Tim Hanley, P.E. WisDOT Project Manager Daniel Schave, P.E. WisDOT - - PowerPoint PPT Presentation
Tim Hanley, P.E. WisDOT Project Manager Daniel Schave, P.E. WisDOT - - PowerPoint PPT Presentation
Tim Hanley, P.E. WisDOT Project Manager Daniel Schave, P.E. WisDOT Project Leader May 16, 2017 Review purpose and needs for the project Identify alternatives (solutions) to address the needs Discuss next steps 2 3 Regional
Review purpose and needs for the project Identify alternatives (solutions) to address the
needs
Discuss next steps
2
3
Regional and local traffic Approximately 3,700 vehicles per day
- 16% trucks
Constructed in 1998 Existing asphalt 8 inches thick asphalt 24 crashes in 5 year period
- Run-off-the-road crashes present
Ice and snow primary factors
4
Purpose
Maximize the life of the pavement Improve safety
Needs
Deteriorating pavement (cracking and rutting) Four culvert pipes in poor condition Deteriorating railroad crossing pavement
5
6
7
8
Four culverts are in poor condition
- Proposing to replace three
Two by railroad in Oxford One by 5th Drive
- Repair one
1 mile east of 5th Drive
Size/location unchanged
9
10
- Resurface
- Recycle
- Replacement
All alternatives include:
- Culvert pipe repair
- Railroad crossing surface replacement
Five-day detour required (WIS 13, WIS 21 and I-39)
- Centerline rumble strips
- Safety edge installation
11
12
Reduce head-on fatal/injury crashes by 44% Increase “awareness”
- Inattentive driving
- Limited Visibility
Rain, snow or fog
Low installation cost Not installed near intersections or commercial
driveways
13
6% reduction in all crashes Low cost of installation Reduces hazard of low shoulders Creates “smooth transition” back onto roadway
14
Normal Edge Safety Edge
15
Resurface
- Mill (remove) 2 inches of pavement
- Place 1.75 inches of new pavement
Temporarily eliminates rutting/cracking.
- Underlying issues not addressed.
Limited traffic impacts (flagging operation, 5 day detour) Cost = $1.5 million – $2 million
16
Remove 2 inches of asphalt Place 1.75 inches of asphalt Install centerline rumble strips Lane and shoulder width unchanged
17
Recycle
- Mill (remove) 2 inches of asphalt
- Cold-in-place recycle 4 inches of asphalt
- Place 1.75 inches of new asphalt
Addresses more of the rutting and cracking issues Limited traffic impacts (flagging operation, five-day
detour)
Cost = $2.4 million – $3 million
18
Remove 2 inches of asphalt Recycle 4 inches of asphalt Place 1.75 inches of asphalt Install centerline rumble strips Lane and shoulder width unchanged
19
Replacement
- Remove all pavement
- Replace with new pavement
Removes pavement not past its useful life (wastes money) Possible real estate impacts (slope widening) Greater traffic impact (four-month detour) Cost = $3.7 million – $4.5 million
20
Remove all existing asphalt Replace with 6 inches of new asphalt Install centerline rumble strips Lane and shoulder width unchanged Slopes possibly widened
21
Five-day detour (Monday – Friday) State signed detour route via WIS 13, WIS 21, I-39 Local access maintained at all times
- V. Oxford
Closure
Meet with local officials: April 26, 2017 Public involvement meeting: May 16, 2017 Select preferred alternative: June 2017 Project design complete: August 2018 Construction currently scheduled: Summer 2019
22
Daniel Schave, P.E.
- WisDOT Project Leader
- 715-421-8084
- daniel.schave@dot.wi.gov
23