Preliminary results from the operation of the fjrst WEEE sorting - PowerPoint PPT Presentation

Preliminary results from the operation of the fjrst WEEE sorting centers in Greece K. Lasaridi*, C. Chroni, C. Abeliotis, G. Protopapas, P . Kirkitsos, A. Dalamaga, R. Charitopoulou, K. Kalafata, C. Angelakopoulos *klasaridi@hua.gr


  1. Preliminary results from the operation of the fjrst WEEE sorting centers in Greece K. Lasaridi*, C. Chroni, C. Abeliotis, G. Protopapas, P . Kirkitsos, A. Dalamaga, R. Charitopoulou, K. Kalafata, C. Angelakopoulos *klasaridi@hua.gr With the LIFE fjnancial instrument Harokopio University of contribution of LIFE14 Athens European Union for the Environment ENV/GR/000858

  2. LIFE RE-WEEE Project Project Title Implementation Duration “Development and Demonstration of Waste January 2016 – August 2020 Electrical & Electronic Equipment (WEEE) Prevention and Reuse Paradigms” Project Objective WEEE reduction and reuse Total Budget strategy implementation 2.161.405 € Action Areas  Greece EC contribution 60%  Belgium LIFE+ Environment Coordinator Co-Benefjciaries Benefjciary Harokopio University of Athens

  3. Impacts of EEE – WEEE life cycle Recycle Consumption of natural resources & Continuous Continuous energy production production Improper of of wastes Improper environme environme appliances ntal ntal Impact to health manageme manageme nt nt Impact to environment Black market economy

  4. LIFE RE-WEEE Project Objectives Prevention and reduction of WEEE production  Priority to re-use and ensuring of high quality management activities Compliance with legislation & policy targets  Standards development for infrastructure and transportation at national and EU level Natural resources and energy savings  Access to cheaper appliances for vulnerable groups

  5. pecifjcations and technical requirements for WEEE SCs Research on existing standards (CENELEC, WEEELabex, OVAM, WRAP, PAS etc.) Proposals to Development of specifjcations and competent technical requirements adjusted to the authorities for Greek situation incorporation of specifjcations into legislation *Specifjcations for the management plan of preparing for reuse (collection, transportation, sorting, storage) * General specifjcations for preparing for reuse * Specifjc issues for preparing for reuse for each WEEE category * WEEE good management practices guide (for public)

  6. Development and operation of Sorting Centres Environmental Impact  Objective : Reduce WEEE driven to treatment/recycling Prepari 300 tn of WEEE annually for preparing for reuse ng for  Reduction of greenhouse gas production reuse actions (5,470 tn CO 2 eq. annually)

  7. LIFE RE-WEEE Project – Sorting Centres 2 new facilities for sorting and preparing for reuse activities – the fjrst in Greece SC SC Central Attica region Macedonia region (CM) Potential for preparing for reuse: all WEEE categories, except Lamps 5 years operation of SCs

  8. Operational plan - 1 Reuse: Put on the market / Source Donation s B2B Contractor PUBLIC SC Municipali ties Sorting / Reporti Preparing for ng reuse RETAILERS W E E E p r f e a p i l a e c r d a W i r t n e f e E r g u o g E s o f m E o e r T echnical Requirements of i i r o n e f t s e LIFE RE-WEEE o r Treatment e u s t t o Facilities f Final dispo sal

  9. Operational plan - 2 Target WEEE for preparing for reuse activities (Activities Group B, C) SC min 1.000 tn/y 2% of WEEE Target (Attica) addressed for min 500 tn/y preparing for reuse (CM) activities to be fjnally reused. Sorting to Sorting to WEEE WEEE categories and initial categories: inspection: Input: ~ 4.000 tn/y (Attica) ~ 2.000 tn/y (CM)

  10. Sorting Centres activities Activities Group Activity Sorting: - WEEE Handling – Loading / Unloading - Load inspection Activities Group - Classifjcation to the WEEE categories A (according to KYA - 23615/651/E.103/2014) - Visual inspection Initial Inspection Activities Group Sorting of WEEE driven for treatment or B preparing for reuse activities Activities Group Preparing for reuse activities / put on the C market (selling or donation)

