Stakeholder Comments on the Sponsors’ Proposal and Stakeholder Counter-Proposal
Order 1000: Regional Planning and Cost Allocation
July 9, 2012 Stakeholder Process Meeting
1
Stakeholder Comments on the Sponsors Proposal and Stakeholder - - PowerPoint PPT Presentation
Stakeholder Comments on the Sponsors Proposal and Stakeholder Counter-Proposal Order 1000: Regional Planning and Cost Allocation July 9, 2012 Stakeholder Process Meeting 1 Outline Stakeholder Comments on the Sponsors Proposal Why
July 9, 2012 Stakeholder Process Meeting
1
compliant with key requirements of Order 1000
requirements of Order 1000
2
3
effectiveness of performance for alternative solutions offered during the transmission planning process”
proposer identifies benefits and proposes cost allocation (Section 1 at 4.A.7)
because … (next slide)
4
processes
independent outlook (“everybody for themselves” approach)
proprietary knowledge in calculating its version of the benefits – not “transparent” and not in “sufficient detail”
governance is a supermajority of a Board of members where the sponsors have (close to) enough votes to block passage of any alternative projects in a regional plan. As a result, the lack of an independent view to inform the Board combined with a supermajority voting structure of member driven governance results in an “unduly discriminatory” process
5
ensure that public utility transmission providers in each transmission planning region, in consultation with stakeholders, identify and evaluate transmission alternatives at the regional level that may resolve the region’s needs more efficiently and cost-effectively than solutions identified in the local transmission plans of individual public utility transmission providers.”
evaluate alternatives that may meet the needs of the region more efficiently or cost-effectively”
affirmative obligation placed on public utility transmission providers to explore such alternatives in the absence of a stakeholder request to do so. We correct that deficiency in this Final Rule.” (emphasis added)
a proposal / request and does not meet “affirmative obligation” requirements
6
two months from receiving the “roll-up” plan to propose alternatives complete with benefit assessments and proposed cost allocation (the “homework”), giving a competitive advantage to the Sponsors (unduly discriminatory and preferential)
planning (Order 1000 at P 151) and Order 890 places the burden of benefits assessment, etc., on the transmission providers, e.g., see Order 1000, P 324 n.304:
stakeholder to request that the transmission provider perform an economic planning study or otherwise suggest consideration of a particular transmission solution in the regional transmission planning process.”
placed on the region
7
uncertainty and disputes
cost allocation when combining:
cost allocation assessment with
agreement
1000 and 1000-A because … (next slide)
8
eliminates uncertainties
where all the parties have their own version of benefits and cost allocation (in fact, under the Sponsors’ proposal, any party essentially has the right to unilaterally veto a project with the
disputes will not be quickly resolved under the FRCC dispute resolution procedures.
9
themselves for projects in the local plans needed for reliability to reflect an obligation to meet reliability standards
CEERTS projects.
provider to … (establish) appropriate qualification criteria for determining an entity’s eligibility to propose a transmission project for selection in the regional transmission plan for purposes
transmission provider or a nonincumbent transmission developer. These criteria must not be unduly discriminatory or preferential.” (emphasis added)
10
Committee “will … make a decision as to whether public policy is driving a transmission need that is not otherwise readily met via requests for new transmission service”
to which transmission needs driven by public policy requirements would be evaluated (P 207); however:
requirements are not “readily met via requests for new transmission service”?
requirements can be readily met through requests for transmission service; hence, the Sponsors’ proposed procedure would result in a “null” set to be studied in the regional planning process, which is unresponsive to the Order
11
recovery may be important during the project development phase; but it is not compliant to use such criteria in advance:
establish, in consultation with stakeholders, procedures to ensure that all projects are eligible to be considered for selection in the regional transmission plan for purposes of cost allocation.” (emphasis added)
require, as part of the qualification criteria, that a transmission developer demonstrate that it either has, or can obtain, state approvals necessary to operate in a state, including state public utility status and the right to eminent domain, to be eligible to propose a transmission facility.” (emphasis added)
12
allocation in alignment with FERC policy?
