TADG Working Group Responses to Issues Questionnaire TADG 7 th - - PowerPoint PPT Presentation

tadg working group responses to issues questionnaire
SMART_READER_LITE
LIVE PREVIEW

TADG Working Group Responses to Issues Questionnaire TADG 7 th - - PowerPoint PPT Presentation

TADG Working Group Responses to Issues Questionnaire TADG 7 th Meeting - February 2007 Millbank, London TADG Background to Questionnaire Views expressed on need to assess issues with existing arrangements Ofgem presentation at Meeting


slide-1
SLIDE 1

TADG

TADG Working Group – Responses to Issues Questionnaire

TADG 7th Meeting - February 2007 Millbank, London

slide-2
SLIDE 2

TADG

Background to Questionnaire

  • Views expressed on need to assess issues with existing arrangements
  • Ofgem presentation at Meeting 6:

– summarised issues with existing arrangements and associated consequences raised by at least one party at meetings to date – sought views on extent parties agree with each issue & on its materiality

  • Working group discussion at Meeting 6:

– Some additional issues noted – Range of views on issues and materiality – View that issues should not be perceived as agreed by all or equal weighting – Strawmen focus on addressing issues proposer considers to be material

  • Agreed way forward:

– Ofgem to seek group’s written views on issues & materiality via questionnaire

slide-3
SLIDE 3

TADG

Issues identified in questionnaire

  • 1. Impact on GB queue
  • 2. Information available to NGET
  • 3. Rights/obligations of non-BEGA DG
  • 4. Impact on constraint management
  • 5. Perverse incentives from differential treatment in charging
  • 6. Cost-reflectivity of differential treatment in charging
  • 7. GSP vs. GSP group treatment
  • 8. Evolution of transmission system
  • 9. Competitiveness

10.Contractual burden

slide-4
SLIDE 4

TADG

Questions and responses

  • For each issue, 3 questions were asked:
  • 1. Do you consider this to be an issue?
  • YES / NO
  • 2. How big an issue do you consider this to be?
  • NOT AN ISSUE / IMMATERIAL ISSUE / MATERIAL ISSUE
  • 3. Set out your views on the issue in the context of your answers to

questions 1 and 2.

  • 15 responses received, of which 2 confidential
  • Range of views on issues and materiality
  • This presentation seeks to give a flavour of the range of

respondents’ comments, fuller discussion to be set out in working group report

slide-5
SLIDE 5

TADG

Issue 1: Impact on GB queue

4 respondents consider this to be an issue 1 respondent considers it to be material Range of views:

– Criteria for identifying relevant small power stations – Cumulative impact of many small DG – Capacity gaps in GB queue absorbed by small DG – Existing means for any issues to be addressed (CUSC amendment) – Connection of small DG an issue for DNOs to manage – Materiality of issue not demonstrated

slide-6
SLIDE 6

TADG

Issue 2: Information available to NGET

3 respondents consider this to be an issue 1 respondent considers it to be material Range of views:

– Adequate existing arrangements for information provision by DNOs – Existing means for any issues to be addressed (Grid Code mod) – Need contractual arrangements to provide cost-reflective investment signals

slide-7
SLIDE 7

TADG

Issue 3: Rights/obligations of non-BEGA DG

9 respondents consider this to be an issue 8 respondents consider it to be material Range of views:

– Contractual gap should be addressed – Treat all exporting nodes equally in charging / contractual framework – Lack of export product – Only an issue if DG leads to exports or is prevented connecting - materiality unclear – Consider issue in terms of export from distribution system as a whole – Arrangements for non-BEGA DG based on not using transmission system and netting off GSP group demand

slide-8
SLIDE 8

TADG

Issue 4: Impact on constraint management

6 respondents consider this to be an issue 3 respondents consider it to be material Range of views:

– NGET bilateral trading with individual DG not a long term solution – Introduce access product with compensation rights – Existing means to address issues, e.g. Grid Code mod to enhance existing emergency control provisions, changes to BM – Active BM participation is voluntary, non-participants should not be constrained unless for system reasons – NGET should not directly constrain or control users of the distribution system

slide-9
SLIDE 9

TADG

Issue 5: Perverse incentives

10 respondents consider this to be an issue 7 respondents consider it to be material Range of views:

– Capacity-based thresholds lead to incentives – Combined impact of multiple DG charged as negative demand same as

  • ne charged as generation

– Need consistent arrangements for all DG – Charge for exports – Thresholds always a compromise, existing arrangements strike suitable balance

slide-10
SLIDE 10

TADG

Issue 6: Cost-reflectivity

7 respondents consider this to be an issue 5 respondents consider it to be material Range of views:

– Generally similar to issue 5 – Current embedded benefit not related to actual benefit – DG has same impact as transmission connected generation and should be charged the same – Charge for exports – DG not using the transmission system should not be charged for doing so – Locational signal provided through TNUoS charge to supplier

slide-11
SLIDE 11

TADG

Issue 7: GSP vs. GSP group treatment

11 respondents consider this to be an issue 4 respondents consider it to be material Range of views:

– Issue in some GSP groups – Cross-subsidy from transmission connected generation to DG – Charge for exports on a GSP basis – Existing distortions an unavoidable consequence of GSP group based settlement arrangements which are costly to change

slide-12
SLIDE 12

TADG

Issue 8: Evolution of transmission system

9 respondents consider this to be an issue 6 respondents consider it to be material Range of views:

– Role of transmission system naturally evolves over time – Access & charging arrangements should evolve as appropriate – Review structure of charges – Change now to be robust to evolving role – Evolution slow, issue insufficiently material for fundamental change now

slide-13
SLIDE 13

TADG

Issue 9: Competitiveness

6 respondents consider this to be an issue 3 respondents consider it to be material Range of views:

– Only an issue if transmission charges are not cost-reflective – Existing embedded benefit (~£17/kW) is material – Cross-subsidy from transmission-connected generation to DG – Charge for exports – DG deemed not to use transmission system and pay distribution charges – Connection voltage decisions often determined by other factors

slide-14
SLIDE 14

TADG

Issue 10: Contractual burden

11 respondents consider this to be an issue 10 respondents consider it to be material Range of views:

– Requirement for multiple interfaces a burden, and barrier to small DG – Users should contract only with operator of network connected to – Uncertainty as to enduring arrangements a greater barrier than complexity – Agency model would maximise efficiency of interfaces – Recent reforms remove need for DG-NGET interfaces in some cases – Existing requirements not overly onerous

slide-15
SLIDE 15

TADG

Summary of responses

Responses to I ssues Questionnaire

3 6 9 12 15 1 2 3 4 5 6 7 8 9 10 I ssue Respondents Yes Mat erial

slide-16
SLIDE 16

TADG

Promoting choice and value for all gas and electricity customers