ST. MARKS CHARITY WEBSITE Team Phoenix Roshan Manawadu Project - - PowerPoint PPT Presentation

st mark s charity website team phoenix
SMART_READER_LITE
LIVE PREVIEW

ST. MARKS CHARITY WEBSITE Team Phoenix Roshan Manawadu Project - - PowerPoint PPT Presentation

ST. MARKS CHARITY WEBSITE Team Phoenix Roshan Manawadu Project Manager Rumesh Aponso Prasad De Silva AdnanAdamally Introduction Project Description Objectives Benefits Product Scope Project


slide-1
SLIDE 1
  • ST. MARK’S CHARITY WEBSITE
slide-2
SLIDE 2

Team Phoenix

  • Roshan Manawadu – Project Manager
  • Rumesh Aponso
  • Prasad De Silva
  • AdnanAdamally
slide-3
SLIDE 3

Introduction

  • Project Description
  • Objectives
  • Benefits
  • Product Scope
  • Project Scope

Project Duration

Cost Summary

  • Risk Management
  • Project Management Plan

Work Breakdown Structure

Gantt chart

Budget

  • Conclusions and Recommendations
  • Summary
slide-4
SLIDE 4

Project Description

  • The project aim is to develop a user friendly, effective

website for St Mark’s Charity.

  • The website should race averseness as a charity release

heavily on voluntary contribution from the community therefore they can get a competitive advantage through this website.

slide-5
SLIDE 5

Objectives

Business Objectives

  • Marketing & raising awareness about charity.
  • Raise more funds and donations.
  • Attract more people for volunteer service.
  • Keep better management.
  • Increase the revenue of the shops.
  • Operate in an effective manner, in a competitive business environment.

Project Objectives

  • Ensure that user requirement is met with the final website design.
  • Accomplish business objectives and develop the website within defined

budget and time period.

  • Identify and minimize the risks that could badly affect the project.
slide-6
SLIDE 6

Benefits

  • Get donations from the private sector.
  • Get sufficient volunteers to the charity shops and to the

hospice.

  • Increase of revenue from the shops.
  • Better management throughout the charity.
  • Marketing & raising awareness about charity.
  • Attract more people for volunteer service.
slide-7
SLIDE 7

Product Scope

The website will include,

  • Information about the St. Mark’s Charity
  • Board of Management
  • Events Calendar/Upcoming events
  • Online donations
  • Donations up-to-date
  • Apply for volunteer service
  • Online Shopping
  • Links with all related Departments
  • News letter
  • Photo gallery
slide-8
SLIDE 8

Project Scope

  • Project Duration

 Start Date – 29/11/2010  The report and present on planning and costing for the

website – 26/01/2011

 Deadline – 17/6/2011

  • Cost Summary

 Total amount allocated for the project is Rs. 15 Million.  Total estimated project cost is Rs. 14,277,351.00.

slide-9
SLIDE 9

Risk Management

Risks

  • System breakdown
  • Data loss
  • Network breakdown
  • Overruns of project schedule
  • Incomplete Requirements
  • Failure to manage and control change
  • Unfamiliar system software
  • System doesn’t meet the business requirements.
  • Requirements not agreed
slide-10
SLIDE 10

Project Management Plan

  • Work Breakdown Structure
  • Gantt chart
  • Budget
slide-11
SLIDE 11

Work Breakdown Structure

slide-12
SLIDE 12

Project Management Plan

  • Gantt chart and Budget
slide-13
SLIDE 13

Conclusions and Recommendations

Conclusions

  • The charity has found it increasingly difficult to raise

funds due to the global financial crisis.

  • Launching a website is a good idea to overcome the

problems and raise awareness among people.

  • Benefits that can gain through the website,

 Marketing & raising awareness about charity.  Attract more people for volunteer service.  Raise more funds and donations.  Better management throughout the charity.  Increase the revenue of the shops.

slide-14
SLIDE 14

Conclusions and Recommendations

Recommendations

  • Maintaining Web Server
  • Online Registration / Donations
  • Unauthorized Access Protection
slide-15
SLIDE 15

Summary

  • Project Description
  • Objectives
  • Benefits
  • Project Scope

Project Duration

Cost Summary

  • Product Scope
  • Risk Management
  • Project Management Plan

Work Breakdown Structure

Gantt chart

Budget

  • Conclusions and Recommendations
slide-16
SLIDE 16

Any Questions?