SLIDE 1
Den Brook Wind Farm Community Liaison Group May 2016 Den Brook - - PowerPoint PPT Presentation
Den Brook Wind Farm Community Liaison Group May 2016 Den Brook - - PowerPoint PPT Presentation
Den Brook Wind Farm Community Liaison Group May 2016 Den Brook Wind Farm RES Construction Phase Team Den Brook Wind Farm Headline Project Details Consented 2009 Construction commenced July 2015 6.5km of site road 33kV
SLIDE 2
SLIDE 3
Headline Project Details
- Consented 2009
- Construction commenced
July 2015
- 6.5km of site road
- 33kV grid connection at
North Tawton
- 9 V90 Vestas 2MW turbines
with 75m hub height
- 18MW installed capacity
Den Brook Wind Farm
SLIDE 4
Den Brook Wind Farm – Progress
Engineering
Element S tatus Civil Infrastructure detailed design Complete Foundation detailed design Complete Grid S ubstation detailed design Complete WF substation detailed design Complete
Procurement
Civil works Complete S ubstation package Complete Turbines Complete
SLIDE 5
Den Brook Wind Farm – Progress
Construction Progress
Works Completed:
- Off-site highway works complete
- S
ite roads/ signage and all crane hardstandings complete
- All 9 turbine foundations complete and backfilled
- HV Cable network for the wind farm between the
substation and all turbines is complete
- Turbine delivery Trial Run complete
- Overhead protection for railway tunnel installed
Works Ongoing:
- Fencing and gate installation ongoing
- S
ubstation construction ongoing – foundations/ drainage constructed, electrical phase to follow
- Ecological works for the environmental mitigation plan
currently being discussed
- Planning for the turbine delivery/ installation and
commissioning phase ongoing
SLIDE 6
Den Brook Wind Farm – Civil Infrastructure Layout
SLIDE 7
Den Brook Wind Farm – Civil Infrastructure
Track to Turbine 5 Track from site entrance Water Crossing Blade fingers constructed
SLIDE 8
Den Brook Wind Farm – Civil Infrastructure
Railway tunnel protection works HV cable network installation
SLIDE 9
Den Brook Wind Farm – Turbine Foundations
SLIDE 10
Den Brook Wind Farm – Turbine Foundations
T 6 foundation/hardstanding area reinstated and finished
SLIDE 11
Den Brook Wind Farm – Turbine Foundations
Truck pave material installed and topsoiled for visual purposes
SLIDE 12
Den Brook Wind Farm – Turbine Foundations
View of T6
SLIDE 13
Den Brook Wind Farm – S ubstation construction
SLIDE 14
Den Brook Wind Farm – Progress
Grid Connection Works (carried out by WPD)
- WPD’s cabling works on the wind farm site approximately 90%
complete
- Grid contractor now working east from site towards A3124
- Directional drilling is complete under the Den Brook as well as the A3124
and A3072 to remove any disturbance to local traffic
- WPD expected finish date is early July
SLIDE 15
Den Brook Wind Farm - Programme
Commencement at site July 2015 Civil Works July 2015 – April 2016 Substation Works January 2016 – August 2016 Turbine Works August 2016 – November 2016 Project Completion - November 2016 Grid Available August 2016
SLIDE 16
Den Brook Wind Farm – Wind Turbines
Each turbine consists of
- 3 tower sections
- 3 blades
- Nacelle
- Hub
SLIDE 17
Den Brook Wind Farm – Upcoming
Turbine component deliveries – currently planned for late June 2016 Turbine erection and commissioning – July to November 2016 Ecology – hedgerow planting and bird boxes – August to October 2016 Local Electricity Discount Scheme
- Expression of interest at 28 % of eligible properties since launch in May 2014
- Direct mailer scheduled for late May/early June with instructions on how to join via
website/LEDs team
- Registration ends October 2016
- First payment end of 2016/early 2017
Community Benefit Fund
- Available once the wind farm is operational
- Administered locally
SLIDE 18