public involvement meeting january 30 2018 wisdot north
play

Public Involvement Meeting January 30, 2018 WisDOT North Central - PowerPoint PPT Presentation

Public Involvement Meeting January 30, 2018 WisDOT North Central Region Jim Volkmann, P.E. Project Manager EMCS, Inc. Stephanie Christensen, P.E. Consultant Designer Project location Project purpose and need


  1. Public Involvement Meeting January 30, 2018

  2.  WisDOT North Central Region  Jim Volkmann, P.E. – Project Manager  EMCS, Inc.  Stephanie Christensen, P.E. – Consultant Designer

  3.  Project location  Project purpose and need  Proposed improvements  Real estate needs  Construction staging  Current project schedule  Discussion

  4.  WIS 47/55 importance  Regional route for truck and passenger vehicles  Primary link from the Menominee Reservation to the city of Shawano  Marked bicycle route between Old Lake Road and Curt Black Road  WisDOT’s objective is to ensure the safe and efficient operations of the state’s highway system while supporting local access

  5.  Identified needs  Deteriorating pavement (resurfaced in 2000)  Deteriorating railroad crossing surface with need for improved signals and new gates  Curb ramps do not meet ADA (Americans with Disabilities Act) requirements  Guardrails, signing, and pavement marking do not meet current standards  Some curb and gutter, inlets, and culverts require repair

  6.  The absence of turn lanes at some intersections results in conflicts between turning and through traffic  The existing 3-foot paved shoulders do not adequately accommodate bicycles or pedestrians

  7.  Improvements recommended to keep traffic moving safely and efficiently  Resurface WIS 47/55 and pave 5-foot shoulders  Replace the railroad crossing surface and install new signals and gates  Reconstruct all curb ramps to meet ADA requirements  Repair spot locations of curb and gutter  Replace guardrails and two drainage culverts

  8.  Install new signing, pavement marking, and centerline rumble strips  Modify intersections to improve traffic flow and efficiency  County H and Maple Avenue  Frailing Lane  County A

  9.  County H and Maple Avenue conditions  Transition from high speed to lower speed urban area  Speed limit lowered to 40 mph in 2014 to maintain safety  Crash rates are not growing  8 crashes (2007 to 2011)  8 crashes (2011 to 2015)  Crash rates do not warrant changing intersection control (i.e. signals, roundabout, all-way stop)  Intersection modifications proposed to improve traffic flow and efficiency

  10.  County H and Maple Avenue upgrades  Widen the roadway and install pavement markings to accommodate turning traffic  Southbound left-turn lane at County H  Northbound left-turn lane at Maple Avenue  Complete tree clearing to improve sight distance looking north from County H

  11. County H and Maple Avenue Elm Ave Maple Ave Old Keshena Rd

  12.  Frailing Lane conditions  Lack of properly marked turn lanes (2 to 4 lanes)  Driveways near the intersection can cause confusion between through and turning traffic  6 crashes (2011 to 2015)  County A bypass and turn lanes  Do not meet current design standards (length and tapers)  Do not accommodate a continuous paved shoulder through the intersection

  13.  Frailing Lane  Widen the roadway and install pavement markings to accommodate turning traffic  The painted median area will improve traffic flow at the intersection and adjacent commercial entrances  County A bypass and turn lanes  Modify the bypass and turn lanes to meet current design standards  A continuous 5-foot paved shoulder will be provided through the intersection

  14. Frailing Lane

  15. County A

  16.  Permanent fee and temporary limited easements  Intersection modifications  Guardrail grading  Curb ramp upgrades  Acquisition process  WisDOT will acquire real estate  Individual property owner meetings will be held  Begin real estate acquisitions in fall 2018

  17.  Maintaining safety and mobility are important during construction  Proposed traffic impacts  Single lane closures with flagging conditions  One week detour during railroad crossing replacement  Shoulder closures in areas of intersections and guardrails  Local and emergency access will be maintained

  18.  Local officials meetings – February 2017 and January 2018  Public involvement meeting – January 2018  Preliminary plans – Spring 2019  Final environmental document – Spring 2018  Final right of way plat – Summer 2018  Right of way acquisition – Fall 2018 to Fall 2019  Final plans – November 2019  Construction – 2020

  19.  Jim Volkmann, P.E. – WisDOT Project Manager Jim.Volkmann@dot.wi.gov; 715.365.5773  Stephanie Christensen, P.E. – Consultant Designer  schristensen@emcsinc.com; 715.845.1081 wisconsindot.gov/Pages/projects/by-region/nc/wis47/public.aspx

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend