Stadium Boulevard Road Reconstruction Public Meeting September 30, - - PowerPoint PPT Presentation

stadium boulevard road reconstruction
SMART_READER_LITE
LIVE PREVIEW

Stadium Boulevard Road Reconstruction Public Meeting September 30, - - PowerPoint PPT Presentation

Stadium Boulevard Road Reconstruction Public Meeting September 30, 2015 Agenda Welcome and introductions (15 min.) Presentation (20 min.) Project overview and summary of process to date Highlights of feedback received,


slide-1
SLIDE 1

Stadium Boulevard Road Reconstruction

Public Meeting September 30, 2015

slide-2
SLIDE 2

Agenda

§ Welcome and introductions (15 min.) § Presentation (20 min.)

§ Project overview and summary of process to date § Highlights of feedback received, and how reflected in final design § Construction plan, schedule, and traffic impacts

§ Discussion (50 min.)

§ Reactions, questions, suggestions?

§ Timeline and next steps (5 min.)

2

Stadium Boulevard Reconstruction Project

slide-3
SLIDE 3

Stadium Boulevard: Hutchins to Kipke

3

feet km 4000 1 STADIUM BOULEVARD RECONSTRUCTION PROJECT VICINITY DRAWING (File No. 2014-035) 30" Watermain work - may include roadway reconstuction Stadium Blvd Reconstruction

Stadium Boulevard Reconstruction Project

slide-4
SLIDE 4

Project Goals

  • 1. Road reconstruction

– Stadium Boulevard from Hutchins to Kipke – Potter and Prescott, as a result of utility work

  • 2. Underground utility improvements

– Water mains (clean drinking water) – Stormwater management

  • 3. Consider inclusion of non-motorized amenities

– Bike lanes in the roadway – Mid-block crossings – Sidewalk installation on south side of E. Stadium

4

Stadium Boulevard Reconstruction Project

slide-5
SLIDE 5

Summary of process to date

§ Data collection, preliminary engineering work § Stakeholder engagement

– University of Michigan – Ann Arbor Public Schools – Ann Arbor Golf & Outing Club – AAATA – Local public safety/law enforcement organizations – Pedestrian Safety and Access Task Force – Washtenaw Biking and Walking Coalition – Adjacent residential and business communities – City of Ann Arbor Alternative Transportation Committee

§ Public meetings

§ December 2, 2014 and February 25, 2015

5

Stadium Boulevard Reconstruction Project

slide-6
SLIDE 6

Highlights of feedback received

  • 1. Support for improved pedestrian, cyclist safety
  • Affirmation of need for on-street bike lanes
  • Request for improved mid-block crossings,

particularly near Pioneer High School

  • Appetite for sidewalk on south side of Stadium

Boulevard; collaborative approach with AAGO

  • 2. Desire to manage disruption to stakeholders
  • Adjacent residential, business communities
  • University of Michigan; Ann Arbor Public Schools; Ann

Arbor Golf & Outing; AAATA

6

Stadium Boulevard Reconstruction Project

slide-7
SLIDE 7

Non-motorized design elements

ü Inclusion of on-street bike lanes to provide continuity along East/West Stadium Boulevard ü Installation of sidewalks on south side of Stadium Boulevard ü Enhanced street lighting ü Improved mid-block crossings

7

Stadium Boulevard Reconstruction Project

slide-8
SLIDE 8

Bike lanes; sidewalk; lighting upgrades

8

Stadium Boulevard Reconstruction Project

slide-9
SLIDE 9

Midblock crossing at Edgewood (Pioneer High’s north entrance)

9

Stadium Boulevard Reconstruction Project

slide-10
SLIDE 10

Midblock crossing at Gate 2

(UM Stadium’s south entrance)

10

Stadium Boulevard Reconstruction Project

slide-11
SLIDE 11

Construction plan and schedule

11

Stadium Boulevard Reconstruction Project

slide-12
SLIDE 12

Construction plan and schedule

§ 2016: Construction will begin in April and conclude before the start of UM football season § 2017: Similar timing, with some work in winter § Traffic patterns will change every few weeks during construction (in stages)

§ Details available on handouts and project website

§ Biggest disruption post-school year, pre-Art Fair Recommend avoiding construction area as much as possible – use detour routes

12

Stadium Boulevard Reconstruction Project

slide-13
SLIDE 13

Traffic pattern: Stage 1 (Early April)

13

Stadium Boulevard Reconstruction Project

  • N. Main St.
  • W. Stadium Blvd.
  • E. Stadium Blvd.
  • S. Main St.

