Regulatory Update TITRE Stakeholder Forum 04 April 2013 Stakeholder Forum . Second Stakeholder Forum . Purpose First forum held on 17 th January 2013 To provide a general European Update from ACER and ENTSOE To discuss the latest


slide-1
SLIDE 1

TITRE

Regulatory Update

04 April 2013

Stakeholder Forum

slide-2
SLIDE 2

. Second Stakeholder Forum

»

First forum held on 17th January 2013

. Purpose

»

To provide a general European Update from ACER and ENTSOE

»

To discuss the latest developments in Framework Guidelines and Network Codes

»

To discuss individual codes and potential implications for the SEM market

  • Identification of issues that should be raised in ACER and

ENTSOE

. Meetings will be held every two months

»

Future dates to be discussed today 2

Stakeholder Forum

slide-3
SLIDE 3

Market Codes

. Capacity Allocation and Congestion Management (CACM)

»

ACER Recommendation to EC published on 14th March 2013

»

Key Areas for SEM included

  • Flexibility for Regional Intraday Auctions
  • 2 year Derogation for SEM
  • Capacity Calculation
  • Early harmonisation of redispatch and countertrading arrangements by TSOs.

»

ENTSOE has since published a letter outlining its support for parts of the ACER opinion and its opposition to wording on key areas including Regional Intraday Auctions Capacity Calculation and redispatching and countertrading

»

The Network Code is now with the EC for finalisation and incorporation of the Governance Guidelines

  • Expected to go forward to comitology in summer 2013
  • SEM Engagement with the EC

. Forwards

»

Published for consultation by ENTSOE on 28th March (will be covered later)

. Balancing

»

Under development by ENTSOE (will be covered later)

»

Central Dispatch concepts in early stages

»

Early drafts and presentations on the ENTSOE website.

Network Codes Update

slide-4
SLIDE 4

Technical Codes

. Requirements for Grid Connection Applicable to all Generators (RfG)

»

ACER Recommendation to EC published on 25th March 2013

  • NC first submitted to ACER on 13th July 2012
  • ACER Opinion recommending improvements issued on 13th October 2012
  • NC resubmitted to ACER on 8th March 2013

»

One qualification in the recommendation relating to the significant grid user

  • test. ACER recommended using “commercially available” rather than

“commercially viable”.

»

The Network Code is now with the EC for finalisation

. Requirements for Demand Connection

»

ACER Opinion and Recommendation to EC published on 25th March 2013

»

Positive Opinion with a number of non critical recommendations

  • Mainly relate to national competencies and demand side participation

»

The Network Code is now with the EC for finalisation

. Operational Planning and Scheduling

»

Submitted to ACER by ENTSOE on 29th March 2013

»

ACER has three months to review.

Network Codes Update

slide-5
SLIDE 5

Other European Work . Inter TSO Compensation (ITC) Fund

»

ACER Review of the ITC Fund Launched on 16th October 2012

»

Workshop held in Ljubljana and consultation closed on 14th November 2012

»

ACER decision expected soon

  • The RAs will hold a workshop on losses in SEM on 15th April 2013 in CER
  • ffices.

. REMIT

»

ACER launched a public consultation on technical requirements for data reporting under REMIT on 22nd March

  • Technical Standards for Trade Reporting
  • Registration Guidelines

»

Consultation closes on 7th May, workshop in Ljubljana on 25th April

  • RA contacts are Andrew Ebrill in CER and Andrew McCorriston in UR
slide-6
SLIDE 6

Other European Work . Capacity Mechanisms

»

EC consultation on generation adequacy and capacity payments closed on 28th February

»

CEER responded to the EC consultation and ACER issued an

  • pinion to the EU Parliament on capacity mechanisms

»

EC is currently considering next steps and is expected to publish information on next steps during the summer

. Infrastructure Regulation and Projects of Common Interest

»

Final Infrastructure Regulation expected to be published in May

»

Regulation will set out in detail the process to be designated as a project of common interest (PCI).

slide-7
SLIDE 7

. During the coming year, ACER will review:

Operational Security Network Code Q2 2013 Operational Planning and Scheduling Network Code Q2 2013 Load Frequency and Reserves Network Code Q3 2013 Forward Network Code Q4 2013 HVDC Network Code Q1 2014 Balancing Network Code Q1 2014

. Also key role for Member States in Network Codes at

Comitology

»

Starting in mid 2013

Review of Network Codes

slide-8
SLIDE 8

Thank you for your attention! www.acer.europa.eu