1
Tamaki Drive
Transport Safety Improvements
March 2012
Tamaki Drive Transport Safety Improvements 1 March 2012 Auckland - - PowerPoint PPT Presentation
Tamaki Drive Transport Safety Improvements 1 March 2012 Auckland City Council Actions Speed indicator signs A cycle advance education sign at the intersection of Ngapipi and Tamaki Drive Installation of clearways and cycle lanes
1
March 2012
2
3
Sept 09
Sept-Jan 2009 Jan-July 2010 Nov-Dec 2010 Jan-July 2011 Jan-July 2012 July-Dec 2011 Aug-Dec 2012 2013-2014
Jan-Feb 10 Nov-Dec 09 Oct-Dec 09 Jan-July 10 Dec 10 Jan-July 11 May-July 11 July 11 Jun-Sept 11 Aug 11 Jan-July 12 Aug 11-Feb 12 Aug 11-Dec 11 Jan-July 11 Dec 12-Nov 13 Jan 13 and beyond 17 Nov 10 20 Nov 10 Feb 11 Feb-Apr 11 Apr 11
Quick wins delivered Cliff Road crash Eastern Bays & Transport Committee Resolutions Forum & working group agree high priority actions Share the road education campaign delivered Medium term actions delivered Safety Audit Commissioned Safety audit received Preliminary investigation Site walkover to decide high risk priority actions in collaboration with CAA Feasibility studies undertaken Maintenance items delivered Investigation & Design on projects commenced Auckland Council preliminary presentation on longer term
Design Review Panel) Education campaigns Additional Ngapipi intersection option study Workshop with Orakei Local Board Quay Street Safety & improvements, cycle boxes for RWC Delivery of remaining minor safety projects including stakeholder engagement Review previous work, Business case preparation Commencement
capital works programme Lower priority safety actions designed & delivered parking removed Tragic cyclist fatality Design, consultation & implementation of Okahu Bay Boat trailer prohibition, Solent Street Intersection, Stage 1 Averill Avenue Consultation & consent subject to funding of major capital works programmes
4
Three workstreams
collaboration with CAA
(Kelly Tarlton’s to Millennium Bridge)
5
following actions completed:
works for delivery by July 2012, subject to stakeholder engagement
6
Kelly Tarlton’s bend
tourist destination
design elements
and the Tamaki Drive Masterplan
7
Campaign Start Date End Date Description
Check before
Nov ‘10 Feb ‘11 Public awareness and trailer owner campaign to outline changes to parking restrictions
Boat Trailer Parking Campaign
Sept ‘11 Oct ‘11 Boat Trailer - Public awareness and trailer owner campaign to outline changes to parking restrictions
Bunch Cycling Campaign
Mar ‘11 June ‘12 Bunch Cycling Leader Training aimed at experienced cyclists. Code of conduct cards developed for cyclists and distributed through cycle clubs and cyclists
Share the Road Campaign
Dec ‘10 On going Campaign is “Equal rights, Equal responsibilities” with primary messages of “Check before opening door”, “Watch out bikes about”, “Give bikes 1.5m” for motorists, and “Be safe be seen” for cyclists.
Be Safe Be Seen Campaign
May ‘12 June ‘12 The campaign promotes cyclist to wear brighter clothing in the darker winter months (May/June 2012), so that they are visible to the motorists and other road users. The promotion will include cyclist stations where cyclists on Tamaki Drive can safely stop and get information on cycle safety
9
10
Project Name Mar-12 Apr-12 May-12 Jun-12 Jul-12 1 Safety improvements at Tamaki Drive/The Strand intersectjon. Design Constructjon Stakeholder Engagement 2 Tamaki Drive / Solent Street Intersectjon Completed 3 Prohibtjon of boat trailer parking in the vicinity of The Landing Parking prohibitjon completed 4 Tamaki Drive / Watene Intersectjon Design Constructjon Stakeholder Engagement 5,6,7 Kelly Tarltons Safety improvements Design Constructjon Stakeholder Engagement Mission Bay Safety improvements Design Constructjon Stakeholder Engagement 13 Tamaki Drive / Kohimarama Road intersectjon Design Constructjon Stakeholder Engagement 14 Tamaki Drive/ Averill and Stage 1 Complete Stakeholder Engagement complete Constructjon 15 Tamaki Drive Long Drive/ Auckland Intersectjon Design Constructjon Stakeholder Engagement 16,17 Tamaki Goldie and Tamaki Vale, Cliff Road Intersectjon ( St Heliers improvements) Design Constructjon Stakeholder Engagement 8,9,10,11, 12
Tamaki Drive Safety Improvement Programme Stage 1
11
Mar ¡-‑ ¡Jul Jul-‑ ¡ ¡Dec Jan-‑ ¡June Jul ¡ ¡-‑ ¡Dec Jan-‑ ¡Jun Jul ¡ ¡-‑ ¡Dec Jan-‑ ¡Jun Jul ¡ ¡-‑ ¡Dec Jan-‑ ¡Jun Jul ¡ ¡-‑ ¡Dec NGAPIPI ¡INTERSECTION ¡
Investigation - stage 1 Stakeholder Engagement Investigation - stage 2 (SAR) Consents Design Procurement and Construction
TAKAPARAWHA ¡POINT ¡ ¡& ¡BOARDWALK
Investigation - stage 1 Stakeholder Engagement Investigation - stage 2 (SAR) Consents Design Procurement and Construction
2012 2013 2014 2015
Tamaki ¡Drive ¡Safety ¡Major ¡Capital ¡Works ¡Indicative ¡Programme
2016
Andrew Allen
Manager Road Corridor Operations