Update to the Stadium Advisory Group (SAG) for the CSU - - PowerPoint PPT Presentation

update to the stadium advisory group sag for the csu
SMART_READER_LITE
LIVE PREVIEW

Update to the Stadium Advisory Group (SAG) for the CSU - - PowerPoint PPT Presentation

Update to the Stadium Advisory Group (SAG) for the CSU Multi-Purpose Stadium June 13, 2016 Tonights Agenda 5:30 pm - Meeting called to order Public Comment (up to 30 minutes) Stadium Updates Doug Wilson, Project Manager,


slide-1
SLIDE 1

June 13, 2016

Update to the Stadium Advisory Group (SAG) for the CSU Multi-Purpose Stadium

slide-2
SLIDE 2

Tonight’s Agenda

  • 5:30 pm - Meeting called to order
  • Public Comment (up to 30 minutes)
  • Stadium Updates
  • Doug Wilson, Project Manager, ICON Venue Group
  • Construction Updates
  • Fred Haberecht, CSU Assistant Director of Facilities Management and Campus Planner
  • Cass Beitler, CSU Assistant Director of Construction and Project Management
  • Proposed Shields Underpass Presentation
  • Fred Haberecht, CSU
  • Tim Kemp, City of Fort Collins Capital Projects Engineer
  • Joe Olson, City of Fort Collins Head of Traffic Operations
  • SAG Post-Presentation Discussion
  • Creating a More Accessible, Multi-Modal Campus (Time Permitting)
  • Discussion and Agenda Items for Next Meeting
  • 7:30 pm – Meeting Adjournment
slide-3
SLIDE 3

Public Comments

slide-4
SLIDE 4

SAG Process/Procedures for Discussion, Consensus and Recommendations

slide-5
SLIDE 5

Stadium Updates

slide-6
SLIDE 6

Stadium Construction Updates

  • Progress To Date
  • Anticipated Progress to Next SAG Meeting
  • Current Challenges

6

slide-7
SLIDE 7

Stadium Construction Updates

NORTH

7

slide-8
SLIDE 8

Construction Updates

slide-9
SLIDE 9

Campus Construction Updates: June - July 2016

  • Prospect & Center Ave. Underpass –
  • Aug. 2016 Completion
  • Sidewalk to be installed end of June to early July
  • Aggie Village Redevelopment - Aug.

2016 Completion

  • Substantial completion for South Bldg. was week of

May 30;

  • Substantial completion for West Bldg. = week of June

13; North Bldg. = week of June 28

  • Furniture and appliance deliveries have started (as

early as 3:30 p.m., offload by 9:00 p.m., everyone gone from site by 10:00 p.m.) Goes on for 3 weeks

  • Anticipate move-in starting Aug. 8
  • New S. College Ave. Parking Garage –
  • Aug. 2016 Completion
  • Main part of garage should be open in July.
  • New Chemistry Research Building
  • 2nd floor deck completed
  • New Biology Building
  • Approved completion of 4th floor interior work on

June 8

  • New CSU Health & Medical Center
  • Building 1st floor structure, steel started being erected
  • Planning intersection work on Prospect and College.

The CSU portion (NW corner, right turn lane, southbound on college) will begin end of July/beginning of August 2016. One west bound lane

  • n Prospect will be blocked. Completed in November

2016.

9

slide-10
SLIDE 10

Proposed Shields Street Bike/Pedestrian Underpass

slide-11
SLIDE 11

City’s Past Efforts

– West Central Neighborhoods Plan (1999) – Elizabeth Improvements Constructed (2004) – Transportation Master Plan (2011) – Pedestrian Plan (2011) – Arterial Intersection Prioritization Study (2012) – City’s Student Housing Action Plan (2013) – City of Fort Collins Bicycle Plan (2014) – West Central Area Plan (2015)

11

slide-12
SLIDE 12
  • Keep through traffic on arterials (minimize cut-through)
  • Enhance safety for all travel modes
  • Improve function and operations to minimize

congestion, emissions

  • Better accommodate crossings of arterials to and from

CSU

  • Support bikes and pedestrians and separate modes

where possible

  • Enhance the intersection to allow better accessibility to

the surrounding businesses

Recurring Themes for This Area

12

slide-13
SLIDE 13

Recent Studies at Shields / Elizabeth

  • Bicycle Master Plan
  • Second Ranked Priority Intersection on 2020

Network

  • Student Housing Action Plan
  • Recommends grade separation at Shields/Elizabeth
  • Top Tier Project
  • Congestion, Safety, Multi Modal Conflicts
  • West Central Area Plan
  • Identified as “Short-Mid Term” Intersection Project
  • Reviewed potential for grade-separation

