June 13, 2016
Update to the Stadium Advisory Group (SAG) for the CSU - - PowerPoint PPT Presentation
Update to the Stadium Advisory Group (SAG) for the CSU - - PowerPoint PPT Presentation
Update to the Stadium Advisory Group (SAG) for the CSU Multi-Purpose Stadium June 13, 2016 Tonights Agenda 5:30 pm - Meeting called to order Public Comment (up to 30 minutes) Stadium Updates Doug Wilson, Project Manager,
Tonight’s Agenda
- 5:30 pm - Meeting called to order
- Public Comment (up to 30 minutes)
- Stadium Updates
- Doug Wilson, Project Manager, ICON Venue Group
- Construction Updates
- Fred Haberecht, CSU Assistant Director of Facilities Management and Campus Planner
- Cass Beitler, CSU Assistant Director of Construction and Project Management
- Proposed Shields Underpass Presentation
- Fred Haberecht, CSU
- Tim Kemp, City of Fort Collins Capital Projects Engineer
- Joe Olson, City of Fort Collins Head of Traffic Operations
- SAG Post-Presentation Discussion
- Creating a More Accessible, Multi-Modal Campus (Time Permitting)
- Discussion and Agenda Items for Next Meeting
- 7:30 pm – Meeting Adjournment
Public Comments
SAG Process/Procedures for Discussion, Consensus and Recommendations
Stadium Updates
Stadium Construction Updates
- Progress To Date
- Anticipated Progress to Next SAG Meeting
- Current Challenges
6
Stadium Construction Updates
NORTH
7
Construction Updates
Campus Construction Updates: June - July 2016
- Prospect & Center Ave. Underpass –
- Aug. 2016 Completion
- Sidewalk to be installed end of June to early July
- Aggie Village Redevelopment - Aug.
2016 Completion
- Substantial completion for South Bldg. was week of
May 30;
- Substantial completion for West Bldg. = week of June
13; North Bldg. = week of June 28
- Furniture and appliance deliveries have started (as
early as 3:30 p.m., offload by 9:00 p.m., everyone gone from site by 10:00 p.m.) Goes on for 3 weeks
- Anticipate move-in starting Aug. 8
- New S. College Ave. Parking Garage –
- Aug. 2016 Completion
- Main part of garage should be open in July.
- New Chemistry Research Building
- 2nd floor deck completed
- New Biology Building
- Approved completion of 4th floor interior work on
June 8
- New CSU Health & Medical Center
- Building 1st floor structure, steel started being erected
- Planning intersection work on Prospect and College.
The CSU portion (NW corner, right turn lane, southbound on college) will begin end of July/beginning of August 2016. One west bound lane
- n Prospect will be blocked. Completed in November
2016.
9
Proposed Shields Street Bike/Pedestrian Underpass
City’s Past Efforts
– West Central Neighborhoods Plan (1999) – Elizabeth Improvements Constructed (2004) – Transportation Master Plan (2011) – Pedestrian Plan (2011) – Arterial Intersection Prioritization Study (2012) – City’s Student Housing Action Plan (2013) – City of Fort Collins Bicycle Plan (2014) – West Central Area Plan (2015)
11
- Keep through traffic on arterials (minimize cut-through)
- Enhance safety for all travel modes
- Improve function and operations to minimize
congestion, emissions
- Better accommodate crossings of arterials to and from
CSU
- Support bikes and pedestrians and separate modes
where possible
- Enhance the intersection to allow better accessibility to
the surrounding businesses
Recurring Themes for This Area
12
Recent Studies at Shields / Elizabeth
- Bicycle Master Plan
- Second Ranked Priority Intersection on 2020
Network
- Student Housing Action Plan
- Recommends grade separation at Shields/Elizabeth
- Top Tier Project
- Congestion, Safety, Multi Modal Conflicts
- West Central Area Plan
- Identified as “Short-Mid Term” Intersection Project
- Reviewed potential for grade-separation
13
At Shields / West Elizabeth:
- Vehicle congestion
- Challenging for pedestrians / bikes to
cross Shields
- Long delays for bikes/pedestrians
- More crashes than expected
West Elizabeth Enhanced Travel Corridor
14
Study of Crossings along Shields Street
Laurel Street Plum Street Elizabeth Street Between University Ave and South Drive Lake Street Between Springfield Dr and Pitkin Street 31 (60) 259 (311) 310 (323) 20-30 45 (28) 42
Location Bike/Ped Demand * Feasibility/Comments Cost
$ $$ $$$ $$ $$ $ Existing crossing accommodates need High demand - Not feasible as removal
- f structures is required
Underpass feasible – Highest existing and future demand – Highest conflict area – Major Gateway to Campus Low demand Existing crossing accommodates need At grade signalized crossing already funded
Entering Vehicles
3,229 2,950 3,846 2,775 2,937 2,775
Peak Hour
* Bike/ped demand from original West Central Area Plan (most current counts)
Current Conditions and Anticipated Challenges
- 50,000 vehicles per day
enter the intersection (up 20% since 2009)
- Generally heavy congestion
- n Shields
- Northbound left turn at
Level of Service F in peak hour (creates cut-through traffic in neighborhoods)
Shields looking north
Shields at West Elizabeth – Vehicles
17
- Heaviest vehicular / bike /
pedestrian corridor in City
- f Fort Collins
- More than 2,000 bikes per
day cross Shields (up 40% increase since 2009)
- In a peak hour, 120 bikes
and 200 pedestrians cross Shields
Shields at West Elizabeth – Bikes / Pedestrians
West Elizabeth looking west
2010-2014 (five years)
- 154 total crashes - 28 injury crashes (more than expected)
- 3 bike crashes
- 2 pedestrian crashes
2015
- 30 total crashes – 5 injury crashes
- 3 bike crashes
Shields at West Elizabeth – Safety
- Accessibility for Campus Community:
– 7,500 – 10,000 students currently live west of campus in this corridor – Improve access between campus and the surrounding businesses and neighborhoods on a daily basis and during events on campus (at Moby Arena, etc.)
