SuDS
SuDs Management at Glenconway Windfarm SuDS Introduction to Gael - - PowerPoint PPT Presentation
SuDs Management at Glenconway Windfarm SuDS Introduction to Gael - - PowerPoint PPT Presentation
SuDs Management at Glenconway Windfarm SuDS Introduction to Gael Force Renewables SuDs Gael Force Renewables Ltd was formed in 2011 by McLaughlin & Harvey Ltd and William & Henry Alexander (Civil Engineering) Ltd to target
SuDs
Introduction to Gael Force Renewables
SuDs
- Gael Force Renewables Ltd was
formed in 2011 by McLaughlin & Harvey Ltd and William & Henry Alexander (Civil Engineering) Ltd to target onshore Wind Farm
- pportunities in GB & ROI.
SuDs
Gael Force Renewables – What We Do:
- 150 years of Civil Engineering Experience
- Gael Force offer full Design and Build Services
- Early client and designer involvement so that innovative, safe, buildable solutions are developed.
- At Gael Force we implement lessons learnt to ensure our teams constantly progress, develop and
refine skills, methodologies and work sequences
- Full time on site Environmental Professionals
SuDs
Project - Balmurrie Fell Wind Farm, Stranraer, South West Scotland. (7 x 1.3 MW Siemens WTG)
SuDs
Project – Glenconway Windfarm, Limavady, Northern Ireland (20 x 2.3MW WTG)
SuDS
Design to Construction
SuDS
Settlement Ponds
SuDS
Silt Fencing
SuDS
Clean water cut off drains
SuDS
Swales & check dams
SuDS
Breakouts
SuDS
Settlement Areas
SuDS
Monitoring Effectiveness
- Water Quality testing (internal & external)
- External inspections by Designers
- Internal weekly inspections by
Environmental Representative
- SEARS (Safety Environmental Awareness
Reporting Scheme). Positive and Negative issues raised by everyone on site.
SuDS
SuDS
Water Quality Testing
- External water quality testing was carried
- ut every two weeks at 5 locations for Phase
1 and 8 locations for Phase 1 & 2
- Testing covered 21 chemical parameters and
biological (macro invertebrate) monitoring
- Internal samples took place daily for phase 1
and weekly for phase 2. Parameters included turbidity, dissolved oxygen, pH, temp & EC.
SuDS
Environmental Awareness
- Water Quality results are displayed on
site
- Correlation between turbidity and
rainfall is also presented on graphs.
SuDS
Toolbox Talks
- Every Tuesday
morning
- Covers key issues
such as waste, energy, water pollution
- All site staff
shared the responsibility
SuDS
Environmental Awareness
SuDS
Environmental Coaching
Environmental Sessions to date:- SuDS (McCloys) Peat Stability / Peat Slides (BLP) Archaeology (Gahan & Long) Flora and Fauna (Blackstaff)
SuDS
SuDS
Conclusion
- SuDS design must account for inclement weather
conditions
- SuDS design must be site specific
- SuDS features must be installed prior to works
starting
- Very beneficial to have an on site environmental
representative
- Water Quality monitoring is important during
construction – even visual inspection of water courses
- Maintenance of SuDs Features is critical
Richard Collins BSc MSc AIEMA
Construction-Phase Temporary SuDS: A75 Case Study
Construction Context
- 3.67km carriageway realignment and upgrade:
include earthworks, drainage and culverts, utility works, surfacing & underpass construction
- Existing drainage mitigation inadequate
- Filter drains & 4 balancing ponds with reed beds
Key Environmental Aim ‘Protecting the Pow Water tributaries during construction’
Challenges & Uncertainties
- Geology & soils
- Earthworks intensive
- EIA stated ‘potentially increased sedimentation’
- True nature of soils
Fine Clays
- Spatial constraints
- Limited opportunity for temporary SuDS
locations
- Temporal Constraints
- Not scheduled in programme of works
- Resources to complete with immediate effect
- Costs
Usual Suspects
- Exposed soils: ensuring capping/seeding is
completed ASAP
- Stockpiles: limiting, stabilising
- Washing & washout facilities
- Haul roads: wheel wash operative (spatial
constraints)
- Dewatering: sumps, releasing at suitable times
- Inclement weather: be prepared
Water Management Strategy
Liaise with local SEPA representative
Alum sulphate required: minimal dosing policy
Tiered, impermeable treatment zones
Maintenance plan: Daily checks
pH (6-8) & turbidity (<10ntu) testing
Controlled release
Tangible Results
Permanent Pond Installation
- Isolated pond
- Limited opportunity for
treatment
- Use of existing vegetation
- Lined sediment forebay
- Aquatic bench in
permanent pool; ecology, amenity & safety
Native Species Planting
Pond Edge Mix Yellow Flag Iris Water Avens
- Benefits of bio-retention and enhanced biodiversity
Meadowsweet
Learning Points
Detailed pre-construction review of EIA Robust planning, management & maintenance required Micro-managed retention & release Maximise use of sub-catchments in design