13
14
making recommendations
understood as those projects that have been submitted by project proposers, as well as additional projects that result from pro- active planning, that are considered more cost-effective and efficient than project(s) in the roll-up plan
described in the next few slides
benefits will be calculated (e.g., methodology, assumptions, criteria, database)
15
16
. D)
Transmission Working Group (TWG) Stability Working Group (SWG), and Resource Working Group (RWG), except focused on identifying transmission needs related to economics and public policy requirements
17
. D)
and public policy requirements of the region (including in response to requests by FRCC members for specific economic studies), and make independent recommendations for more cost-effective and efficient solutions
the FRCC PC and TWG, SWG, RWG and EPPS; however, FRCC RP Staff would be able to independently propose alternative projects to the FRCC Board if staff has an opinion different from the PC
18
. D)
Parallel Databases - Identical and parallel schedules would be used to maintain and update the TWG, SWG and EPPS databases
representation of transmission system
within FRCC Roll-up Plan Development
Up Plan” (consolidation of local plans checked for simultaneous feasibility), which is the starting point for evaluating alternative proposals, including CEERTS proposals
19
. D)
Parallel Assessment of the Roll-Up Plan
the Roll-Up Plan for simultaneous feasibility and to assess the ability to meet regulatory and legal requirements
Roll-up Project Identification
proposed projects within the Roll-Up Plan) will be identified and basic information about the Roll-Up Projects will be provided
20
CEERTS Project Proposals
Proposal) from any interested party (CEERTS Project Proposer)
Stakeholder counter proposal) and FRCC RP Staff will determine whether Proposal is complete
CEERTS Project Criteria
the Roll-Up Plan are CEERTS Project Proposals eligible for cost allocation if selected in the Regional Plan. The FRCC RP Staff makes the determination as to whether a CEERTS Project Proposal is materially different, with expedited Dispute Resolution if there is a disagreement
21
Evaluation of Benefits
alternative proposal(s) in their respective areas of expertise
be evaluated for the overall benefits it provides compared to benefits in the Roll-Up Plan taking into consideration, at a minimum, the following four types of benefits:
1. Reliability 2. Incremental capital costs 3. Economic/Congestion relief 4. Public Policy requirements
Proposer(s), will be evaluated by a method independently developed by the Planning Committee and FRCC RP Staff
to be used in the assessment process (e.g., to independently evaluate benefits of competing projects)
22
. D)
CEERTS Project Development
developer, otherwise FRCC RP Staff will issue RFP
CEERTS Project Developer Eligibility Evaluation
using pre-determined criteria used to evaluate the CEERTS project developers on a comparable basis and makes written recommendations to the FRCC Board
23
. D)
Selection of CEERTS Project and Approval of the Regional Plan by FRCC Board based upon:
Proposal(s), if any, that are more cost-effective and efficient and that are to be included in the Regional Plan, and therefore eligible for regional cost allocation. The Board will then approve the Regional Plan which will be a combination of the Roll-Up Plan (excluding displaced projects) and the selected CEERTS Projects, if any.
from voting
Planning Calendar (See Separate Planning Calendar document)
24
. D)
25
. D)
CEERTS and Roll-Up Project Delays
regional transmission plan to determine if delays in the project require the evaluation of alternative solutions, to ensure that reliability needs
RP Staff may propose solutions that will enable reliability needs or service obligations to be met. The FRCC Planning Committee and FRCC RP Staff shall report to the FRCC Board as necessary
CEERTS Project Abandonment
may include incumbents) may offer to complete the project. If there are multiple developers proposing to complete development of the project, then the FRCC Board (or delegated group or consultant) will develop selection criteria (such as an RFP). The FRCC Board will then make a selection based on those criteria and bids/proposals received
26
with costs allocated roughly commensurate with benefits
27
Principles of cost allocation and cost recovery through a regional tariff are as follows:
tariff
long as Network Resource Interconnection Service (NRIS), or grandfathered equivalent
would still be applicable to inter-regional transmission service
the Flowgate Methodology
Transmission Owner’s area will be used in calculation of Transmission Owner’s revenue requirement
28
. D)
Option 1 – Zonal Allocation
Allocation Process
such Roll-Up Project resides and all incremental Transmission Revenue Requirements for those Roll-Up Projects would be allocated to that zone
to zones in proportion to benefits calculated to that zone
Option 2 – Highway and Byway
directly to the zone in which such CEERTS or Roll-Up Project resides and all incremental Transmission Revenue Requirements for those projects would be allocated to that zone
300 kV are socialized to all zones in the region
29
30