SuDs Management at Glenconway Windfarm SuDS Introduction to Gael - - PowerPoint PPT Presentation

suds management
SMART_READER_LITE
LIVE PREVIEW

SuDs Management at Glenconway Windfarm SuDS Introduction to Gael - - PowerPoint PPT Presentation

SuDs Management at Glenconway Windfarm SuDS Introduction to Gael Force Renewables SuDs Gael Force Renewables Ltd was formed in 2011 by McLaughlin & Harvey Ltd and William & Henry Alexander (Civil Engineering) Ltd to target


slide-1
SLIDE 1

SuDS

SuDs Management at Glenconway Windfarm

slide-2
SLIDE 2

SuDs

Introduction to Gael Force Renewables

slide-3
SLIDE 3

SuDs

  • Gael Force Renewables Ltd was

formed in 2011 by McLaughlin & Harvey Ltd and William & Henry Alexander (Civil Engineering) Ltd to target onshore Wind Farm

  • pportunities in GB & ROI.
slide-4
SLIDE 4

SuDs

Gael Force Renewables – What We Do:

  • 150 years of Civil Engineering Experience
  • Gael Force offer full Design and Build Services
  • Early client and designer involvement so that innovative, safe, buildable solutions are developed.
  • At Gael Force we implement lessons learnt to ensure our teams constantly progress, develop and

refine skills, methodologies and work sequences

  • Full time on site Environmental Professionals
slide-5
SLIDE 5

SuDs

Project - Balmurrie Fell Wind Farm, Stranraer, South West Scotland. (7 x 1.3 MW Siemens WTG)

slide-6
SLIDE 6

SuDs

Project – Glenconway Windfarm, Limavady, Northern Ireland (20 x 2.3MW WTG)

slide-7
SLIDE 7

SuDS

Design to Construction

slide-8
SLIDE 8

SuDS

Settlement Ponds

slide-9
SLIDE 9

SuDS

Silt Fencing

slide-10
SLIDE 10

SuDS

Clean water cut off drains

slide-11
SLIDE 11

SuDS

Swales & check dams

slide-12
SLIDE 12

SuDS

Breakouts

slide-13
SLIDE 13

SuDS

Settlement Areas

slide-14
SLIDE 14

SuDS

Monitoring Effectiveness

  • Water Quality testing (internal & external)
  • External inspections by Designers
  • Internal weekly inspections by

Environmental Representative

  • SEARS (Safety Environmental Awareness

Reporting Scheme). Positive and Negative issues raised by everyone on site.

slide-15
SLIDE 15

SuDS

slide-16
SLIDE 16

SuDS

Water Quality Testing

  • External water quality testing was carried
  • ut every two weeks at 5 locations for Phase

1 and 8 locations for Phase 1 & 2

  • Testing covered 21 chemical parameters and

biological (macro invertebrate) monitoring

  • Internal samples took place daily for phase 1

and weekly for phase 2. Parameters included turbidity, dissolved oxygen, pH, temp & EC.

slide-17
SLIDE 17

SuDS

Environmental Awareness

  • Water Quality results are displayed on

site

  • Correlation between turbidity and

rainfall is also presented on graphs.

slide-18
SLIDE 18

SuDS

Toolbox Talks

  • Every Tuesday

morning

  • Covers key issues

such as waste, energy, water pollution

  • All site staff

shared the responsibility

slide-19
SLIDE 19

SuDS

Environmental Awareness

slide-20
SLIDE 20

SuDS

Environmental Coaching

Environmental Sessions to date:- SuDS (McCloys) Peat Stability / Peat Slides (BLP) Archaeology (Gahan & Long) Flora and Fauna (Blackstaff)

slide-21
SLIDE 21

SuDS

slide-22
SLIDE 22

SuDS

Conclusion

  • SuDS design must account for inclement weather

conditions

  • SuDS design must be site specific
  • SuDS features must be installed prior to works

starting

  • Very beneficial to have an on site environmental

representative

  • Water Quality monitoring is important during

construction – even visual inspection of water courses

  • Maintenance of SuDs Features is critical
slide-23
SLIDE 23

Richard Collins BSc MSc AIEMA

Construction-Phase Temporary SuDS: A75 Case Study

slide-24
SLIDE 24

Construction Context

  • 3.67km carriageway realignment and upgrade:

include earthworks, drainage and culverts, utility works, surfacing & underpass construction

  • Existing drainage mitigation inadequate
  • Filter drains & 4 balancing ponds with reed beds

Key Environmental Aim ‘Protecting the Pow Water tributaries during construction’

slide-25
SLIDE 25

Challenges & Uncertainties

  • Geology & soils
  • Earthworks intensive
  • EIA stated ‘potentially increased sedimentation’
  • True nature of soils
slide-26
SLIDE 26

Fine Clays

slide-27
SLIDE 27
  • Spatial constraints
  • Limited opportunity for temporary SuDS

locations

slide-28
SLIDE 28
  • Temporal Constraints
  • Not scheduled in programme of works
  • Resources to complete with immediate effect
  • Costs
slide-29
SLIDE 29

Usual Suspects

  • Exposed soils: ensuring capping/seeding is

completed ASAP

  • Stockpiles: limiting, stabilising
  • Washing & washout facilities
  • Haul roads: wheel wash operative (spatial

constraints)

  • Dewatering: sumps, releasing at suitable times
  • Inclement weather: be prepared
slide-30
SLIDE 30

Water Management Strategy

Liaise with local SEPA representative

Alum sulphate required: minimal dosing policy

Tiered, impermeable treatment zones

Maintenance plan: Daily checks

pH (6-8) & turbidity (<10ntu) testing

Controlled release

slide-31
SLIDE 31

Tangible Results

slide-32
SLIDE 32

Permanent Pond Installation

  • Isolated pond
  • Limited opportunity for

treatment

  • Use of existing vegetation
  • Lined sediment forebay
  • Aquatic bench in

permanent pool; ecology, amenity & safety

slide-33
SLIDE 33

Native Species Planting

Pond Edge Mix Yellow Flag Iris Water Avens

  • Benefits of bio-retention and enhanced biodiversity

Meadowsweet

slide-34
SLIDE 34

Learning Points

Detailed pre-construction review of EIA Robust planning, management & maintenance required Micro-managed retention & release Maximise use of sub-catchments in design

slide-35
SLIDE 35

Thank you