Special assignment, OFES, USA
1
Clement Clement Wong, General Atomics, USA Wong, General Atomics, USA
US US-
- ITER TBM Meeting, UCLA,
ITER TBM Meeting, UCLA, February February 14 14-
- 15, 2007
TBM Facility Requirements in ITER and Estimated Cost An initial - - PowerPoint PPT Presentation
TBM Facility Requirements in ITER and Estimated Cost An initial assessment A special assignment: At the request from Dr. V. Chuyanov of ITER and approved by Dr. G. Nardella of OFES Clement Wong, General Atomics, USA Wong, General
Special assignment, OFES, USA
1
Special assignment, OFES, USA
2
footer text, location, date
3
footer text, location, date
4
The two main functions of BB are: i) to convert neutron & gamma energy in heat and collect it by mean of an high grade coolant to reach high conversion efficiency (>30%) ii) to produce and recover all Tritium required as fuel for D-T reactors Tritium breeding self-sufficiency BB are complex components submitted to very severe working conditions
the construction of the DEMO Test Blanket Modules (TBMs)
(ITER SWG Report to the IC) TBMs have to be representative of a DEMO breeding blanket, capable of ensuring tritium-breeding self-sufficiency using high-grade coolants for electricity production
Parties for the development of tritium breeding and power extraction technology.
footer text, location, date
5
footer text, location, date
6
The TBMs first wall is recessed of 50 mm and protected with a 2 mm Be layer
Shield plug Frame TBM Location
TBM TBMs tests need a whole TBM system
footer text, location, date
7
List of presented TBM Design Proposals for day-one (DDDs also available) Helium-cooled Lithium-Lead TBM (1 design, F/MS struct.) Dual-coolant (He+Lithium-Lead) TBM (2 designs, F/MS struct.) He-cooled Ceramic Breeder/Be multiplier TBM (4 designs, F/MS struct.) Water-cooled Ceramic Breeder/Be multiplier TBM (1 design, F/MS struct.) He-cooled Liquid Lithium TBM (1 design, F/MS struct.) Self-cooled Liquid Lithium TBM (1 design, V-alloy struct.) Selection of the coolant connections at each of the 3 ITER test ports based on the TBM proposals System type Test Port nb. 16 Test Port nb. 18 Test Port nb. 2 He-coolant 2 lines 2 lines 3 lines H2O-coolant
rejection system available available available He purge gas 4 lines 4 lines 4 lines ITER component cooling system 1 line 1 line 1 line
12 3 4 5 8 6 7
footer text, location, date
8
Ancillary Equipment
EU HCPB helium system
Cooling lines
Port plug cask
footer text, location, date
9
TBM Removal from the machine:
Step 1: Disconnect port plug and ancillary equipment and move the ancillary equipment unit (AEU) to its maintenance area (yet to be defined). Step 2: Bring in the transfer cask, extract the port plug to the transfer cask and move them to hot cell area. Step 3: Move and insert the port plug into the hot cell “red zone” area. Step 4: Maintain or replace the TBM and maintain or refurbish the AEU in its maintenance area.
TBM Return to the machine:
Step 5: Test the TBM and AEU with the testing utilities. Step 6: Disconnect utilities, insert the port plug to the transfer cask and return them to the port cell. Step 7: Insert port plug, move the transfer cask away, move in the AEU and reconnect TBM (port plug) with the AEU.
AEU TBM transfer cask
Cutting and re-welding of PbLi pipes on the AEU will be done in a temporary tent
footer text, location, date
10
footer text, location, date
11
Utilities: e.g. AC/DC, water, high pressure helium, diagnostics…etc., for the testing of TBM and ancillary equipment
Could be parked and maintained here with Increased area (TBD)
Special assignment, OFES, USA
12
Level 0.0 Level 18.06 Port Cell Area TCWS Area TBM Cooling system Equipment Room TBM Ports #2, 18, 16
footer text, location, date
13
Needs high pressure Helium (8MPa) and water (15.5 MPa) lines from port cell to TCWS and 4 more coolant system areas
EU HCPB helium system
This approach may not be acceptable due to building code seismic requirements and interference with the assembly hall
footer text, location, date
14
Tritium interface schematic
Two sources of tritium: 1. From the breeder and its corresponding purge stream and/or extraction stream.
contaminating the main coolant stream. Observations:
very small (~2.09 10-6 gm/s) it may be reasonable to assume that the bred tritium could be collected locally by the use of suitable gettering units or traps, which can then be delivered to the tritium plant for analysis.
more detailed specification on coolant purification system (CPS) and tritium extraction system (TES) and accountancy requirements is needed.
footer text, location, date
15
footer text, location, date
16
footer text, location, date
17
footer text, location, date
18
since additional equipment can always be purchased later.
Don’t want to double count.
Port Cell: Components design, TBM exchange and maintenance, procedure…etc. TCWS: Detail TBM cooling system location, design and cooling lines design. Hot Cell: AEU parking and maintenance (TBD), TBM RH equipment Tritium Plant: Further specifications from parties and re-assess needs.