19th January 2012
NATIONAL SEMINAR TO AT
1
TO AT NATIONAL SEMINAR 19 th January 2012 1 PR PRESENT - - PowerPoint PPT Presentation
TO AT NATIONAL SEMINAR 19 th January 2012 1 PR PRESENT ESENTATIO TION N ON ON By Vice President - HNPCL Mumbai 19 th January 2012 2 GOOD LEADERSHIP IS THE ART OF GETTING EXTRA ORDINARY WORK DONE THROUGH ORDINARY PEOPLE 3 PROJECT
1
PR PRESENT ESENTATIO TION N ON ON
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
NOTE : UNIT-2 SHALL FOLLOW WITH A PHASE SHIFT OF 3 MONTHS
COMPLETED IN PROGRESS TO BE STARTED
30.05.11 11.06.11 30.06.10 30.06.10 30.06.11 30.05.11 15.11.11 (08.01.12) 30.09.12 (30.09.12) 15.02.13 (15.02.13) 15.04.13 (15.04.13) 10.05.13 (10.05.13) 15.05.13 (15.05.13) 31.05.13 (31.05.13) 25.06.13 (25.06.13) 30.06.13 (30.06.13)
BL R
ZER OD
BE S DL SB
BL U
H T SV F
SY N
CF FL T O
30.01.12 (30.01.12) 30.06.10 30.06.10
TG FD
15.02.12 (15.02.12) 15.03.12 (15.03.12) 15.11.12 (15.11.12) 30.01.13 (30.01.13) 31.03.13 (31.03.13) 30.04.13 (30.04.13)
ZER OD
CE S TE S O F
TB U
SL B G SCHEDULE ACTUAL (ANTICIPATED) 28.02.12 (28.02.12)
TG FLR
CES – CONDENSER ERECTION START TES – TURBINE ERECTION START SL – STATOR LIFTING TBU – TURBINE BOX UP OF – OIL FLUSHING BG – BARRING GEAR SYN - SYNCHRONISATION TO – TRIAL OPERTION BES – BOILER ERECTION START DL – DRUM LIFTING HT – HYDRAULIC TEST BLU – BOILER LIGHT UP SB – STEAM BLOWING SVF – SAFETY VALVE FLOATING CF – COAL FIRING FL – FULL LOAD
27
28
29
30
31
32
33
34
35
COMML MAFG UNITS & ENGG CENTRES ISX TSX PUR QLY PREBID INVOLVEMENT POST AWARD RECEIVE C I S & CONT DOC ORGANISE KICK OFF MTG PREPARATION OF L-1 SCH & CHB . RECEIVE L- 2s AND WITH L-1 PREPARATION OF ENABLING WORK SCH & EXPEDITE COORDN FOR ENGG, QP APPRL, VENDOR APPRL, PROCUREMENT, TESTING, X-PORTN OF CRITICAL PKGS MONITOR PROGRESS, REVIEW PROJECT / MILESTONE (PMX-F15) AND TAKE CORRECTIVE ACTIONS FOR DEVIATION FREEZE SCOPE, INTERFACES, CUST INPUTS & ESTABLISH CONT COORDN PROCEDURE RESOLVE CUST COMPLAINT CONTRACT CLOSING (FORM PMX-F14)
C U S T O M E R R E Q U I R E M E N T
CUSTOMER CONSULTANT
C U S T O M E R S A T I S F A C T I O N
SOX
PROCESS MAP
MSX CONTINUAL IMPROVEMENT IN PM PROCESS
36
37
38
TRIAL OPERATION
(ER/ UNITS)
PG TEST
(ER/ UNITS)
TIME EXTENSION (WR/ UNITS)
APPLIED GRANTED
RECONCILIATION OF MAIN SUPPLIES
UNITS PHY FIN PEM (STN C&I) HWR TRY BAP BPL EDN HYD PC
UNIT - 1 UNIT - 2
UNIT - 1 UNIT - 2 BLR STG STN C&I ESP
RECONCILIATION OF SPARES INITIAL SPARES
UNITS PHY FIN PEM (C&I) HWR TRY BAP BPL EDN HYD JHS PC
SUBMISSION OF DOCUMENTS
AS BUILT/ DRGS / MANUALS/ PROTOCOLS
PEM HWR TRY BAP BPL EDN HYD JHS PC ER
LIQUIDATION OF PENDING POINTS
(UNITS / ER) NOS NIL PEM HWR TRY BAP BPL EDN HYD JHS PC ER
SITE CLOSED (ER : YES / NO PAYMENTS OUTSTANDING
TOTAL
PEM HWR TRY BAP BPL EDN HYD JHS PC WR
CC MEETINGS INTERNAL WITH CUST ZERO DATE :
ACT/ANT. COMPLN : BANK GUARENTEES INSURANCE : LD AMOUNT WITH HELD
ENGG SUPP E & C
RECONCILATION OF SPL T & P ( WR / UNITS )
PEM HWR TRY BAP BPL EDN HYD ER PC BANK GUARANTEES STATUS OF PENDING ISSUES
BG NO
DATE FOR AMOUNT
Valid upto
1 2
TOTAL
CONTRACT CLOSING NOTES 1 2 3
PROJECT MANAGEMENT : MUMBAI
PMX-F20/00
CONTRACT CLOSING WINDOW
STATUS AS ON :
PROJECT : PROJECT :
TOTAL CONTRACT VALUE :
39
40
FORMAT NO. PMX-F01/01 SHEET NO. …. OF. ….
