New Multi-Product Pipeline Project Media Presentation 8 December - - PowerPoint PPT Presentation

new multi product pipeline project
SMART_READER_LITE
LIVE PREVIEW

New Multi-Product Pipeline Project Media Presentation 8 December - - PowerPoint PPT Presentation

New Multi-Product Pipeline Project Media Presentation 8 December 2010 1 Objectives of the Presentation To provide an update of the progress of the NMPP Project; Provide the revised cost estimate and delivery schedule; Update on action plans


slide-1
SLIDE 1

Media Presentation 8 December 2010

New Multi-Product Pipeline Project

1

slide-2
SLIDE 2

I ndex Speaker

Introduction and Project Overview Mr Chris Wells Project Delivery Progress, Revised Project Costs and Delivery Schedule Mr Neville Eve Security of Supply Mr Charl Möller Conclusion Mr Chris Wells

To provide an update of the progress of the NMPP Project; Provide the revised cost estimate and delivery schedule; Update on action plans to ensure security of supply; and To provide an overview of processes put in place to mitigate against any further delays and cost increases

2

Objectives of the Presentation

slide-3
SLIDE 3

NMPP GOVERNANCE STEERING COMMITTEE (Dry Run for the Board on 26 November 2010) 17 November 2010

New Multi-Product Pipeline Project

I ntroduction and Project Overview

3

Mr Chris Wells

slide-4
SLIDE 4

Background and Context: NMPP Project

4

  • The Moerane Commission Report on fuel shortages in late 2005 noted, that additional pipeline

capacity was "urgently required to supply the inland markets" and recommended that Petronet (now Transnet Pipelines) expedite the development of a new pipeline from Durban to Gauteng.

  • The DME in its strategic document entitled “The Energy Security Master Plan – Liquid Fuels

(August 2007)”, states that: “When it comes to infrastructure investments in the South African liquid fuels sector, in the next 5 years, the single most important recommendation is the approval of a new appropriately sized, properly integrated pipeline, which should come on line in the 2nd quarter of 2010 at the latest.” NMPP I nvestment: Strategic I ntent

  • To replace the existing 45-year old Durban-Johannesburg Pipeline (DJP - 12 inch)

urgently as it is running at full capacity and nearing the end of its design life

  • To increase the capacity on this critical route (Durban-Gauteng) to meet projected

demand and to ensure security of supply for the long term

I nvestment Overview

  • 555km of 24 inch pipeline (mainline) and 160km of 16 inch pipelines
  • NMPP as a hybrid of ‘Greenfields’ and ‘Brownfields’ project executed over long distances

with difficult terrain would have significant cost and time delivery issues.

  • Upgradable to meet projected demand to 2035 - assuming high GDP growth in future
  • 70 year design life

Urgent drive to secure the supply of fuel to the strategically important inland market

slide-5
SLIDE 5

Overview of NMPP Project

The process to determine the final changes to cost and schedule has been completed and in line with our commitment to be totally transparent, Transnet would like to share with ALL STAKEHOLDERS, a full explanation of these changes:

5

The NMMP Project is within benchmark norms, is fair value and Transnet is confident that the project will be delivered within the revised schedule and cost forecast

slide-6
SLIDE 6

New Multi-Product Pipeline Project

Project Update

6

Mr Neville Eve

Areas to be covered:

  • Project Progress
  • Forecast cost and schedule
  • Explanation of variances
  • Benchmarking results
  • Project delivery assurance
slide-7
SLIDE 7

In lan d te rm in al an d p u m p s ta tio n C o as ta l te rm in al a n d p u m p s ta tio n

K w a Z u lu ‐N a ta l L e s o th o F re e S ta te M p u m a la n g a N o rth ‐ W e s t