- Stadium Game Day:
– In the peak hour after a game, more than 1,000 bikes/pedestrians will need to cross Shields at West Elizabeth – Concurrently with heavy vehicular volumes along Shields and in Moby parking lot
Planning for the Future
20
At Shields / West Elizabeth:
- Heavy bike and pedestrian volumes
- Poor Levels of Service for vehicles
- Recommends improvements
including additional lanes
The CSU Parking and Transportation Master Plan is incorporated into the CSU Physical Master Plan, approved by Board of Governors April 2014. Available online: https://www.fm.colostate.edu/files/forms/Parking_Transportation_Master_Plan_Study.pdf
CSU Parking and Transportation Master Plan April 2014
21
- Seats 41,000 people
- Transportation framework includes
strong multi-modal element with a focus
- n better access to campus
CSU On-Campus Stadium
- City and CSU entered into Intergovernmental Agreement (IGA)
that outlines infrastructure improvements needed for the Stadium
- Goal of improvements is to address game day needs that
cannot be addressed operationally
- Ensure that improvements are good investment and also
support daily needs
22
Part C: Transportation Improvements: CSU agrees to construct or to fund the following improvements to be completed …. prior to the first Major Event held at the Stadium: Lane improvements at Elizabeth and Shields
IGA Dated April 13, 2015, Section C “Transportation Improvements,” Page 8
How Shields/Elizabeth is Listed in IGA
23
Part D: Additional and Ongoing Study: The Parties [CSU and City] are fully committed to implementing the following projects as soon as practicable: Grade-separated pedestrian and bike crossings
- r other improvements to address crossing issues on
Shields Street between Laurel Street and Bennett Court.
IGA Dated April 13, 2015, Section D “Additional or Ongoing Study,” Page 9
How Shields/Elizabeth is Listed in IGA
24
CSU Infrastructure Projects
25
Proposed At-Grade Intersection Improvements
Proposed At-Grade Intersection Improvements
27
Proposed At-Grade Intersection Improvements
28
Spring 2016 Feasibility Study Addressed: – What problems are we trying to solve? – Overpass vs. underpass – Floodplain – Best location for a grade-separated crossing (including Plum St. vs. Shields St.)
Grade-Separated Crossing Feasibility Study
29
Proposed Underpass Project
Proposed Underpass Project – Concept Plan
31
View Looking East Towards Shields on South Side of Elizabeth
Proposed Underpass Project – Concept Plan
32
View Looking West Towards Shields on South Side of Elizabeth
Proposed Underpass Project – Concept Plan
33
- Improved intersection function and operations:
– Reduced overall delay by 25%
- Increased safety:
– Reduced number of conflict points among modes – Reduction in overall delay reduces rear-end crashes
- Eliminated crossing delay for bikes / pedestrians
- Increased comfort and safety for active modes of travel
- Gateway opportunity for Colorado State
- Aesthetic improvements to area
Benefits of Grade Separation
34
Only initial concept has been completed. Once design team is selected critical issues to be addressed include: – Business access changes and improvements – Preservation of parking – Trail crossing of Campus West access and West Elizabeth – Timeline (When this project may start construction) – Construction impacts
Critical Issues To Be Addressed
For At-Grade Improvements and Underpass Project: – Start date dependent on right-of-way acquisitions – Duration anticipated at 10-month total – Construction would be phased and would be planned to not keep the entire area closed for that duration – Goal is to minimize disruption to businesses during construction
Estimated Construction Timeframe
36
– Neighborhood meeting held May 25, 2016 and comments received were shared with three potential design-build teams and recorded by City Staff – Follow-up Underpass Neighborhood Meeting: Tentatively Scheduled for August 2016 Additional Informational Opportunity: – Open House for West Elizabeth Enhanced Travel Corridor: June 16, 6 – 8 pm, Westminster Presbyterian Church Proposed Public Process for the Intersection Improvement and Underpass Projects
37
Neighborhood Meeting on May 25, 2016:
- Conflict zone between bikes/pedestrians and vehicles
at Elizabeth Street driveway
- Parking impacts during and after construction
- Potential access changes and potential Elizabeth Street
median reconfigurations
- How to safely move westbound bikes across Elizabeth
Street
- Phased construction to minimize business impacts
What We’ve Heard
38
Process for Intersection Improvements & Potential Underpass
City Planning Alternatives Selection of Alternative Location Feasibility Study of Selected Location Public Outreach Design Development Neighborhood Meeting Site Plan Advisory Review (SPAR) Planning & Zoning Hearing Start Construction
- Neighborhood
Meetings
- W. Elizabeth
Corridor Plan
- City Council
Approval
2014 - 2015 2017 - 2018
City Staff Review Neighborhood Meeting Comments to Ensure Final Design Aligns
We Are Here
39
– Open House for West Elizabeth Enhanced Travel Corridor: June 16, 6 – 8 pm, Westminster Presbyterian
Church
– To Provide Feedback on the West Elizabeth ETC:
- fcgov.com/westelizabeth
– CSU Construction Updates:
- http://source.colostate.edu/construction-and-parking/
– To Provide Feedback on CSU Construction Projects:
- http://source.colostate.edu/we-want-to-hear-from-you/
Ways to Obtain Information and Comment on Related Construction Projects
40