AEMT – Scottish Meeting May 2018
Technical Challenges Emery | Engineering | May 16th, 2018 AEMT - - PowerPoint PPT Presentation
Technical Challenges Emery | Engineering | May 16th, 2018 AEMT - - PowerPoint PPT Presentation
HV Test and Overspeed Facility Technical Challenges Emery | Engineering | May 16th, 2018 AEMT Scottish Meeting May 2018 Agenda 1. Introduction 2. Motor Testing 3. High Speed Rotor Testing AEMT Scottish Meeting May 2018 Introduction
AEMT – Scottish Meeting May 2018
Agenda
- 1. Introduction
- 2. Motor Testing
- 3. High Speed Rotor Testing
AEMT – Scottish Meeting May 2018
◼ Richard Emery ◼ Engineering Manager - Sulzer EMS UK Ltd
◼ Engineering team based in Birmingham ◼ 16 service centres ◼ High Voltage Coil Manufacture
◼ Talk about technology behind two developments
Introduction
17
AEMT – Scottish Meeting May 2018
Agenda
- 1. Introduction
- 2. Motor Testing
- 3. High Speed Rotor Testing
AEMT – Scottish Meeting May 2018
◼ Reasons for not testing…
◼ Cost ◼ Time ◼ Lack of suitable test plant
◼ Eliminate risk…
◼ Expense of trouble shooting ◼ Cost of returning from site ◼ Delay in correcting issues
◼ Ensure performance….
◼ Temperature ◼ Vibration ◼ Balanced currents
Why Test a Motor?
19
AEMT – Scottish Meeting May 2018
◼ Static tests - always performed
◼ Phase resistances ◼ Insulation Resistances (&PI) ◼ Interturn surge tests
◼ These prove windings are ok or otherwise ◼ Suitable for minor overhauls, small machines and site checks ◼ Let’s consider running tests
What Tests to Perform?
20
AEMT – Scottish Meeting May 2018
No-load run allows checks of: ◼ No load currents
◼ Magnitude ◼ Balance
◼ Vibration
◼ Almost sync speed ◼ Cold rotor only
◼ Noise ◼ Bearing condition
◼ Oil flow, temperatures
◼ Load test can be left until motor arrives at site………………..
Benefits of Running Tests
21
Loaded run checks: ◼ Full load currents
◼ Magnitude ◼ Balance
◼ Vibration
◼ Slip speed ◼ Hot rotor
◼ Loaded noise ◼ Rotor currents on load ◼ Cooling performance
AEMT – Scottish Meeting May 2018
◼ Availability of constant load
◼ Machine under test needs to be at constant load for 4-6 hours
◼ Availability of full load
◼ Process doesn’t always allow full load
◼ Shut down time
◼ Need to measure hot winding resistances as soon as possible after shutdown ◼ RTD temperatures don’t tell complete story
◼ Flexibility of testing in Service Centre
◼ Can stop, start or change load at will ◼ Can start at 9:00 and finish at 17:00 ◼ Set up, reconfigure and start quickly
◼ Known test bed stiffness
◼ Repeatable vibration levels
Difficulty of Load testing at Site
22
AEMT – Scottish Meeting May 2018
New test bed gives opportunities:
◼ To modernise from existing ◼ Increase flexibility
Systems reviewed:
◼ Gearbox systems ◼ Variable frequency ◼ AC Generator
Proposed Test System Topologies
23
AEMT – Scottish Meeting May 2018
◼ Frequency 50Hz and 60Hz required ◼ Voltage 400V up to 13800kV ◼ Speed 2 pole to 8 pole ◼ Induction motors
Motor Testing Challenges
24
50Hz M G 1485rpm 49Hz Power supply 50Hz Tx ? 50Hz
AEMT – Scottish Meeting May 2018
◼ Variable speed drive would solve some of the issues ◼ However has technical issues
◼ Harmonics ◼ Switching spikes ◼ Single phase testing ◼ Transformer testing
Variable Frequency Solution
Voltage spikes PWM Waveform
AEMT – Scottish Meeting May 2018
◼ Decision made to go with Diesel Generator driven system
