Session 4 Economic Session 4 Economic Session 4 Economic Session 4 - - PowerPoint PPT Presentation

session 4 economic session 4 economic session 4 economic
SMART_READER_LITE
LIVE PREVIEW

Session 4 Economic Session 4 Economic Session 4 Economic Session 4 - - PowerPoint PPT Presentation

th Annual Technical Forum th th 7 th Annual Technical Forum Annual Technical Forum 7 th th Annual Technical Forum Annual Technical Forum 7 Annual Technical Forum Geohazards Geohazards In Transportation In The Appalachian In


slide-1
SLIDE 1

7 7 7 th

th th th th th Annual Technical Forum

Annual Technical Forum Annual Technical Forum Annual Technical Forum Annual Technical Forum Annual Technical Forum Geohazards Geohazards Geohazards Geohazards Geohazards Geohazards In Transportation In The Appalachian In Transportation In The Appalachian In Transportation In The Appalachian In Transportation In The Appalachian In Transportation In The Appalachian In Transportation In The Appalachian Region Region Region Region Region Region US Army Corps of US Army Corps of US Army Corps of US Army Corps of Engineers, Engineers, Engineers, Engineers, Nashville District Nashville District Nashville District Nashville District

Session 4 Economic Session 4 Economic Session 4 Economic Session 4 Economic Impacts of a Impacts of a Impacts of a Impacts of a Karst Karst Karst Karst Foundation Wolf Foundation Wolf Foundation Wolf Foundation Wolf Creek Dam, Creek Dam, Creek Dam, Creek Dam,

slide-2
SLIDE 2

Outline of Topics Outline of Topics Outline of Topics Outline of Topics

  • Project Description.
  • General Background.
  • Reliability Studies.
  • Interim Risk Reduction Measures.
  • Operating Restrictions.
  • Economic Impacts.
slide-3
SLIDE 3

Project Location Project Location Project Location Project Location

slide-4
SLIDE 4

Project Features Project Features Project Features Project Features

slide-5
SLIDE 5

EMBANKMENT PLAN AND EMBANKMENT PLAN AND EMBANKMENT PLAN AND EMBANKMENT PLAN AND SECTION SECTION SECTION SECTION

Cut Off Trench Toe of Random Fill Drainage Blanket

slide-6
SLIDE 6

Foundation Treatment Foundation Treatment Problems Problems

  • Treatment techniques were

inadequate for this geology

  • Most of the alluvium left in place
  • Except for cut-off trench, no

embankment foundation treatment

  • Cutoff trench design and

construction inadequate

slide-7
SLIDE 7

Overhangs and loose rocks w ill only be removed w here Overhangs and loose rocks w ill only be removed w here they cross the line of the trench, since the they cross the line of the trench, since the earthfill earthfill in in the sides of the trench w ill have the function only of the sides of the trench w ill have the function only of stability and not of an absolutely uniform tight contact stability and not of an absolutely uniform tight contact w ith the trench w alls. Tamping w ill w ith the trench w alls. Tamping w ill suppliment suppliment the the regular rolling of the fill as required under the regular rolling of the fill as required under the

  • verhangs and irregular
  • verhangs and irregular salients

salients. .

slide-8
SLIDE 8

Foundation Treatment Foundation Treatment

Cave Cave Solution Features

slide-9
SLIDE 9

1968 Sinkhole

Sinkhole Sw itchyard

slide-10
SLIDE 10

1960 1960 ’ ’s and 70 s and 70 ’ ’s s Remedial Features Remedial Features

Concrete Dam

Earth Emb Sw itchyard

Diaphragm Wall Grout Lines Sw itchyar Wall

Pow erhouse

Diaphragm Wall

Sw itchyard Wall

slide-11
SLIDE 11

1 1 2 3

Post Wall Performance Post Wall Performance Post Wall Performance Post Wall Performance – – Wet Areas Wet Areas Wet Areas et Areas March 2004 March 2004 March 2004 March 2004

Existing Diaphragm Wall

slide-12
SLIDE 12

Risk Risk Risk Risk

Risk is defined as the probability of unsatisfactory

performance times the consequences of the unsatisfactory performance.

For Wolf Creek, based on a breach of the dam the

estimated consequences are up to 350 lives lost and over $3 billion in damages.

How do we establish the probability of

unsatisfactory performance?