V a n R e e n e n L a d ys m ith V re d e M o oirive r H ow ic k D U R B A N

In d ia n O c e a n

P S 1 P S 2 P S 3 P S 4 P S 5 P S 6 P S 7 P S 8 L a n g la a g te K e n d a l W a ltloo S a s o lbu rg K ro o ns ta d K le rk s d orp P otc he fs tro om C o a lbroo k S e c u nd a T a rlto n O R T IA R u s te nb u rg P re to ria W e s t V o lk s ru s t W ilg e J A M E S O N P A R K B e th le he m W itba nk K e y P rop o s e d N M P P T ru nk lin e E xis ting p ip e line (D J P ) C itie s a n d to w ns P um p s ta tion s N MP P Inla nd lin e s E xis ting inla n d n e tw ork N o rth e rn c o rrid o r a lte rn a tiv e A lro d e In lan d te rm in al an d p u m p s ta tio n C o as ta l te rm in al a n d p u m p s ta tio n

K w a Z u lu ‐N a ta l L e s o th o F re e S ta te M p u m a la n g a N o rth ‐ W e s t

V a n R e e n e n L a d ys m ith V re d e M o oirive r H ow ic k D U R B A N

In d ia n O c e a n

P S 1 P S 2 P S 3 P S 4 P S 5 P S 6 P S 7 P S 8 L a n g la a g te K e n d a l W a ltloo S a s o lbu rg K ro o ns ta d K le rk s d orp P otc he fs tro om C o a lbroo k S e c u nd a T a rlto n O R T IA R u s te nb u rg P re to ria W e s t V o lk s ru s t W ilg e J A M E S O N P A R K B e th le he m W itba nk K e y P rop o s e d N M P P T ru nk lin e E xis ting p ip e line (D J P ) C itie s a n d to w ns P um p s ta tion s N MP P Inla nd lin e s E xis ting inla n d n e tw ork N o rth e rn c o rrid o r a lte rn a tiv e A lro d e

Durban Streetworks (26.5km) 93.2% Durban Mainlay (53.9km) 77.7% Mainline (474.3km) 94.6%

NMPP Mainline Progress

slide-8
SLIDE 8

Progress as of 5 December 2010

  • PL1 Welded 474.3 km (100%)
  • PL1 Backfilled 459.1 km (95.1%)
  • PL1 Re-instated 386.1 km (81.4 %)
  • PL1 Hydrotest km 313.7 km (56.5%)
  • Durban Welded 70.0km (98.0%)
  • Durban Backfilled 59.0km (81.3%)
  • Durban Re-instated 11.5km (14.3 %)
  • Durban Hydrotest 0 km (0%)

Figure 1: Road installation directly after Umlaas Canal Figure 2: Durban Street Works Figure 3: Typical Valve chamber construction

NMPP Mainline Progress

slide-9
SLIDE 9

NMPP Terminal 2 Progress

9

Intermediate Phase Scope

  • Planned 50%
  • Actual 42%

Full Scope

  • Planned 17.6%
  • Actual 18.5%
slide-10
SLIDE 10

NMPP Pump Stations Progress

Construction Progress

  • Planned 35.5%
  • Actual 37.5%
slide-11
SLIDE 11

NMPP Project Progress Achievements

I nland Pipelines

Construction completed PL4 – ready for operations by the end of December PL2 & PL3 – RFC by mid December

Mainline

Main River crossings complete (49) Major Wetland crossings complete (481) (95km) Land Acquisitions complete (1148 properties) All Environmental Approvals in place 550 km in the ground

Pump Stations

Major equipment procured On schedule Excellent safety record

Terminals

TM2 on schedule TM1 re-setup complete Excellent safety record

11

This important strategic project is on track to meet the revised schedule

slide-12
SLIDE 12

Revised Dates: Ready for Hot Commissioning / Operation (RFC / RFO)

12

Component RFC RFO

PL4 Inland Pipeline 1 Dec 2010 31 Dec 2010 PL2 & 3 Inland Pipelines 18 Dec 2010 mid Jan 2011 PL1 24 inch Trunk Line and Inland Pump Stations (PS1, PS3, PS5) 30 Sept 2011 31 Dec 2011 Inland Terminal (TM2) 30 Sept 2012 31 Dec 2012 Coastal Terminal (TM1) 30 Sept 2013