CONTRACT CO-ORDINATION PROCEDURE - DETAILS OF CO-ORDINATOR
PROJECT : SL NO AGENCY MAILING ADDRESS CO-ORDINATOR MOBILE NO. TELEPHONE NO (O) TELEPHONE
FAX NO. e- MAIL AREA REMARKS
41
FORMAT NO. PMX-F02 / 01 CORRESPONDENCE AND DOCUMENT TRANSMITTAL PROCEDURE PROJECT : INITIATING ADDRESSED HNPCL HNPCL CONSULTANT OTHERS BHEL BHEL AGENCY TO ENGINEERING SITE PMG UNIT
( TECHNICAL ) BHEL UNIT HNPCL CONSULTANT OTHERS HNPCL CONSULTANT OTHERS / BHEL PMG BHEL UNIT CONSULTANT HNPCL OTHERS BHEL UNITS OTHERS HNPCL CONSULTANT BHEL UNIT
( COMMERCIAL ) BHEL UNIT HNPCL ( PS COMMERCIAL ) CONSULTANT OTHERS HNPCL CONSULTANT OTHERS / BHEL PMG BHEL UNIT / PSCM CONSULTANT HNPCL OTHERS BHEL UNITS OTHERS HNPCL CONSULTANT BHEL UNIT
BHEL UNIT HNPCL / CONSULTANT OTHERS HNPCL/CONSL OTHERS BHEL UNIT OTHERS HNPCL / CONSULTANT BHEL UNIT
BHEL UNIT HNPCL / CONSULTANT OTHERS HNPCL/CONSUL OTHERS BHEL UNIT OTHERS HNPCL / CONSULTANT BHEL UNIT BHEL UNIT HNPCL / CONSULTANT OTHERS OTHERS HNPCL / CONSULTANT BHEL UNIT NUMBER OF COPIES
42
ENGINEERING INFORMATION FLOW SCHEDULE
FROM TO SCH. ACT. SCH. ACTUAL REMARKS FOR MILE STONE NOTE :- FINAL APPL.
FORMAT NO. PMX-F04 / 01 PROJECT :
SL. NO. DESCRIPTION DRAWING / DOCUMENT NUMBER AGENCY FIRST SUBMISSION
43
FORMAT NO. PMX-F05 / 01
QUALITY PLAN SCHEDULE
PROJECT :
SCH. ACT. SCH. ACTUAL NOTE :-
Compiled by : ( Project Manager )
REMARKS SL. NO.
AGENCY QUALITY PLAN NUMBER DESCRIPTION FIRST SUBMISSION APPROVAL
44
FORMAT NO. PMX-F10 / 02 PROJECT : FROM TO
LIST OF MANPOWER IDENTIFIED FOR SITE
( TO BE FURNISHED BY SMX 7 TSX WITHIN 2 WEEKS OF RECEIPT OF CONTRACT HANDBOOK ) SL. NO. CATEGORY SCHEDULED DEPLOYMENT ACTUAL DATE OF POSTING REMARKS
45
FORMAT NO. PMX-F12/01
ZERO DATE (PROJ) : CIS RECEIPT DATE : ZERO DATE (ERN) : ERECTION START : PROJECT COMPLETION :
SL NO DISCRIPTION PRIM. RESP. SCH SCH. DATE ACT. DATE REMARKS 1 CONTRACT HANDBOOK PMX 6 2 L1 NETWORK PMX 6 3 L2 NETWORK FOR INSTALLATION ISX 6 4 SITE OPENING ISX 8 5 IDENTIFY CONST. MANAGER ISX 4 6 IDENTIFICATION AND DEPLOYMEN PLAN FOR SITE STAFF ISX TSX 4 7 PACKAGING OF SUB- CONTRACTOR PMX 6 8 COMPLETE INPUT DATA FOR TENDER PREPARATION PMX 3 9 SITE MOBILISATION BY SUB CONTRACTOR FOR PUR
10 SITE OFFICE( BUILDING) ISX 11 MATL, STORAGE WITH WATCH & WARD ISX 12 COMMUNICATION FACILITIES TO BE ARRANGED MSX
13 FIRE FIGHTING AND SAFTY ARRNAGEMENTS SITE 14 T&P IDENTIFICATION & DEPLOYMENT PLAN ISX 15 IMTE IDENTIFICATION & DEPLOYMENT PLAN TSX 16 INSURANCE PUR 17 BILLING SCHEDULDE FINALISATION FOR SUPPLY UNITS 18 BILLINGSCHEDULDE FINALIATION FOR ERECTION ISX 19 ERECTION GUIDE LINES TSX 20 INSTALLATION DRAWINGS PMX 21 CONTRACT DOCUMENT PMX 22 STORAGE AND PRESERVATION MANUALS TSX 23 QUALITY SYSTEM DOCUMENTS QLY 24 FQA CHECK LIST QLY 25 CONST WATER& POWER SITE