13

slide-14
SLIDE 14

At Shields / West Elizabeth:

  • Vehicle congestion
  • Challenging for pedestrians / bikes to

cross Shields

  • Long delays for bikes/pedestrians
  • More crashes than expected

West Elizabeth Enhanced Travel Corridor

14

slide-15
SLIDE 15

Study of Crossings along Shields Street

Laurel Street Plum Street Elizabeth Street Between University Ave and South Drive Lake Street Between Springfield Dr and Pitkin Street 31 (60) 259 (311) 310 (323) 20-30 45 (28) 42

Location Bike/Ped Demand * Feasibility/Comments Cost

$ $$ $$$ $$ $$ $ Existing crossing accommodates need High demand - Not feasible as removal

  • f structures is required

Underpass feasible – Highest existing and future demand – Highest conflict area – Major Gateway to Campus Low demand Existing crossing accommodates need At grade signalized crossing already funded

Entering Vehicles

3,229 2,950 3,846 2,775 2,937 2,775

Peak Hour

* Bike/ped demand from original West Central Area Plan (most current counts)

slide-16
SLIDE 16

Current Conditions and Anticipated Challenges

slide-17
SLIDE 17
  • 50,000 vehicles per day

enter the intersection (up 20% since 2009)

  • Generally heavy congestion
  • n Shields
  • Northbound left turn at

Level of Service F in peak hour (creates cut-through traffic in neighborhoods)

Shields looking north

Shields at West Elizabeth – Vehicles

17

slide-18
SLIDE 18
  • Heaviest vehicular / bike /

pedestrian corridor in City

  • f Fort Collins
  • More than 2,000 bikes per

day cross Shields (up 40% increase since 2009)

  • In a peak hour, 120 bikes

and 200 pedestrians cross Shields

Shields at West Elizabeth – Bikes / Pedestrians

West Elizabeth looking west

slide-19
SLIDE 19

2010-2014 (five years)

  • 154 total crashes - 28 injury crashes (more than expected)
  • 3 bike crashes
  • 2 pedestrian crashes

2015

  • 30 total crashes – 5 injury crashes
  • 3 bike crashes

Shields at West Elizabeth – Safety

slide-20
SLIDE 20
  • Accessibility for Campus Community:

– 7,500 – 10,000 students currently live west of campus in this corridor – Improve access between campus and the surrounding businesses and neighborhoods on a daily basis and during events on campus (at Moby Arena, etc.)

  • Stadium Game Day:

– In the peak hour after a game, more than 1,000 bikes/pedestrians will need to cross Shields at West Elizabeth – Concurrently with heavy vehicular volumes along Shields and in Moby parking lot

Planning for the Future

20

slide-21
SLIDE 21

At Shields / West Elizabeth:

  • Heavy bike and pedestrian volumes
  • Poor Levels of Service for vehicles
  • Recommends improvements

including additional lanes

The CSU Parking and Transportation Master Plan is incorporated into the CSU Physical Master Plan, approved by Board of Governors April 2014. Available online: https://www.fm.colostate.edu/files/forms/Parking_Transportation_Master_Plan_Study.pdf

CSU Parking and Transportation Master Plan April 2014

21

slide-22
SLIDE 22
  • Seats 41,000 people
  • Transportation framework includes

strong multi-modal element with a focus

  • n better access to campus

CSU On-Campus Stadium

  • City and CSU entered into Intergovernmental Agreement (IGA)

that outlines infrastructure improvements needed for the Stadium

  • Goal of improvements is to address game day needs that

cannot be addressed operationally

  • Ensure that improvements are good investment and also

support daily needs

22

slide-23
SLIDE 23

Part C: Transportation Improvements: CSU agrees to construct or to fund the following improvements to be completed …. prior to the first Major Event held at the Stadium: Lane improvements at Elizabeth and Shields

IGA Dated April 13, 2015, Section C “Transportation Improvements,” Page 8

How Shields/Elizabeth is Listed in IGA

23

slide-24
SLIDE 24

Part D: Additional and Ongoing Study: The Parties [CSU and City] are fully committed to implementing the following projects as soon as practicable: Grade-separated pedestrian and bike crossings

  • r other improvements to address crossing issues on

Shields Street between Laurel Street and Bennett Court.