31 Dec 2013

NMPP Project Scheduled Completion

slide-13
SLIDE 13

NMPP Cost Changes: Context and Background

13

Date Feb ‘08 Feb ‘09 Nov ‘09 Nov ‘10 ETC R11.1bn R12.67bn R15.4bn R23.4bn

Basis of Estimate

  • Bottom-up detail

analysis

  • Forecast off

Feb 08 base

  • Forecast off Nov

08 base

  • Detail bottom-up

analysis (re-based) Risks

  • Aggressive

timelines

  • Full FEL3 Front

End Engineering Design (FEED)

  • Risks largely

unknown

  • Optimistic

timelines

  • Substantial

Engineering Changes (terminals & facilities)

  • Definition

reduced to FEL 2 (pre-FEED)

  • Optimistic

timelines

  • Engineering

changes (TM1)

  • Full FEL 3 not

achieved

  • Realistic timelines
  • Validated detail

engineering progress

  • Full FEL 3 achieved
  • MAC / MCC

Comments

  • Demand /

Schedule Driven

  • Pre-engineering

changes Impact

  • Scope defined
  • Optimistic EPCM

costs / strategy

  • Opportunity

missed to re- estimate project

  • Scope definition

reduced

  • Re-estimate

Opportunity missed

  • Incomplete

engineering progress data

  • High level of

confidence/ credibility of estimated cost and schedule

  • Project re-

structured

  • Integrated EPCM &

Owners team

slide-14
SLIDE 14

Review of NMPP Estimation process followed

  • Bottom-up re-estimation process provides a high level of confidence in the cost

estimates for both Transnet and AWP

  • Performed a detailed analysis of all related cost elements and estimates
  • Reconstructed the revised estimate
  • Performed a detailed risk analysis of all revised cost elements
  • The re-estimate was undertaken:
  • By an international team of experienced corporate estimators
  • In conjunction with Transnet’s Team
  • With peer review assurance by Global & Regional experts

14

Revised estimate provides a high level of confidence that the forecast final cost target will be achieved.

slide-15
SLIDE 15

Reconciliation of Latest Estimated Total Cost (ETC)

15

Analysis of Increase in ETC (R billion)

0.7

15.4

4.3

11.1

10.8 Final ETC (All risks) (P 70)

23.4

EPCM Risk

0.5

Risk Adjustment to P70

0.3

Transnet ETC (P50)

22.6

Risk Adjustment

Revised AWP ETC (P50)

21.9

Cost increase

6.5

ETC Nov 2009 (P 50)

Cost increase

ETC Feb 2009

Revised ETC (P70) a fair reflection of cost based on detail reviews and benchmarks

slide-16
SLIDE 16

Summary of Cost and Schedule Movements

Movement in Schedule & Budget from February 2008 Board (R11,137bn) to November 2010 Board (R23,4bn) 16

R15.4bn

*

* Driven by regulatory and engineering design requirements

+ R10,844bn appears reasonable and conservative when compared to the validation

  • f the AWP re-

estimate +

slide-17
SLIDE 17

Detail reasons for increase: Pipeline

Reason Value

1 Escalation in steel prices ZAR 1.519 B 2 Pipeline construction ZAR 0.535 B 3 Negotiated final account ZAR 1.059 B 4 Increased wall thickness 5 Increase in crossings 6 Increase in pipe length (re-location of TM 1)

Total

Reason R billion

  • Escalation in steel prices and quantity (increase in world steel

prices, increase in pipe wall thickness, transport cost) 1.522

  • Inland Lines Compensation Events (delays due to EIA, pipe

supply, servitude availability, move-arounds, field joint coating development) 0.342