It is especially difficult to predict the behavior in

Karst.

slide-13
SLIDE 13

Reliability Analysis for Dams and Reliability Analysis for Dams and Levees Levees Reliability Analysis for Dams and Reliability Analysis for Dams and Reliability Analysis for Dams and Reliability Analysis for Dams and Levees Levees Levees Levees

Excerpts from a presentation by Thomas F. Wolff, Ph.D., P.E. Michigan State University Grand Rapids Branch ASCE September 2002

slide-14
SLIDE 14

General Approaches: General Approaches: Event Tree Event Tree General Approaches: General Approaches: General Approaches: General Approaches: Event Tree Event Tree Event Tree Event Tree

Sand Boil p = 0.5 Carries material p=0.3 Doesn’t p = 0.7 Close to levee p = 0.6 Not close p = 0.4 0.09 0.06 0.35

Most problems of interest involve or could be represented by an event tree.. given some water level :

slide-15
SLIDE 15

Probabilities for the Probabilities for the Event Tree Event Tree - How ?????

  • w ?????

Probabilities for the Probabilities for the Probabilities for the Probabilities for the Event Tree Event Tree Event Tree Event Tree -

  • How ?????

How ????? How ????? How ?????

A) f (Uncertainty in parameter values) Reliability Index

Methods (β)

– Monte Carlo method – FOSM methods

point estimate Taylor’s Series

Mean Value Hasofer-Lind

B) Frequency Basis

– Exponential, Weibull, or other lifetime distribution

C) Judgmental Values

– Expert elicitation

slide-16
SLIDE 16

A) Pr(f) = Function of A) Pr(f) = Function of Parameter Uncertainty Parameter Uncertainty A) A) A) A) Pr(f Pr(f Pr(f Pr(f) = Function of ) = Function of ) = Function of ) = Function of Parameter Uncertainty Parameter Uncertainty Parameter Uncertainty Parameter Uncertainty

Identify performance function and limit

state, typically ln(FS) = 0

Identify random variables, X i Characterize random variables,

– E[X], σ x, ρ

Determine E[FS], σFS Determine Reliability Index, β Assume Distribution and calculate

Pr(f) = f(β)

slide-17
SLIDE 17

Pros and Cons of b, Pros and Cons of b, Pr(U) Pr(U) Pros and Cons of b, Pros and Cons of b, Pros and Cons of b, Pros and Cons of b, Pr(U) Pr(U) Pr(U) Pr(U)

Advantages

– “Plug and Chug” – fairly easy to understand with some training – provides some insight about the problem

Disadvantages

– Still need better practical tools for complex problems – Non-unique, can be seriously in error – No inherent time component – only accounts for uncertainties related to parameter values and models

slide-18
SLIDE 18

B) Frequency-based B) Frequency-based Probabilities Probabilities B) Frequency B) Frequency B) Frequency B) Frequency-

  • based

based based based Probabilities Probabilities Probabilities Probabilities

Represent probability of event per time

period

Poisson / exponential model well-

recognized in floods and earthquakes

Weibull model permits increasing or

decreasing event rates as f(t), well developed in mechanical & electrical appliactions

Some application in material deterioration Requires historical data to fit

slide-19
SLIDE 19

Pros and Cons of Frequency Pros and Cons of Frequency Models Models Pros and Cons of Frequency Pros and Cons of Frequency Pros and Cons of Frequency Pros and Cons of Frequency Models Models Models Models

Advantages

– Can be checked against reality and history – Can obtain confidence limits

  • n the number of

events – Is compatible with economic analysis

Disadvantages

– Need historical data – Uncertainty in extending into future – Need “homogeneous”

  • r replicate data sets

– Ignores site-specific variations in structural condition

slide-20
SLIDE 20

C) Judgmental C) Judgmental Probabilities Probabilities C) Judgmental C) Judgmental C) Judgmental C) Judgmental Probabilities Probabilities Probabilities Probabilities

Mathematically equivalent to

previous two, can be handled in same way

Can be obtained by Expert Elicitation

– a systematic method of quantifying individual judgments and developing some consensus, in the absence of means to quantify frequency data or parameter uncertainty

slide-21
SLIDE 21

Pros and Cons of Judgmental Pros and Cons of Judgmental Probabilities Probabilities Pros and Cons of Judgmental Pros and Cons of Judgmental Pros and Cons of Judgmental Pros and Cons of Judgmental Probabilities Probabilities Probabilities Probabilities

Advantages

– Gives you a number when nothing else will – May be better reality check than parameter uncertainty approach – permits consideration

  • f site-specific

information – Some experience in application to dams

Disadvantages

– Distrusted by some (including some within Federal Agencies) – Some consider values “less accurate” than calculated ones – Non-unique values – Who is an expert?

slide-22
SLIDE 22
  • 1. Major Rehabilitation
  • 1. Major Rehabilitation
  • 1. Major Rehabilitation
  • 1. Major Rehabilitation

Report. Report. Report. Report.