◼ One large, one small for flexibility (2500kW and 700kW) ◼ Similar technology to old test plant
◼ Benefits of Fixed Frequency Supply
◼ Sine wave on stator winding - No dv/dt spikes or harmonics ◼ No harmonic heating, noise, vibration ◼ Allows momentarily overload ◼ Motor starts asynchronously
– higher starting currents – Higher rotor currents
Diesel Generator Test Facility
26
AEMT – Scottish Meeting May 2018
◼ There are a number of accepted ways of testing a motor described in:
◼ IEC60034-29 ◼ IEEE 112
◼ Run at full rated load ◼ Or perform equivalent tests:
◼ Extrapolation
– Needs a load of some sort
◼ Mixed frequency
– Needs 2 power supplies
◼ Forward short circuit
– Needs 2 power supplies
◼ Equivalent tests need explanation
How to Determine a Motor Temperature Rise
27
AEMT – Scottish Meeting May 2018
Sulzer System Layout
28
0 – 415V 50-60Hz M G1 Dyno Transformer G2 3.3, 6.6, 11&13.8kV 2500kW 700kW Consider: 100A Motor Starting current 600A No load current 35A
AEMT – Scottish Meeting May 2018
Agenda
- 1. Introduction
- 2. Motor Testing
- 3. High Speed Rotor Testing
AEMT – Scottish Meeting May 2018
Turbo-Generator Service and Repair
After any inspection or repair ◼ Balance checked (in shop or at site) ◼ Site runs often difficult to manage ◼ Access to all balance locations difficult ◼ In-house balancing quicker and better results
AEMT – Scottish Meeting May 2018
Rotor Running Tests
◼ Balance below first critical speed ◼ Then above critical speed ◼ Then overspeed for 2 mins ◼ Check vibration levels before/after
AEMT – Scottish Meeting May 2018
High Speed Balance Results
Before After
AEMT – Scottish Meeting May 2018
Overspeed Video
https://www.youtube.com/watch?v=1C2pyTtbkjo
AEMT – Scottish Meeting May 2018
The HSB facility was installed in 2002 and operates between 20-30 times a
- year. It is used to test in-house repairs and plus test third party rotors.
High Speed Balance Pit Upgrade
Risk assessments Process improvements Investment in Technology Improved quality Repeatability Cost savings
AEMT – Scottish Meeting May 2018
High Speed Balance - Improvements
◼ Training
◼ Installing ◼ High speed balancing
◼ 5S of test area ◼ Safety risk assessments
◼ Lone worker ◼ Evacuation procedures
◼ Standard test paperwork ◼ Investment in new software
AEMT – Scottish Meeting May 2018
◼ More accurate sensors ◼ Fast Modelling ◼ Simulations possible = Faster process
New Balancing System
36
AEMT – Scottish Meeting May 2018
◼ Replacement of glass banding ◼ 4 pole generator ◼ Initial run shows need for balance
Case Study
37
AEMT – Scottish Meeting May 2018
◼ After a few runs ◼ Balance weights added
Case Study – Final Run
38
AEMT – Scottish Meeting May 2018
Case Study – Final Run
39
AEMT – Scottish Meeting May 2018
◼ Upgrade Drive system ◼ Old drive:
◼ DC Starter ◼ Ward Leonard Set ◼ 11kV Synchronising panel ◼ DC Motor (700rpm) ◼ Gearbox ◼ Large lube system ◼ Emergency gen set ◼ Highly skilled operators
High Speed Balance- Phase 2
40
◼ New drive:
◼ AC Variable frequency drive ◼ Direct drive Motor (5000rpm) ◼ Smaller lube system
AEMT – Scottish Meeting May 2018
Old drive system
Comparison
41
New system
AEMT – Scottish Meeting May 2018
Final Thoughts
Customers expecting: ◼ More testing ◼ More comprehensive reports ◼ Better information Requires smart investments and new technologies
AEMT – Scottish Meeting May 2018 43