  • Trunkline revised scope after Stage 1 validation (number of

valves, valve chambers, 29km longer pipe trunkline, end of line, cathodic protection, crossings) 0.8

  • Weather, additional hydrotesting, production (actual welding

production 61% of estimate and actual laying of pipe 72% of estimate); escalation 0.4

  • Growth / Other

0.064

Total 3.128

17

slide-18
SLIDE 18

Reason R billion

  • Additional Pump Station PS3

0.133

  • Addition of 2 metering stations PS7 & PS8

0.059

  • HV Electrical Supply and Sub Stations

0.081

  • Spill basin; acoustic pump housing; blast proofing

buildings incl. doors; building growth; paving embankments; bulk earthworks; internal surfacing; piping class change; additional diesel storage tanks; fence specification; extended construction period; additional isolation valves 0.083

  • Power Generators

0.177

  • Growth / Other

0.017

Total 0.550

18

Detail reasons for increase: Pump Stations

slide-19
SLIDE 19

Engineering, Procurement and Construction Management Forecast

  • Total EPCM forecast is R2.88bn
  • EPCM forecast is 13% of forecast total installed cost
  • Home office services (engineering, procurement, project management) is 9,4% of forecast total installed cost
  • Field services is 3,6% of forecast total installed cost

EPCM FORECAST I NDEPENDANT PROJECT ANALYSI S (I PA) TABULATI ONS

Total EPCM 13% 22.3% Home office Services 9.4% 18%

* Note 1

Construction management 3.6% 4.3%

*Note 1 – Based on process plant, includes Front End Engineering Design

19

EPCM cost within acceptable levels compared to industry benchmark

slide-20
SLIDE 20

20

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Feb‐08 Class 3 Estimate Oct‐08 Change in Contracting Strategy Mar‐09 Change in Purchasing Strategy Jan‐10 TM1 Option 6 Jul‐10 Current ‐ Baseline Other concurrent issues, which typically are resolved prior to emergence from FEED, would contributed to the overall delay, including: 1 Servitude Acquisition Delays 2 Environmental Impact Assessment 3 Extensive Scope Changes Post Feed (From Feb‐08)

Procurement Procurement Construction

Engineering

Construction Procurement Construction

Engineering

Procurement Construction

Date Event

Schedule Analysis (Key Contributors)

Engineering 2008 2009 2010 2011 2012 2013 Engineering

Procurement Construction

2007 Engineering

Schedule Analysis

slide-21
SLIDE 21

Latest ETC benchmarked against peer projects

Benchmarking: Methodology

  • Turner & Townsend, an independent international benchmarking authority, has undertaken a

review of the NMPP Project in comparison to other global pipeline projects.

  • Source data- Joint Independent Performance (JIP) Forum database. 700 facilities and USD 300

billion projects value

  • Experts – piping and fuel distribution experts (Australia & USA) – external & internal
  • Projects – Previous completed piping projects benchmarked by Turner and Townsend

Pipelines (20 projects)

  • Comparator data, normalised to RSA conditions (escalation/productivity etc.)
  • Initially 34 pipelines reviewed - 20 from Asia/Australia/USA chosen as comparators
  • Ranging from 170 – 1141km
  • Similar terrain
  • 50 year lifespan

Pump Stations & Terminals (7 projects)

  • Unique, fit for purpose design and therefore no common basis for benchmarking
  • Converted component data to common basis
  • Review of market related rates per component

Benchmark Value

  • R15.971bn out of R17.673bn (81%) excluding Owner’s Cost, Sunken Costs, MAC
  • Total project cost R21.98bn (excluding owner’s cost for comparability) used for the

benchmarking exercise

21

Projects compared are commercial pipelines - the NMPP Project includes legacy project allowances commensurate with national security of supply responsibility

slide-22
SLIDE 22

Benchmarking: Pipeline

  • Review included 550km of 24” and 160km of 16”
  • Percentage below indicates how the NMPP

pipeline compares to the comparator norm

  • Construction
  • 9%
  • Materials

+ 14%

  • Overall
  • 13.4%

22

67 22 110 50 69

Transport Field Coating Location Steel price Pipeline Coating

Increases - R million

Variances

slide-23
SLIDE 23

Benchmarking: Pump Stations (on the basis of KW/R)