IGA Dated April 13, 2015, Section D “Additional or Ongoing Study,” Page 9

How Shields/Elizabeth is Listed in IGA

24

slide-25
SLIDE 25

CSU Infrastructure Projects

25

slide-26
SLIDE 26

Proposed At-Grade Intersection Improvements

slide-27
SLIDE 27

Proposed At-Grade Intersection Improvements

27

slide-28
SLIDE 28

Proposed At-Grade Intersection Improvements

28

slide-29
SLIDE 29

Spring 2016 Feasibility Study Addressed: – What problems are we trying to solve? – Overpass vs. underpass – Floodplain – Best location for a grade-separated crossing (including Plum St. vs. Shields St.)

Grade-Separated Crossing Feasibility Study

29

slide-30
SLIDE 30

Proposed Underpass Project

slide-31
SLIDE 31

Proposed Underpass Project – Concept Plan

31

slide-32
SLIDE 32

View Looking East Towards Shields on South Side of Elizabeth

Proposed Underpass Project – Concept Plan

32

slide-33
SLIDE 33

View Looking West Towards Shields on South Side of Elizabeth

Proposed Underpass Project – Concept Plan

33

slide-34
SLIDE 34
  • Improved intersection function and operations:

– Reduced overall delay by 25%

  • Increased safety:

– Reduced number of conflict points among modes – Reduction in overall delay reduces rear-end crashes

  • Eliminated crossing delay for bikes / pedestrians
  • Increased comfort and safety for active modes of travel
  • Gateway opportunity for Colorado State
  • Aesthetic improvements to area

Benefits of Grade Separation

34

slide-35
SLIDE 35

Only initial concept has been completed. Once design team is selected critical issues to be addressed include: – Business access changes and improvements – Preservation of parking – Trail crossing of Campus West access and West Elizabeth – Timeline (When this project may start construction) – Construction impacts

Critical Issues To Be Addressed

slide-36
SLIDE 36

For At-Grade Improvements and Underpass Project: – Start date dependent on right-of-way acquisitions – Duration anticipated at 10-month total – Construction would be phased and would be planned to not keep the entire area closed for that duration – Goal is to minimize disruption to businesses during construction

Estimated Construction Timeframe

36

slide-37
SLIDE 37

– Neighborhood meeting held May 25, 2016 and comments received were shared with three potential design-build teams and recorded by City Staff – Follow-up Underpass Neighborhood Meeting: Tentatively Scheduled for August 2016 Additional Informational Opportunity: – Open House for West Elizabeth Enhanced Travel Corridor: June 16, 6 – 8 pm, Westminster Presbyterian Church Proposed Public Process for the Intersection Improvement and Underpass Projects

37

slide-38
SLIDE 38

Neighborhood Meeting on May 25, 2016:

  • Conflict zone between bikes/pedestrians and vehicles

at Elizabeth Street driveway

  • Parking impacts during and after construction
  • Potential access changes and potential Elizabeth Street

median reconfigurations

  • How to safely move westbound bikes across Elizabeth

Street

  • Phased construction to minimize business impacts

What We’ve Heard

38

slide-39
SLIDE 39

Process for Intersection Improvements & Potential Underpass

City Planning Alternatives Selection of Alternative Location Feasibility Study of Selected Location Public Outreach Design Development Neighborhood Meeting Site Plan Advisory Review (SPAR) Planning & Zoning Hearing Start Construction

  • Neighborhood

Meetings

  • W. Elizabeth

Corridor Plan

  • City Council

Approval

2014 - 2015 2017 - 2018

City Staff Review Neighborhood Meeting Comments to Ensure Final Design Aligns

We Are Here

39

slide-40
SLIDE 40

– Open House for West Elizabeth Enhanced Travel Corridor: June 16, 6 – 8 pm, Westminster Presbyterian

Church

– To Provide Feedback on the West Elizabeth ETC:

  • fcgov.com/westelizabeth

– CSU Construction Updates:

  • http://source.colostate.edu/construction-and-parking/

– To Provide Feedback on CSU Construction Projects:

  • http://source.colostate.edu/we-want-to-hear-from-you/

Ways to Obtain Information and Comment on Related Construction Projects

40

slide-41
SLIDE 41

SAG Post-Presentation Discussion

slide-42
SLIDE 42

Discussion and Agenda Items for Next Meeting