China Scan Tour on Ground Improvement Technologies Prepared by the - - PowerPoint PPT Presentation
China Scan Tour on Ground Improvement Technologies Prepared by the - - PowerPoint PPT Presentation
China Scan Tour on Ground Improvement Technologies Prepared by the ASCE G-I China Scan Tour Team Presented by Jie Han, Ph.D., PE, F.ASCE Glenn L. Parker Professor The University of Kansas China Scan Tour on Ground Improvement Technologies
China Scan Tour on Ground Improvement Technologies from May 23 to 26, 2018 Followed by the 2nd US-China Workshop on Ground Improvement Technologies on May 27, 2018
- Organized by the G-I Soil Improvement Committee
- Sponsored by ASCE Geo-Institute
Scope of the scan tour was:
- to identify and document new and implementable
soil improvement technologies successfully used in China, with the goal of implementing the technologies into the current U.S. GeoTech Tools selection system.
China Scan Tour Team
- Prof. Jie Han, the University of Kansas (chair); Dr. Jose Clemente, Bechtel (co-chair)
- Dr. James Collin, the Collin Group (G-I board representative)
- Prof. Jie Huang, the University of Texas at San Antonio; Rob Jameson, Malcolm
- Prof. Prabir K. Kolay, Southern Illinois University Carbondale
- Prof. Cheng Lin, the University of Victoria, Canada; Dr. Guoming Lin, Terracon
- Dr. Antonio Marinucci, V2C Strategists, LLC; Dr. Lisheng Shao, Hayward Baker, Inc.
- Prof. Leon van Paassen, Arizona State University; Dr. David Yang, JAFEC USA, Inc.
Scan Tour Route
Project 1 Super-Deep (105 m/345 ft) Diaphragm Wall Shanghai
Suzhou River Deep Drainage and Storage Facility
Suzhou river Huangpu river
- Circular shafts
60 to 70 m (195 to 230 ft) deep
- Connected by 15.3 km
(9.5 mi) of deep tunnels
- r pipelines with
diameters ranging from 8 to 10 m (26 to 33 ft)
- Deep tunnels at depths
- f 40 to 60 m (130 to
195 ft) along the Suzhou River
Credit: Shanghai Foundation Engineering Group CP., LTD., The Third Engineering Company
Project 1 Super-Deep (105 m/345 ft) Diaphragm Wall Shanghai
(110 ft) (195 ft) (112 ft) (345 ft) (345 ft) (162 ft)
Wall thickness = 3.3 to 4.9 ft
Credit: Shanghai Foundation Engineering Group CP., LTD., The Third Engineering Company
Project 1 Super-Deep (105 m/345 ft) Diaphragm Wall Shanghai
- Max. excavation depth
= 150m (492ft)
Credit: Shanghai Foundation Engineering Group CP., LTD., The Third Engineering Company
Project 1 Super-Deep (105 m/345 ft) Diaphragm Wall Shanghai
Credit: Shanghai Foundation Engineering Group CP., LTD., The Third Engineering Company
Super-Deep (105 m) Diaphragm Wall
Bauer BC40 hydromill mounted on a Bauer MC128 crane Bauer BC40 on a Bauer MC96 & Jintai SG60A hydromills Support cranes and hydromills
- Max. excavation depth
= 80 m (262 ft)
- Max. excavation depth
= 150m (492 ft)
Super-Deep (105 m) Diaphragm Wall
Milling a 300 mm (12 in)
- verlap into each primary
panel using the hydromill. Pre-installed steel pipes for a post-construction freezing system at the panel ends. Option for exterior grouting patterns at the panel joints.
Panel No. Start Date Installation Time (hours) Measured Verticality Over- break ZQ2 30 Dec 2017 120 1/3750 114% ZQ3 06 Jan 2018 76 1/1600 106% ZQ2-3 12 Jan 2018 297 1/1000 109% Credit: Shanghai Foundation Engineering Group CP., LTD., The Third Engineering Company
Super-Deep (105 m) Diaphragm Wall
Hydration and settling tanks Desanding and desilting units Quality assurance / quality control performed on the bentonite slurry
Project 2 Dynamic Compaction + Vacuum Dewatering
DDC typical suitable for partially saturated, non-plastic
- r low plasticity soil (e.g., PI<
8) where the groundwater table is sufficiently deep. DDC also effective for low permeability silt and clay, provided a proper drainage and/or dewatering system is installed Quick process, No fill or temporary matting (i.e., no preload or surcharge fill), Cost effectiveness for massive treatment, Straightforward, relatively simple installation, & construction equipment.
Project 2 Dynamic Compaction + Vacuum Dewatering
- Improve dredged land for a 1 km
(0.6 mi) long municipal road. The total treatment area is 28,000 m2 (6.9 acre).
- Achieve a minimum allowable
bearing capacity of 120 kPa (2,500 psf), and a subgrade modulus no less than 25 MPa (3,625 psi)
Credit: Shanghai GeoHabour Co.
Credit: Shanghai GeoHabour Co.
