH Efficiency and Seakeeping

Description Vertical Accelerations Lateral Accelerations Roll Angle

60m SWATH

Light manual work 0.20g 0.10g 6.0 Heavy manual work 0.15g 0.07g 4.0 Intellectual work 0.10g 0.05g 3.0 Transit passenger 0 05g 0 04g 2 5 Transit passenger 0.05g 0.04g 2.5 Cruise liner 0.02g 0.03g 2.0

Description Limiting Significant Wave Height (m) Vertical Acceleration Surge Acceleration Pitch Angle Mono SWATH Mono SWATH Mono SWATH Light Manual

  • Heavy Manual

3 2

  • Heavy Manual

3.2 Intellectual 2.4

  • Transit Passenger

2.0 5.0

  • Cruise Liner

1.6 4.0 4.5

  • 4.2
slide-24
SLIDE 24

Launch and Recovery Systems Launch and Recovery Systems

P I iti l I ti ti i t A il bl T h l i d th i A li ti

  • Review Technologies

A A li ti f Purpose : Initial Investigation into Available Technologies and their Application

  • Assess Application of

Technologies

  • Estimate Operating

Limits for the technologies

slide-25
SLIDE 25

Launch and Recovery Systems Launch and Recovery Systems

Obj ti A l i Related to type of Mothership Objective Analysis Mothership Related to required type

  • f ITV

System Limiting Max Hs Without HC With HC M l 1 0 1 5 Monopole crane 1.0 m 1.5 m Davits 1.5 m 2.0 m Stern A-frame crane 2.0 m 2.5 m Stern ramp 2.0 m N/A Floating docks 2 5 m N/A Floating docks 2.5 m N/A Semi-submersible 2.5 m N/A Open transom 2.0 m N/A

slide-26
SLIDE 26

Constants ITV R i 30 V i bl ITV Range mins 30 Variable ITV Speed kts 10 Calculated Turbine Spacing km 1

  • No. of ITVs per MS

4 Wi df Windfarms Location Dogger Bank Moray Firth Firth of Forth Hornsea Norfolk Hastings IOW Atlantic Array Irish Sea Area km2 8660 520 2852 4735 6037 270 724 950 2200 Distance from Port Max km 125 Distance from Port Min km 290 Distance from Port Average km 160 28 67 112 56 20 21 24 28 Water depth Max m 18 30 30 30 5 19 28 20 28 Water depth Min m 63 57 80 70 70 62 56 61 78 Capacity GW 9 1.3 3.5 4 7.2 0.6 0.9 1.5 4.2 Number of Turbines 1800 260 700 800 1440 120 180 300 840 ITV Operability % 60 60 60 60 60 60 60 60 60 MS Operability % 90 90 90 90 90 90 90 90 90 Calculated ITV Range Dist nm 5 5 5 5 5 5 5 5 5

  • No. of turbines in ITV Range

# 273 273 273 273 273 273 273 273 273 Number of man days (3 techs, 5 days per turbine) days 6825 6825 6825 6825 6825 6825 6825 6825 6825 Number of ITV days (12 techs per ITV) days 569 569 569 569 569 569 569 569 569 Number of MS days per location (=ITV days/No. ITVs) days 142 142 142 142 142 142 142 142 142

  • No. of locations done by MS (=365*MS Operabiliy/MS days)

# 2.31 2.31 2.31 2.31 2.31 2.31 2.31 2.31 2.31 Number of Locations (=Total No. Turbs/Turbs in ITV Rng) # 6.59 0.95 2.56 2.93 5.27 0.44 0.66 1.10 3.08

  • No. of MS Required

# 3 1 2 2 3 1 1 1 2 Reduncacy (Time Each MS not required) % 5 59 45 37 24 81 71 52 33

slide-27
SLIDE 27

THANK YOU Any questions?