  • 1. Analysis from Major Rehabilitation Report

(MRR)

– Based on analysis of stress indicators – Limit State defined as condition that would require

  • perational restrictions. Limit State threshold selected

by expert elicitation. – Damage accumulation based on projection of instrumentation data coupled with historical pool stages using a Monte Carlo simulation. – Reviewed by an independent panel of experts – Stress indicators show gradual change from 1984 to present – Considered risk to be high – Analysis based on engineering judgment

slide-23
SLIDE 23
  • 2. Screening Portfolio Risk
  • 2. Screening Portfolio Risk
  • 2. Screening Portfolio Risk
  • 2. Screening Portfolio Risk

Assessment Assessment Assessment Assessment

  • 2. Screening Portfolio Risk

Assessment

– In-house Corps expertise – Reviewed MRR and other data – Purpose to determine ranking in severity

  • f Corps dams

– Placed Wolf Creek in the “Urgent and Compelling” category

slide-24
SLIDE 24
  • 3. Independent Peer
  • 3. Independent Peer
  • 3. Independent Peer
  • 3. Independent Peer

Review Panel Review Panel Review Panel Review Panel

  • 3. Independent Peer Review Panel

– Independent Consultants – Purpose to validate the SPRA process and review projects in the “Urgent and Compelling” category – Recommended immediate operating restrictions at Wolf Creek – Considered risk to be high – Analysis based on engineering judgment

slide-25
SLIDE 25

Reliability Results Reliability Results Reliability Results Reliability Results

All three studies conclude the project

is deficient.

Immediate measures should be taken

to reduce the risk.

Some of them can be implemented

without serious negative impact.

slide-26
SLIDE 26

Risk Risk Risk Risk Reduction Reduction Reduction Reduction Actions Actions Actions Actions

slide-27
SLIDE 27

Interim Risk Mitigation Interim Risk Mitigation Interim Risk Mitigation Interim Risk Mitigation Measures Measures Measures Measures

Dam Safety Program Monitoring 24/7 Increased instrumentation Enhanced and aggressive EAP

process

Public Meetings Independent Expert Panel Stockpiling material

slide-28
SLIDE 28

Risk Reduction Risk Reduction Risk Reduction Risk Reduction Actions Actions Actions Actions

  • Trigger Events that Would Require

Emergency Drawdown

  • Significant abnormal instrumentation readings
  • Sinkholes or settlement in the dam
  • Muddy flows
  • Slide in the dam slope
  • Modified Lake Level Operation
slide-29
SLIDE 29

Operating Restrictions Operating Restrictions Operating Restrictions Operating Restrictions

Low er the Lake = Low er the Risk Low er the Lake = Low er the Risk Low er the Lake = Low er the Risk Low er the Lake = Low er the Risk

This decision comes with a cost. The benefits derived from the project

diminish as the lake is lowered.

How do you make the decision which

balances lowered risk with lost benefits.

slide-30
SLIDE 30

Project Benefits And Project Benefits And Project Benefits And Project Benefits And Lake Level Target Zone Lake Level Target Zone Lake Level Target Zone Lake Level Target Zone

  • Flood Control
  • Average annual flood damages prevented

= $34 million

  • Hydropower
  • $77 million / year
  • Recreation
  • 5 million visitors per year
  • $159 million impact on local economy
  • Water Supply
  • Water Quality
  • Navigation
slide-31
SLIDE 31
  • 4. Probability of Failure/
  • 4. Probability of Failure/
  • 4. Probability of Failure/
  • 4. Probability of Failure/

Operational Restrictions Operational Restrictions Operational Restrictions Operational Restrictions

  • 4. RAC Engineers and Economists Study

(Operating Restrictions) Utah State U. Initiated before Peer Group.