Pump stations (7 projects)

  • Review of market conditions, favourable 75% of rates reviewed (earthwork, excavation,

concrete, formwork, steel , rebar and pumps)

  • Normalised rates from both Gauteng & KwaZulu Natal
  • Comparison of pump station components against norms

Result

  • Tendered rates compare very favourably to prevailing market conditions at the time:
  • Costs are above norm (Based on KW/R comparison)
  • Reasons for variances: (legacy allowances & time related costs)
  • Security, explosion resistant control room and electrical substations (R80million)
  • NKP (R70 million)
  • Generators/Diesel storage (R180 million)
  • Additional standby pumps (R147 million)
  • Escalation (R75 million)
  • Sound proofing (R28 million)
  • 50 year flood basin (75mpa concrete) (R10million)

I tem NMPP Comparator %

Clearing and grubbing m² R 2.10 R 7.80 72% Excavation m³ R 19.30 R35.40 45% Concrete 30mpa m³ R 989 R1055 6.1% Rebar ton R7941 R9190 13%

23

Benchmarking: Pump Stations

slide-24
SLIDE 24

Project Management Summary

24

  • Detailed and thorough re-baselining exercise is complete with full involvement of

the EPCM service provider and Transnet teams

  • The delivery team has been substantially strengthened, together with greater

collaboration, integration and alignment and a new leadership team is in place

  • Reporting is accurate and reflects current performance
  • Enhanced governance and controls along with updated project processes,

systems and tools implemented

  • Rigorous change management control has been implemented
  • Engineering production management process enhanced, engineering review

completed and peer reviews undertaken Transnet is confident that the NMPP Project has been structured for success and will be delivered to meet the revised cost and schedule commitments

slide-25
SLIDE 25

.

  • Stream 8: Stakeholder Engagement and Reputation Management
  • NERSA
  • DOE
  • DPE
  • Recommendations

Security of Supply

25

Mr Charl Möller

slide-26
SLIDE 26
  • An intelligent pigging exercise has be done which shows that the DJP will not need

to be down-rated as was initially anticipated

  • A rigorous maintenance and repair programme will however continue, to ensure

the integrity of the DJP

  • As a mitigating strategy Transnet is planning to move 10Ml/week to rail and this

will enable additional volumes to move from road to the DJP

Way Forward and Action Plan: DJP

26

Whilst technically the down-rating initially expected is not required, Transnet from a contingency perspective will place 10Ml/w on rail.

slide-27
SLIDE 27

NMPP GOVERNANCE STEERING COMMITTEE (Dry Run for the Board on 26 November 2010) 17 November 2010

New Multi-Product Pipeline Project

Conclusion and Way Forward

27

Mr Chris Wells

slide-28
SLIDE 28

I n Closing

28

NMPP is a key strategic investment for South Africa to secure the supply of petroleum products to the market over long term. In-depth reviews and benchmarking indicates that: Scope and engineering changes to the project were necessary and justified to ensure that the project meets the set objectives; Latest cost estimates of project is a fair reflection of the total costs of an asset of this nature, complexity and magnitude. Transnet is committed to roll out the investment in line with the licence agreement and timelines agreed with the Regulator. Security of supply will remain a critical deliverable throughout the construction and commissioning phase of the project and will be robustly monitored. The impact of the additional costs will not have a material impact on the pump price of fuel and based on

  • ur current assessment, is estimated to be less than 5 cents per litre.

All stakeholders will be fully briefed, including SAPIA, DoE, DPE and the media.

Competitive and world class multi-product pipeline that will secure the supply of petroleum products to the inland market safely, cost effectively and in an environmentally friendly manner

Outcome of NMPP Project