Den Brook Wind Farm Community Liaison Group May 2016 Den Brook - - PowerPoint PPT Presentation

den brook wind farm
SMART_READER_LITE
LIVE PREVIEW

Den Brook Wind Farm Community Liaison Group May 2016 Den Brook - - PowerPoint PPT Presentation

Den Brook Wind Farm Community Liaison Group May 2016 Den Brook Wind Farm RES Construction Phase Team Den Brook Wind Farm Headline Project Details Consented 2009 Construction commenced July 2015 6.5km of site road 33kV


slide-1
SLIDE 1

Den Brook Wind Farm

Community Liaison Group

May 2016

slide-2
SLIDE 2

Den Brook Wind Farm

RES Construction Phase Team

slide-3
SLIDE 3

Headline Project Details

  • Consented 2009
  • Construction commenced

July 2015

  • 6.5km of site road
  • 33kV grid connection at

North Tawton

  • 9 V90 Vestas 2MW turbines

with 75m hub height

  • 18MW installed capacity

Den Brook Wind Farm

slide-4
SLIDE 4

Den Brook Wind Farm – Progress

Engineering

Element S tatus Civil Infrastructure detailed design Complete Foundation detailed design Complete Grid S ubstation detailed design Complete WF substation detailed design Complete

Procurement

Civil works Complete S ubstation package Complete Turbines Complete

slide-5
SLIDE 5

Den Brook Wind Farm – Progress

Construction Progress

Works Completed:

  • Off-site highway works complete
  • S

ite roads/ signage and all crane hardstandings complete

  • All 9 turbine foundations complete and backfilled
  • HV Cable network for the wind farm between the

substation and all turbines is complete

  • Turbine delivery Trial Run complete
  • Overhead protection for railway tunnel installed

Works Ongoing:

  • Fencing and gate installation ongoing
  • S

ubstation construction ongoing – foundations/ drainage constructed, electrical phase to follow

  • Ecological works for the environmental mitigation plan

currently being discussed

  • Planning for the turbine delivery/ installation and

commissioning phase ongoing

slide-6
SLIDE 6

Den Brook Wind Farm – Civil Infrastructure Layout

slide-7
SLIDE 7

Den Brook Wind Farm – Civil Infrastructure

Track to Turbine 5 Track from site entrance Water Crossing Blade fingers constructed

slide-8
SLIDE 8

Den Brook Wind Farm – Civil Infrastructure

Railway tunnel protection works HV cable network installation

slide-9
SLIDE 9

Den Brook Wind Farm – Turbine Foundations

slide-10
SLIDE 10

Den Brook Wind Farm – Turbine Foundations

T 6 foundation/hardstanding area reinstated and finished

slide-11
SLIDE 11

Den Brook Wind Farm – Turbine Foundations

Truck pave material installed and topsoiled for visual purposes

slide-12
SLIDE 12

Den Brook Wind Farm – Turbine Foundations

View of T6

slide-13
SLIDE 13

Den Brook Wind Farm – S ubstation construction

slide-14
SLIDE 14

Den Brook Wind Farm – Progress

Grid Connection Works (carried out by WPD)

  • WPD’s cabling works on the wind farm site approximately 90%

complete

  • Grid contractor now working east from site towards A3124
  • Directional drilling is complete under the Den Brook as well as the A3124

and A3072 to remove any disturbance to local traffic

  • WPD expected finish date is early July
slide-15
SLIDE 15

Den Brook Wind Farm - Programme

Commencement at site July 2015 Civil Works July 2015 – April 2016 Substation Works January 2016 – August 2016 Turbine Works August 2016 – November 2016 Project Completion - November 2016 Grid Available August 2016

slide-16
SLIDE 16

Den Brook Wind Farm – Wind Turbines

Each turbine consists of

  • 3 tower sections
  • 3 blades
  • Nacelle
  • Hub
slide-17
SLIDE 17

Den Brook Wind Farm – Upcoming

Turbine component deliveries – currently planned for late June 2016 Turbine erection and commissioning – July to November 2016 Ecology – hedgerow planting and bird boxes – August to October 2016 Local Electricity Discount Scheme

  • Expression of interest at 28 % of eligible properties since launch in May 2014
  • Direct mailer scheduled for late May/early June with instructions on how to join via

website/LEDs team

  • Registration ends October 2016
  • First payment end of 2016/early 2017

Community Benefit Fund

  • Available once the wind farm is operational
  • Administered locally
slide-18
SLIDE 18

Any Questions?