Project Update to Council February 11, 2020 WHAT WEVE DONE SO FAR - - PowerPoint PPT Presentation

project update to council
SMART_READER_LITE
LIVE PREVIEW

Project Update to Council February 11, 2020 WHAT WEVE DONE SO FAR - - PowerPoint PPT Presentation

Project Update to Council February 11, 2020 WHAT WEVE DONE SO FAR October: Street repaved and striping November: Signals, signal timing, pedestrian signals, and increased detection Signage & additional striping Median


slide-1
SLIDE 1

Project Update to Council

February 11, 2020

slide-2
SLIDE 2

WHAT WE’VE DONE SO FAR October:

  • Street repaved and striping

November:

  • Signals, signal timing, pedestrian signals,

and increased detection

  • Signage & additional striping
  • Median islands, crosswalks and rapid

flashing beacons

  • Barrier for in-street shared-use path

December:

  • Final signage, & striping, and flex posts

2

slide-3
SLIDE 3

REPORTABLE CRASHES

*Does not include calls for service

3

4 1 1 2

10/30/15 - 1/10/16 10/30/16 - 1/10/17 10/30/17 - 1/10/18 10/30/18 - 1/10/19 10/30/19 - 1/10/20

Crash Rate for October 30 - January 10 in prior years Number of reportable crashes

slide-4
SLIDE 4

PROJECT COST

*Staff recommendation to City Council and Traffic and Parking Board Recommendation Note: Costs estimated for categories except Study and Analysis and Repaving categories

$1,025,183 $779,683 $951,091

$0 $200,000 $400,000 $600,000 $800,000 $1,000,000 $1,200,000

Build No Build + HAWK* No Build Study and Analysis Design Plans Repaving Implementation Data Collection

4

slide-5
SLIDE 5

COST TO REVERT*

  • Option 1 – Permanent Restoration: Most thorough & durable $700K
  • Option 2 – Micro-seal: More economical but maintenance challenges/trade-
  • ffs and unclear timeline for durability $500K
  • Option 3 – Marking eradication & asphalt patching: Most economical

but least durable and aesthetically poor. Likely hasten need for full resurfacing in the future. $300K

  • Median island conversion: Replace two standard islands with mountable

islands $40K

5

*High level cost estimates

slide-6
SLIDE 6

PRELIMINARY TRAVEL & TRAFFIC SUMMARY

  • Across the day, average travel times have generally stayed the same:
  • Increased by an average of 4% (6 seconds) in the westbound direction and have decreased by an average of 6% (about 12 seconds)

in the eastbound direction

  • In the eastbound directions, travel times are better or relatively the same as they were during the before period except for the

5pm hour (7% increase or about 6 seconds)

  • During the worst 15-minute period of the day (in the westbound direction from 8:15am – 8:30am) travel times

have increased by 30% (about 1 minute).

  • Across the entire morning peak period (7am-9am), there has been an 8% increase in travel times from 3 minutes to 3.2 minutes

(about 12 seconds)

  • During the evening peak, the greatest increase was between 5:45pm and 6:00pm when there was a 14% increase,

from 3.4 minutes to 3.9 minutes (about 30 seconds)

For most of the day, the City’s Bluetooth travel time monitoring system shows the road is functioning similarly to before implementation. A tradeoff for the peak half hour increases (30 sec – 1 minute) is a street with safer conditions for people who drive, walk, bike and use transit.

slide-7
SLIDE 7

PEAK TRAVEL TIMES

Minutes Minutes BEFORE = Sept 24 – Oct 10, 2019 DURING (Construction) = Oct 14 – Nov 21, 2019 AFTER = Dec 3, 2019 – Jan 30, 2020 Data collection for T, W, Th only – does not include holidays, when school is not in session or weather events

~1 minute ~30 sec 7

slide-8
SLIDE 8

ALL DAY TRAVEL TIMES

Minutes Minutes Minutes

BEFORE = Sept 24 – Oct 10, 2019 DURING (Construction) = Oct 14 – Nov 21, 2019 AFTER = Dec 3, 2019 – Jan 30, 2020 Data collection for T, W, Th only – does not include holidays, when school is not in session or weather events

8

slide-9
SLIDE 9

EMERGENCY ACCESS

Mountable Median Standard Crossing Median

Why were two different medians constructed?

  • Mountable medians were installed in conjunction with the temporary sidewalk so vehicles would not have to pull

into the sidewalk space to let an emergency vehicle (EV) pass, and the EV could go directly over the median

  • Standard crossing medians were installed where vehicles can pull out of the travel lane and into the bike lane to

allow EV to pass.

  • Medians were designed cooperatively between T&ES and AFD
  • Appropriate measures have been put in place for emergency responders to safely travel before,

during and after an emergency call

9

slide-10
SLIDE 10
  • Volumes*
  • Speeds*
  • Crashes*
  • Travel Times

EVALUATION

AFTER Data Collection (Spring 2021) Evaluation Report (June 2021)

*Data for Seminary Road and neighborhood streets

10

slide-11
SLIDE 11

PATRICK HENRY SWING SPACE AND DMES

  • Traffic Study by ACPS for the Patrick

Henry Swing Space used for Douglas MacArthur considered:

  • Normal mode split for the school
  • Six additional buses for MacArthur

students

  • Distribution of trips, the projected

additional trips within the Seminary Road and N. Jordan Street intersection

  • Findings: approximately 60 trips in the

AM peak hour and 20 trips in the PM peak hour.

  • This results in a continued acceptable

LOS for both AM and PM peak hours

slide-12
SLIDE 12

QUESTIONS

12