Tim Hanley, P.E. WisDOT Project Manager Daniel Schave, P.E. WisDOT - - PowerPoint PPT Presentation

tim hanley p e wisdot project manager daniel schave p e
SMART_READER_LITE
LIVE PREVIEW

Tim Hanley, P.E. WisDOT Project Manager Daniel Schave, P.E. WisDOT - - PowerPoint PPT Presentation

Tim Hanley, P.E. WisDOT Project Manager Daniel Schave, P.E. WisDOT Project Leader May 16, 2017 Review purpose and needs for the project Identify alternatives (solutions) to address the needs Discuss next steps 2 3 Regional


slide-1
SLIDE 1

Tim Hanley, P.E.– WisDOT Project Manager Daniel Schave, P.E.– WisDOT Project Leader May 16, 2017

slide-2
SLIDE 2

 Review purpose and needs for the project  Identify alternatives (solutions) to address the

needs

 Discuss next steps

2

slide-3
SLIDE 3

3

slide-4
SLIDE 4

 Regional and local traffic  Approximately 3,700 vehicles per day

  • 16% trucks

 Constructed in 1998  Existing asphalt 8 inches thick asphalt  24 crashes in 5 year period

  • Run-off-the-road crashes present

 Ice and snow primary factors

4

slide-5
SLIDE 5

Purpose

 Maximize the life of the pavement  Improve safety

Needs

 Deteriorating pavement (cracking and rutting)  Four culvert pipes in poor condition  Deteriorating railroad crossing pavement

5

slide-6
SLIDE 6

6

slide-7
SLIDE 7

7

slide-8
SLIDE 8

8

 Four culverts are in poor condition

  • Proposing to replace three

 Two by railroad in Oxford  One by 5th Drive

  • Repair one

 1 mile east of 5th Drive

 Size/location unchanged

slide-9
SLIDE 9

9

slide-10
SLIDE 10

10

slide-11
SLIDE 11
  • Resurface
  • Recycle
  • Replacement

 All alternatives include:

  • Culvert pipe repair
  • Railroad crossing surface replacement

 Five-day detour required (WIS 13, WIS 21 and I-39)

  • Centerline rumble strips
  • Safety edge installation

11

slide-12
SLIDE 12

12

slide-13
SLIDE 13

 Reduce head-on fatal/injury crashes by 44%  Increase “awareness”

  • Inattentive driving
  • Limited Visibility

 Rain, snow or fog

 Low installation cost  Not installed near intersections or commercial

driveways

13

slide-14
SLIDE 14

 6% reduction in all crashes  Low cost of installation  Reduces hazard of low shoulders  Creates “smooth transition” back onto roadway

14

Normal Edge Safety Edge

slide-15
SLIDE 15

15

Resurface

  • Mill (remove) 2 inches of pavement
  • Place 1.75 inches of new pavement

 Temporarily eliminates rutting/cracking.

  • Underlying issues not addressed.

 Limited traffic impacts (flagging operation, 5 day detour)  Cost = $1.5 million – $2 million

slide-16
SLIDE 16

16

Remove 2 inches of asphalt Place 1.75 inches of asphalt Install centerline rumble strips Lane and shoulder width unchanged

slide-17
SLIDE 17

17

 Recycle

  • Mill (remove) 2 inches of asphalt
  • Cold-in-place recycle 4 inches of asphalt
  • Place 1.75 inches of new asphalt

 Addresses more of the rutting and cracking issues  Limited traffic impacts (flagging operation, five-day

detour)

 Cost = $2.4 million – $3 million

slide-18
SLIDE 18

18

Remove 2 inches of asphalt Recycle 4 inches of asphalt Place 1.75 inches of asphalt Install centerline rumble strips Lane and shoulder width unchanged

slide-19
SLIDE 19

19

 Replacement

  • Remove all pavement
  • Replace with new pavement

 Removes pavement not past its useful life (wastes money)  Possible real estate impacts (slope widening)  Greater traffic impact (four-month detour)  Cost = $3.7 million – $4.5 million

slide-20
SLIDE 20

20

Remove all existing asphalt Replace with 6 inches of new asphalt Install centerline rumble strips Lane and shoulder width unchanged Slopes possibly widened

slide-21
SLIDE 21

21

 Five-day detour (Monday – Friday)  State signed detour route via WIS 13, WIS 21, I-39  Local access maintained at all times

  • V. Oxford

Closure

slide-22
SLIDE 22

 Meet with local officials: April 26, 2017  Public involvement meeting: May 16, 2017  Select preferred alternative: June 2017  Project design complete: August 2018  Construction currently scheduled: Summer 2019

22

slide-23
SLIDE 23

 Daniel Schave, P.E.

  • WisDOT Project Leader
  • 715-421-8084
  • daniel.schave@dot.wi.gov

23