Project 2 Dynamic Compaction + Vacuum Dewatering
Process 1st pass tamping 2nd pass tamping 3rd pass tamping Ironing Settlement (cm) 23.4 31.3 7.1 10.8 Total settlement (cm) 72.6 Credit: Shanghai GeoHabour Co.
Dynamic Compaction + Vacuum Dewatering
Project 3 Detachable Anchor & Jet Grouting
Excavation & Ground Water Cut-off by:
- Detachable anchor
- Jet grouting in
anchor bonding zone
- Soil mixing wall
with recoverable W-beams
- Two-story basement excavation to
12 m depth in very difficult soils
- GWT at 0.7 m depth
Credit: Zhejiang Zhongqiao Prestress Equipment Co., Ltd. & The Architectural Design and Research Inst. of Zhejiang Univ. Co., Ltd.
Project 3 Detachable Anchor & Jet Grouting
Detachable Anchor
- Apply 2~3 ton tension on
release strand
- Unlock wedges
- Recover working strands
Credit: Zhejiang Zhongqiao Prestress Equipment Co., Ltd. & The Architectural Design and Research Inst. of Zhejiang Univ. Co., Ltd.
Project 3 Detachable Anchor & Jet Grouting
Project 3 Detachable Anchor & Jet Grouting
Reusable W-beams in the soil mixed columns Beams coated with a tar & grease mix Beams vertically inserted into fresh mixed column Above soil mixing, beams wrapped with styrofoam sheets & cast into concrete grade beam After excavation finished, W-beams pulled out
Project 4 Vacuum Consolidation
Masive dredged land for a new city
Project 4 Vacuum Consolidation
- Vacuum preloading
- Vacuum preloading
+ air injection
- PVD electro-osmosis
dewatering and consolidation Large reclaimed land (2.53 km2
- r 624 acres)
Credit: Huadong Engineering Corporation Ltd.
Project 4 Vacuum Consolidation
- 3 to 10 meters
dredged fill, soft silts & clays W = 50~80%
- Native alluvial
deposits of silts & clays W=30 ~ 70%
- Target bearing
capacity of 40 to 80 kPa for roads and airport runways.
- The long-term
settlement target was 30 centimeters over 15 to 30 years.
Credit: Dr. Huayang Lei Menard (2001)
Project 4 Vacuum Consolidation
Vacuum tubes & PVDs used to inject high pressure air to prevent clogging & facilitate water movements to speed up consolidation
Credit: Dr. Huayang Lei Credit: Dr. Huayang Lei
Project 4 Vacuum Consolidation
Project 4 Vacuum Consolidation
Vacuum consolidation + water surcharge
Project 4 Vacuum Consolidation
Project 4 Vacuum Consolidation
Multiple small water-jet vacuum pumps used on another project site (not on the tour)
Credit: Dr. Jie Han
Project 4 PVD Electro- Osmosis Test
Jones et al. 2011
Project 4 PVD Electro-Osmosis
- 1000 m2 test area
- measured settlement
500~ 750 mm in 32 days of electro-
- smosis
consolidation
- Energy consumption
4~7 kwh/m3
Credit: Hangzhou Shenyuan Environmental Sci-Tech Co. Ltd
Project 6 Soil Mixing, Pre-stressed Hollow Concrete Pile, Mass Mixing, & DAQ
- New 50.8 km Hangzhou
Beltline, 32.5-km long section to be constructed over soft soil
- Soft soil thickness 2 ~ 44 m
- Freeway embankment
heights 2 ~ 6 m, & 5 to 6 m near bridge-approach embankment
- Project site in a plain river
network area
- f Hangjia Lake.
No. Soil layer w (%) Es (MPa) c (kPa) φ(°) ② Soft soil 1 43.5 3.07 9.8 4.6 ③ Soft soil 2 40.9 3.23 10.3 5.3
Project 6 Counter Rotation DSM
Counter rotation deep mixing: 0.5m column
- 10m penetration
- Grout pumped though
inner casing
- One electric motor with
gear box to counter rotate inner and outer casing
- Grease sealed between
casings
Project 6 Wet Mass Mixing
In-situ soil
Soft soil
Moving direction Soft Clay W≤60% Mixing Ratio 1m3 Cement (%) Fly Ash (%) Admix (%) Cement (Kg) Fly Ash (Kg) Admix (Kg) 3.0 3.0 \ 47.4 47.4 \
Full system DAQ
Credit: China Railway Construction Co.
Project 6 Pre-stressed Bamboo Shape Hollow Concrete Pile
The bamboo-shaped or nodular pipe piling system (static drill rooted nodular [SDRN] pile system) Composite system combines pile foundations with soil mixing and grouting Start with a partially grouted and partially soil mixed hole. Insert hollow precast pipe sections Typically used for structural support of structures and in conjunction with column- supported embankments.
Project 6 Pre-stressed Bamboo Shape Hollow Concrete Pile
Other GI Technologies Presented in GI Workshop in Shanghai
Other GI Technologies Presented in GI Workshop in Shanghai
Credit: Dr. Gang Zheng
Other GI Technologies Presented in GI Workshop in Shanghai
Credit: Dr. Hanlong Liu
T-Shape Soil Mixing
Credit: Dr. Songyu Liu