ENABLING WORKS
PROJECT MANAGEMENT
(STATUS AS ON 24TH OF --------. )
PROJECT :
46
FORMAT NO. PMX-F15/00
PROJECT : AS ON :
: CONTRACT VALUE : REVIEW DATE : SCOPE DESCRIPTION SCHEDULE ACT/(ANT) DESCRIPTION SCHEDULE ACT/(ANT) UPTO LAST YEAR BALANCE UPTO MONTH FOR THE MONTH PHYSICAL SCH ACT FINANCIAL SCH ACT BRIEF STATUS CRITICAL ISSUES OVERVIEW ( BUDGET ) FOR THE YEAR COMMG DATE : PROJECT SCHEDULE ( MILESTONES ) CONTRACT PERIOD : CONTRACT TODAY IS IN MONTH CONSULTANT : ERECTION START : ZERO DATE :
HINDUJA NATIONAL POWER CORPORATION LIMITED
PROJECT MANAGEMENT : MUMBAI
CUSTOMER : PROJECT :
50 100 150 200 250 300 350 34943 35034 35125 35217 35309 35400 35490 35582 35674 35765
ENGINEERING
1 100 75.5
20 40 60 80 100 120 35521 35582 35643 35704 35765 35827 35886 35947 36008 36069 36130 36192 36251 36312 36373 ERECTION SCHEDULE VS ACTUAL - UNIT - 1 SG
Actual erection cum
1 100 95.5
20 40 60 80 100 120 35521 35582 35643 35704 35765 35827 35886 35947 36008 36069 36130 36192 35735 ENGINEERING
Actual erection cum
1 100 95.5
20 40 60 80 100 120 35521 35582 35643 35704 35765 35827 35886 35947 36008 36069 36130 36192 35735 ERECTION SCHEDULE VS ACTUAL - UNIT - 1 T G
Actual erection cum
515 30 50 75 105 145 195 225 245 255 260 265 270 273 275 210 22 37 57 77 97 127 157 182 212 237 252 262 269 275
50 100 150 200 250 300 Jan-01 Mar-01 May-01 Jul-01 Sep-01 Nov-01 Jan-02 Mar-02 May-02 Jul-02
(1) ENGINEERING - HYD
Sch Cum Act Cum
5 15 30 50 75 105 145 195 225 245 255 260 265 270 273 275 2 10 22 37 57 77 97 127 157 182 212 237 252 262 269 275
50 100 150 200 250 300 Dec-00 Feb-01 Apr-01 Jun-01 Aug-01 Oct-01 Dec-01 Feb-02 Apr-02 Jun-02
(2) ENGINEERING - TRY
Sch Cum Act Cum
5 15 30 50 75 105 145 195 225 245 255 260 265 270 273 275 2 10 22 37 57 77 97 127 157 182 212 237 252 262 269 275
50 100 150 200 250 300 Jan-01 Mar-01 May-01 Jul-01 Sep-01 Nov-01 Jan-02 Mar-02 May-02 Jul-02
(3) ENGINEERING - PC
Sch Cum Act Cum
47
FORMAT NO. PMX-F18 / 00
HINDUJA NATIONAL POWER CORPORATION LIMITED
PROJECT MANAGEMENT : MUMBAI PROJECTS : SL No CURR ENCY HARDWAR
HYDERA BAD
EDN B' LORE IS BHOPAL PEM PC CHENNAI TRICHY PSWR TOTAL SUPPLY FREIGHT INSURANCE SUPPLY FREIGHT INSURANCE SUPPLY FREIGHT INSURANCE 4 SUPERVISION 5 TRG CHARGE SUPPLY SUPPLY FREIGHT INSURANCE
PRICE ALLOCATION FOR EPC CONTRACT
MAIN SUPPLY CONTRCT MANDATORY SPARES SPECIAL TOOLS & TACKLES TOTAL 1 2 3
48
49
50
51
52
53
54
55
56