  11. Attica Sorting Centre Operation since February 2019 Infrastructures:

  12. Attica Sorting Centre Activities: Sorting for Sorting for initial Reception treatment inspection

  13. Attica Sorting Centre Activities: Sorting for initial inspection Weighting

  14. Attica Sorting Centre Activities: Initial inspection WEEE pending for preparing for reuse activities

  15. Attica SC Activities: Screen check Printer check Data eradication Mobile check Hardware check

  16. Attica SC Educational activities

  17. Attica SC Feb – May 2019: Data analysis (4 months data) ACTIVITIES GROUP A ACTIVITIES GROUP B (CATEGORISATION AND (INITIAL INSPECTION/CHECK AND VISUAL INSPECTION) FURTHER SORTING) WEEE FOR WEEE FOR WEEE FOR PREPARING FOR WEEE FOR INITIAL TREATMENT REUSE OR TREATMENT INSPECTION SPARE PARTS 402.909 285.639 4.135 281.504 (kg) 59% 41% 1,45% 98,55% % Tota l 688.548 285.639 (kg) 2 2 SCREENS; SCREEN GROUP A (Pass) Group b (PASS) 2,81% S; 7,26% 4 LARGE; 6 SMALL 14,41% IT; 6 SMALL 31,42% IT; 37,16% 4 LARGE; 29,97% 5 SMALL; 5 45,61% SMALL; 31,35%

  18. Attica SC Indicative outputs - appliances for preparing for reuse SUBCATEGORY / TYPE OF 846 439 6 SMALL IT APPLIANCE kg pieces BACKUP SIM CARD 0 2 2 SCREENS AND EQ. WITH 16 120 GHARGE USB CABLE 0 29 SCREENS HDD 0 5 LAPTOP 6 38 HDMI SPLITER 1 1 LCD 8 79 MP3 PLAYER 0 73 TABLET 1 3 POWER BABK 1 12 298 259 PRINTER 166 25 5 SMALL SERVERS 494 139 DVD PLAYER 7 5 ΑΣΥΡΜΑΤΟ ΤΗΛ 1 3 GRILL 4 8 ΕΚΤΥΠΩΤΗΣ 21 7 MIXER 1 1 ΘΥΡΟΤΗΛΕΦΩΝΟ 3 28 UPS 28 1 ΚΑΛΩΔΙΟ ΔΙΑΦΟΡΑ 1 2 ΑΕΡΟΘΕΡΜΟ 23 11 ΚΑΡΤΑ ΓΡΑΦΙΚΩΝ 1 5 ΑΝΤΑΛΑΚΤΙΚΑ ΘΕΡΜΑΣΤΡΕΣ ΧΑΛΑΖΙΑ 5 1 ΚΙΝΗΤΟ 22 38 ΑΠΟΧΥΜΩΤΗΣ 8 5 ΜΕΛΑΝΙΑ 4 2 ΑΤΜΟ ΣΙΔΕΡΟ 4 1 ΠΛΗΚΤΡΟΛΟΓΙΟ 22 45 ΑΤΜΟΜΑΓΕΙΡΑΣ 7 1 ΡΑΜ 0 1 ΒΡΑΣΤΗΡΑΣ 2 5 ΦΟΡΤΙΣΤΗΣ ΜΠΑΤΑΡΙΩΝ 1 1 ΓΕΝΗΤΡΙΑ 17 2 DESKTOP 110 21 ΔΙΣΚΟΠΡΙΟΝΟ 4 1 ΖΥΓΑΡΙΑ ΚΟΥΖΙΝΑΣ 1 1 ΖΥΓΑΡΙΑ ΜΠΑΝΙΟΥ 4 5 ΘΕΡΜΑΣΤΡΕΣ ΧΑΛΑΖΙΑ 127 177 ΚΑΦΕΤΙΕΡΑ - 1 ΜΠΟΥΚΛΙΕΡΑ 1 1 ΠΟΛΥΕΡΓΡΑΛΕΙΟ 2 1 ΠΟΛΥΜΠΡΙΖΟ 0 2 ΡΑΔΙΟ 17 10 ΡΟΛΟΙ ΧΕΙΡΟΣ 31 14 ΣΕΣΟΥΑΡ 2 3 ΦΡΑΠΕ ΜΙΞΕΡ 1 1 ΦΡΙΤΕΖΑ 3 1

  19. Central Macedonia (Oraiokastro) Sorting Centre Opera tion beginning: July 2019 Infrastructures:

  20. Thank you for your attention! Website: www.reweee.gr Facebook: reweeeGR Harokopio University of T witter: @LReweee Athens

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.