Stakeholder Meeting January 28, 2019 PROJECT TEAM FDOT DESIGN - - PowerPoint PPT Presentation

stakeholder meeting
SMART_READER_LITE
LIVE PREVIEW

Stakeholder Meeting January 28, 2019 PROJECT TEAM FDOT DESIGN - - PowerPoint PPT Presentation

Stakeholder Meeting January 28, 2019 PROJECT TEAM FDOT DESIGN PROJECT MANAGER Maria I. Perdomo, PE MDX PROJECT MANAGER FDOT CONSTRUCTION PROJECT Claudio Diaferia, PE MANAGER Jacqueline Sequeira, PE OWNERS REPRESENTATIVE SENIOR


slide-1
SLIDE 1

Stakeholder Meeting January 28, 2019

slide-2
SLIDE 2

2

FDOT DESIGN PROJECT MANAGER Maria I. Perdomo, PE MDX PROJECT MANAGER Claudio Diaferia, PE CONTRACTOR Archer Western - de Moya Group Joint Venture SENIOR COMMUNITY OUTREACH SPECIALIST Oscar Gonzalez CEI SENIOR PROJECT ENGINEER Mark Croft, PE FDOT CONSTRUCTION PROJECT MANAGER Jacqueline Sequeira, PE

PROJECT TEAM

OWNER’S REPRESENTATIVE PROJECT MANAGER William Detwiler, PE

slide-3
SLIDE 3

PROJECT INFORMATION

3

  • Partnership between the Florida Department of

Transportation (FDOT) and the Miami-Dade Expressway Authority (MDX)

  • Construction Cost: $802 million
  • FDOT: $616 million
  • MDX: $186 million
  • Anticipated Completion: Fall 2023*

* Schedule subject to change due to weather or other unforeseen circumstances

slide-4
SLIDE 4

SR 836 IMPROVEMENTS I-95 CONCRETE PAVEMENT RECONSTRUCTION I-395 RECONSTRUCTION ENHANCEMENTS

N

PROJECT MAP

4 Consists of three major projects to be constructed concurrently to minimize impacts to the public:

  • I-395 from I-95 to MacArthur Causeway Bridge
  • SR 836 from West of NW 17 Ave to Midtown Interchange
  • I-95 Pavement Reconstruction from NW 8 St to NW 29 St
slide-5
SLIDE 5

5

CURRENT DESIGN STATUS

  • Master Plans for Roadway - Traffic Control Plans (TCP), Signing and ITS
  • 90% roadway plans for SR 836, I-395
  • Final roadway plans for I-95
  • 90% Phase I MOT plans for SR 836, I-395 and I-95
  • 60% signature bridge foundation plans
  • TCP detour routes and generic details

OVERALL DESIGN STATUS

  • Roadway - 75%
  • Structures – 40%
  • Maintenance of Traffic (MOT) – 45%

MAJOR DESIGN SUBMITTALS TO DATE:

slide-6
SLIDE 6

* This schedule does not reflect days added to the contract for holidays, weather days or special events

6

  • Nighttime eastbound lane closures for soil boring operations (ongoing)
  • Westbound SR 836 widening over the Lawrence Canal near NW 17 Avenue (February)
  • Widening on SR 836 at NW 17 Avenue-Shift travel lanes to inside (February/March)
  • Bridge foundations on eastbound and westbound SR 836 at NW 17 Avenue (March)

UPCOMING CONSTRUCTION ACTIVITIES THREE MONTH LOOK AHEAD

slide-7
SLIDE 7

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

7

  • Exploratory test pile activity at several sites along I-395 (ongoing)
  • Utility relocations (ongoing)
  • Permanent closure of NE 12 Street between Biscayne Boulevard and NE 2 Avenue;

Traffic to be routed to NE 13 Street (March)

  • Widening activity on NE 13 Street between Biscayne Boulevard and NE 2 Avenue (March)
  • Bridge foundation work for I-395 collector-distributor bridges (March/April)

UPCOMING CONSTRUCTION ACTIVITIES THREE MONTH LOOK AHEAD

slide-8
SLIDE 8

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

8

Bridge foundation work for westbound Signature Bridge (March/April)

UPCOMING CONSTRUCTION ACTIVITIES THREE MONTH LOOK AHEAD

slide-9
SLIDE 9

* This schedule does not reflect days added to the contract for holidays, weather days or special events

9

  • Nighttime closures for roadway surveying (ongoing)
  • Shift travel lanes on I-95 to the outside to set up work zone in the median from NW 17

Street to NW 29 Street (February)

  • Begin demolition of median barrier wall and relocation of drainage structures (March)
  • Relocate conflicting median overhead sign structures (March)

UPCOMING CONSTRUCTION ACTIVITIES THREE MONTH LOOK AHEAD

slide-10
SLIDE 10

UPCOMING ACTIVITIES - PROPOSED TEST PILE SITES

10

N

slide-11
SLIDE 11

MAINTENANCE OF TRAFFIC (MOT)/HOURS

I-395 SPECIFIC

Mainline Nightly Closures

  • 10 pm to 5:30 am Sunday thru Thursday
  • 1 am to 7 am Saturday and Sunday

SR 836 SPECIFIC

Mainline Nightly Closures

  • 8 pm to 5:30 am Sunday thru Thursday
  • 8:30 pm to 9 am Friday
  • 8:30 pm to 11 am Saturday

I-95 SPECIFIC

Mainline Nightly Closures

  • 9 pm to 5:30 am Sunday thru Thursday

RAMPS

  • 10 pm to 6:30 am Sunday thru Thursday​
  • 11 pm to 7 am Friday and Saturday​

SPECIAL NOTES:

  • Special events will be taken into account when scheduling closures
  • Hours noted above are for single lane closures, multi-lane closures will occur later
  • Weekend lane closures will be permitted on I-95 from 11 p.m. on Friday to 5:30 a.m. on Monday
  • The contract documents allows for weekend closures on certain ramps

11

slide-12
SLIDE 12
  • Provide drivers with real-time

travel information;

  • Encourage motorists to take

alternate routes;

  • Clear incidents more quickly,

thereby reducing secondary incidents; and

  • Make work zones safer for

highway workers and motorists. Smart Work Zone Management System (SWZMS) - The project will implement a SWZMS that will utilize Intelligent Transportation System (ITS) Devices such as traffic cameras, data collection devices and portable message signs to:

TRAFFIC MANAGEMENT SYSTEM

12

slide-13
SLIDE 13

13

COMMUNITY OUTREACH

PROJECT WEBSITE

  • www.i-395miami.com
  • Sign-up for project alerts/updates

Lane Closure information Upcoming construction activities Presentations

  • Calendar of events

OUTREACH OFFICE IN THE OVERTOWN COMMUNITY

  • 1035 NW 3 Avenue, Miami, Florida 33136

STAKEHOLDER MEETINGS

  • Ongoing individual stakeholder meetings and presentations
  • TPO Transportation Aesthetics Review Committee

Presentation- February 6, 2019

slide-14
SLIDE 14

786-280-0983 OGonzalez@mrgmiami.com Contact: Oscar Gonzalez

www.i-395miami.com

THANK YOU!

14