Tour of new eircom Data Centre Blanchardstown by Dervan Engineering - - PowerPoint PPT Presentation

tour of new eircom data centre blanchardstown by dervan
SMART_READER_LITE
LIVE PREVIEW

Tour of new eircom Data Centre Blanchardstown by Dervan Engineering - - PowerPoint PPT Presentation

Tour of new eircom Data Centre Blanchardstown by Dervan Engineering Consultants 11 th March 2015 Presentation Outline Mechanical Overview Chillers and Pumps Pipework and Ancillaries In Row Cooling Units Mechanical Ventilation


slide-1
SLIDE 1

Tour of new eircom Data Centre Blanchardstown by Dervan Engineering Consultants 11th March 2015

slide-2
SLIDE 2

1 April 2015 Dervan Engineering Consultants 2

Presentation Outline

Mechanical

  • Overview
  • Chillers and Pumps
  • Pipework and Ancillaries
  • In Row Cooling Units
  • Mechanical Ventilation
slide-3
SLIDE 3

1 April 2015 Dervan Engineering Consultants 3

Presentation Outline

Electrical

  • Overview
  • MV Switchgear & Transformers
  • Generators / EGIP
  • Main LV Switchgear
  • UPS
  • Miscellaneous
slide-4
SLIDE 4

1 April 2015 Dervan Engineering Consultants 4

Mechanical Overview

slide-5
SLIDE 5

1 April 2015 Dervan Engineering Consultants 5

Chillers and Pumps

Chillers

  • 3 No. chillers (N+1) are each rated at 721 kW at 15/21ºC flow and return, 30% glycol and 30ºC
  • ambient. - Climaveneta
  • All three chillers run in part load to achieve the maximum level of free cooling.
  • The chillers have free cooling coils and the estimated percentage operation on free versus

compressor cooling is as follows: Compressor cooling only @ T > 16 ºC – 7% Compressor & free cooling @ 7 ºC < T <16 ºC – 53% Free cooling only @ T < 7 ºC – 40%

  • The chillers have integral primary pumps with variable speed drives which will control the flow rate

in the primary loop in accordance with the demand in the secondary loop. Secondary Pumps

  • Two sets of duty standby secondary variable speed pumps are provided - Wilo
  • Each pump set is located in its own pump room along with the associated pump headers,

pressurization / auto fill unit.

slide-6
SLIDE 6

1 April 2015 Dervan Engineering Consultants 6

Pipework and Ancillaries

Primary Pipework

  • The three chillers are connected to primary flow and return looped headers with isolation valves

between each chiller connection to facilitate total isolation of any chiller and still allow the other two chillers to function normally.

  • The primary and secondary circuits are connected by two separate paths to allow the system to

continue to function in the event of a component or path failure. Primary Buffer Vessels

  • The two primary by pass lines are each fitted with a 1000L buffer vessel.
  • These provide a minimum level of water in the primary loop to reduce the frequency of chiller starts.
slide-7
SLIDE 7

1 April 2015 Dervan Engineering Consultants 7

Pipework and Ancillaries

Secondary Buffer Vessels

  • A 1000L buffer vessel is located on each of the two flow paths to the data hall.
  • These act as thermal store for chilled water retention in the event of the chiller plant shutting down

during a mains failure period. Secondary Loop in the Data Hall

  • The chilled water is distributed around the data hall in the form of a loop in the floor void below the

cold aisle with tap offs for each row of IRC.

  • Isolation valves are located around the entire loop such as no more than one IRC in any pod would

be out of service if a section of pipe had to be isolated.

slide-8
SLIDE 8

1 April 2015 Dervan Engineering Consultants 8

In-Row Coolers

In- Row Coolers (IRCs)

  • IRCs are supplied as part of the rack and pod system.
  • Each IRC is complete with its own control system and

motorized 3 port modulating valve.

  • The IRC’s in each Pod provide N+1 redundancy
  • They are also complete with Modbus interface for

communicating with the BEMS.

  • Cooling is designed precisely to match the equipment
  • loads. Capacity grows to meet demand
  • Large volume in room acts as a cold air reservoir
slide-9
SLIDE 9

1 April 2015 Dervan Engineering Consultants 9

In-Row Coolers

IRCs were supplied as part of the rack and pod system (shown in blue below)

slide-10
SLIDE 10

1 April 2015 Dervan Engineering Consultants 10

Mechanical Ventilation

  • Transformer and LV switch rooms Extract Fans operated by a temperature sensor
  • Data Hall UPS Room / post discharge fire suppression system Extract fans
  • Battery room extract fans operated by a temperature sensor
  • Data Hall area heat recovery ventilation unit
slide-11
SLIDE 11

1 April 2015 Dervan Engineering Consultants 11

Electrical System Overview

  • 2MVA+ supply
  • 2 x 2MVA Transformers (2N)
  • 2 x 2.5MVA Generators (2N)
  • 2 x 2MVA Form 4 LV

Switchboards (2N)

  • 2 x 4 x 400kVA/360kW UPS

(2N+1)

  • Dual supplies to chillers and

MCC’s (2N)

slide-12
SLIDE 12

1 April 2015 Dervan Engineering Consultants 12

Electrical Redundancy

  • Design is based on 2 No. 2MVA transformers and 2 No. 2.5MVA generators
  • Maximum IT load = 1000kW (2N+1)
  • Target PUE = 1.3
  • Maximum Load for Data Hall = 1400kW
  • Other loads in existing Exchange or Data Hall = 250kW
  • Total Load = 1650kW
slide-13
SLIDE 13

1 April 2015 Dervan Engineering Consultants 13

MV Switchgear & Transformers

MV Switchgear

  • 4 cubicle MV Switchboard – ABB - Unigear

Transformers

  • 2 No. Oil filled, natural air cooled – 2MVA – High

Efficiency AoAk - ABB

  • Own room with louvered doors and mechanical

extract ventilation

  • New 630kVA Cast Resin Transformer to feed

existing exchange - ABB

slide-14
SLIDE 14

1 April 2015 Dervan Engineering Consultants 14

Generators & EGIP

  • 2 No. 2.5MVA diesel power gen sets in

acoustic containers – FG Wilson

  • Each complete with bulk tank to provide a

combined total of 48 hours at full load

  • Generator sets are deemed to be the primary

source of power with ESB a reserve but supplying the load for economic reasons

  • New EGIP – Grid Protection System – 1st in

Ireland

slide-15
SLIDE 15

1 April 2015 Dervan Engineering Consultants 15

Main LV Switchgear

  • 2 No. 2MVA/3000 Amp switchboards connected via normally open bus coupler
  • All breakers are withdrawable and therefore can be added as the load grows
  • Main Board feeds:

Chillers UPS Modules UPS and Air Conditioning in existing Exchange

slide-16
SLIDE 16

1 April 2015 Dervan Engineering Consultants 16

UPS

  • 2 x 4 x 400kVA UPS per site

providing 1080kW (2N+1) - Riello

  • UPS power is delivered to the racks

via dedicated UPS switchboard with plug-in MCCB’s and overhead busbar systems.

slide-17
SLIDE 17

1 April 2015 Dervan Engineering Consultants 17

Miscellaneous

  • BMS System – Standard Controls
  • KNX Lighting Control – Standard Controls
  • Fire Alarm System – Siemens
  • Fire Suppression System - Siemens
slide-18
SLIDE 18

1 April 2015 Dervan Engineering Consultants 18

Thank You for Your Attention End of Presentation