STADIUM & MAIN CLOSINGS & OPEN LANES

PIONEER HIGH SCHOOL MICHIGAN STADIUM ALLOWED TRAFFIC

Northbound Southbound Eastbound Westbound Closed Lanes

For more information, visit www.a2gov.org

slide-14
SLIDE 14

Traffic pattern: Stage 2 (mid/late April)

14

Stadium Boulevard Reconstruction Project

  • N. Main St.
  • W. Stadium Blvd.
  • E. Stadium Blvd.
  • S. Main St.

STADIUM & MAIN CLOSINGS & OPEN LANES

PIONEER HIGH SCHOOL MICHIGAN STADIUM ALLOWED TRAFFIC

Northbound Southbound Eastbound Westbound Closed Lanes

For more information, visit www.a2gov.org

  • W. Stadium Blvd.
Main St. 7 t h A v e . Scio Church Rd.

EASTBOUND STADIUM BLVD DETOUR

slide-15
SLIDE 15

Traffic pattern: Stage 3 (Late April, mid-June)

15

Stadium Boulevard Reconstruction Project

  • N. Main St.
  • W. Stadium Blvd.
  • E. Stadium Blvd.
  • S. Main St.

STADIUM & MAIN CLOSINGS & OPEN LANES

PIONEER HIGH SCHOOL MICHIGAN STADIUM ALLOWED TRAFFIC

Northbound Southbound Eastbound Westbound Closed Lanes

For more information, visit www.a2gov.org

  • W. Stadium Blvd.
Main St. 7 t h A v e . Scio Church Rd.

EASTBOUND STADIUM BLVD DETOUR

slide-16
SLIDE 16

Detour route: Stage 2, 3

16

Stadium Boulevard Reconstruction Project

slide-17
SLIDE 17

Detour routes: Stage 4

17

Stadium Boulevard Reconstruction Project

slide-18
SLIDE 18

Detour route: Stage 5

18

Stadium Boulevard Reconstruction Project

slide-19
SLIDE 19

Detour routes: Stage 6

19

Stadium Boulevard Reconstruction Project

slide-20
SLIDE 20

Localized impacts to residents

§ Driveway access along Prescott, Potter, and Stadium will be limited during:

  • Water main construction (daytime only)
  • Concrete pouring and curing (approximately 3 days)
  • Road construction (daytime only)

§ Encourage replacement of Orangeburg sewer leads; much less expensive for residents to do so during construction

  • Please get in touch with Mike Nearing with questions

20

Stadium Boulevard Reconstruction Project

slide-21
SLIDE 21

Discussion

Reactions, questions, suggestions?

21

Stadium Boulevard Reconstruction Project

slide-22
SLIDE 22

Proposed timeline

§ Stakeholder engagement: ongoing throughout § First public meeting: December 2, 2014 § Preliminary design drawings § Second public meeting: February 2015

  • Share preliminary design; gather feedback

§ Final public meeting: September 2015 (tonight)

  • Share final design, construction plans, impacts

§ Complete final design § Engage in construction bidding process § Construction to begin April 2016

22

Stadium Boulevard Reconstruction Project

slide-23
SLIDE 23

Contact:

Michael Nearing, Senior Project Manager (734) 794-6410, ext. 43635 mnearing@a2gov.org

Project Website:

www.a2gov.org Search on “Stadium Blvd. reconstruction”

Stadium Boulevard Reconstruction Project

Thank you!

slide-24
SLIDE 24

APPENDICES

Stadium Boulevard Reconstruction Project