– Used risk assessment methodology to determine effect on risk of various operating restrictions – Preliminary ‘bounding analysis’ showed unacceptable level of risk – Uses process similar to ‘expert elicitation’ to quantify engineering judgment

slide-32
SLIDE 32

Alluvium

Wolf Creek Dam Section Damage Progression

Dam

Cutoff Trench

Piezometers

Catheys Catheys Formation

  • rmation

Liepers Liepers Formation Formation

Grout Curtain

Rapid Tailwater Fluctuations During Power Generation = surging 1967 & 68 Muddy flow and sink hole

1968 Emergency grouting program 1979 Diaphragm Walls Complete

RAC First Failure Scenario The Event Tree

  • 1. Pipe begins

in rock and expands to alluvium

  • 2. Pipe

continues US to wall

  • 3. Secondary

element in wall fails

  • 4. Pipe expands

rapidly upstream through aluvium

  • 5. Breach and failure
slide-33
SLIDE 33

0.00001 0.0001 0.001 0.01 0.1 T

  • p

S E P A C u r r e n t O R . P F 7 2 O R . P F 7 1 O R . P F 7 5 O R . P F 7 O R . P F 6 9 O R . 6 8 O R . 6 1 a O R . 5 6 2 a O R . 6 1 b O R . 5 6 2 b P robability of Failure (/year) 20% Confidence of not being exceeded 50% 80% 20% 50% 80% Limit for Individual Risk & USBR Public Protection Guideline

Annualized Annualized Annualized Annualized Probability of Failure Probability of Failure Probability of Failure Probability of Failure

slide-34
SLIDE 34

What Does This Mean? What Does This Mean? What Does This Mean? What Does This Mean?

None of the operating restriction meet the

criteria for tolerable risk except those that require structural modification of project.

These restrictions result in loss of annual

benefits totaling $200 million.

There are severe environmental

consequences to these restrictions.

Unforeseen consequences?

slide-35
SLIDE 35

Where Are We Now Where Are We Now Where Are We Now Where Are We Now

Decision based on previous risk studies +

impacts that result and health and safety concerns for upstream residents. (Water Intakes). Corporate decision not solely District jurisdiction.

Operate the pool at 680 – flat. Incremental approach. If distress

indicators improve and grouting proceeds, evaluate new operating level. If not, consider more severe restrictions.

slide-36
SLIDE 36

Not very accurately (my opinion) --

Many ill-defined links in process:

– variations in deterministic and probabilistic models – different methods of characterizing soil parameters − φ - c strength envelopes are difficult – slope is a system of slip surfaces

  • distributions of permeability and permeability ratio

– difficult to quantify spatial correlation in practice – difficult to account for length of embankments – difficult to account for independence vs correlation of multiple monoliths, multiple footings, etc.

Thomas F. Wolff, Ph.D., P.E. Michigan State University “How accurately can Pr(f)

How accurately can Pr(f) be calculated?” be calculated?”

Thomas F. Wolff, Ph.D., P.E. Thomas F. Wolff, Ph.D., P.E. Michigan State University Michigan State University “ “How accurately can Pr(f)

How accurately can Pr(f) How accurately can Pr(f) How accurately can Pr(f) be calculated? be calculated? be calculated? be calculated?” ”

slide-37
SLIDE 37

Construction Costs Construction Costs Construction Costs Construction Costs

First Emergency Grouting $15 million Composite Cut Off Wall $ 90 million Current Emergency Grouting $50

million

Future Cut Off Wall $250 million ±

slide-38
SLIDE 38

Impact Costs Impact Costs Impact Costs Impact Costs

Lost hydropower generation = $70 million Cost of extending launching ramps = $ 165K Cost of extending water intakes = $ several

million

Lost revenue from recreation = $65 million Fish hatchery modifications $750K + Others

slide-39
SLIDE 39

Questions Questions Questions Questions Questions Questions

E FS FS E X E X E X

n

[ ] ( [ ], [ ],... [ ]) =

1 2

Var FS FS X FS X FS X

i X i j X X X X

i i j i j

[ ]

,

= ⎛ ⎝ ⎜ ⎞ ⎠ ⎟ + ⎛ ⎝ ⎜ ⎜ ⎞ ⎠ ⎟ ⎟

∑ ∑

∂ ∂ σ ∂ ∂ ρ σ σ

2 2

2

∂ ∂ FS X FS X FS X X X

i i i i i

≈ − −

+ − + −

( ) ( )

Var FS FS X FS X

i i

[ ] ( ) ( ) = − ⎛ ⎝ ⎜ ⎞ ⎠ ⎟

+ −

2

2