SLIDE 1 SR 247/Pio Nono Avenue and CR 5813/College Street Bridges
- ver Norfolk Southern Railway
Design-Build Industry Forum
January 10, 2019
Andrew Hoenig, P.E., DBIA, DB Program Manager Matthew Fowler, Program Manager
January 10, 2019
Andrew Hoenig, P.E., DBIA, DB Program Manager Matthew Fowler, Program Manager
SLIDE 2
Disclaimer Statement
At this meeting, the Department is providing information about the project’s delivery goals, anticipated scope, anticipated Design- Build procurement process, and potential risks. Participants are encouraged to ask questions during this meeting; however, any information provided by the Department is considered informational only and subject to change.
SLIDE 3 Agenda
- Design-Build Overview
- Schedule
- Project Overview
- Design-Build Procurement
- Open Discussion
SLIDE 4 Design-Build Overview
Design-Build
- Combines preconstruction related services with
construction services into one contract.
- Allows the contractor to participate in the project’s
design in an effort to improve communications, expedite project delivery, and reduce costs.
Governed by:
- 23 Code of Federal Regulations (CFR) Part 636
- Georgia Code Section 32-2-81 (Enacted 2004)
- Board Rules, Chapter 672-18 (Adopted 2006 &
2013)
SLIDE 5 Innovative Delivery
Amount Obligated to Design-Build Contracts
SLIDE 6 Upcoming Design-Build Opportunities
Project PI Number County Anticipated Selection Method Letting
SR 135 @ Altamaha River - TIA 0007037 Jeff Davis Montgomery Two Phase Low Bid 5/17/2019 SR 247/ Pio Nono & College St bridges
- ver Norfolk Southern Railroad
0014895 Bibb Best Value 8/16/2019 0014899 SR 53 WB @ Chattahoochee River 0010212 Hall Two Phase Low Bid 7/19/2019 SR 25 at Savannah River (Houlihan Bridge) and SR 25 at Middle River 0013741 Chatham TBD Anticipated FY 2020 0013742 I-16 @ SR 307 Diverging Diamond Interchange 0013727 Chatham TBD TBD I-985 From I-85/Gwinnett to SR 53/Hall 0014130 Gwinnett Hall TBD TBD I-85 Widening SR 211 to SR 11/US 129 0013545 Barrow Jackson Best Value Summer 2024
http://www.dot.ga.gov/PS/Innovative/DesignBuild
SLIDE 7 DB Procurement Documents Updates
RFQ
- Updated for clarity & format
- Pass/Fail requirements remain
RFP
- Updated for clarity, consistency & continuous
improvement
- Design-Build Contract Template Published
Online
- Combining Volumes 2 & 3 into single volume
- Updating Design-Build Manual Attachments
SLIDE 8 Required Information – RFQ Phase (1/2)
- Organization chart
- Lead Contractor/Lead Design Consultant basic
company information
- Lead Contractor Certificate of Qualifications
- Matrix listing GDOT Prequalified Area Classes
– Include prequalification Notice of Professional Consultant Qualifications
SLIDE 9 Required Information – RFQ Phase (2/2)
– Certification Form for Lead Design Consultant
– GA Security and Immigration Compliance Act Affidavit for Lead Contractor – GA Security and Immigration Compliance Act Affidavit for Lead Design Consultant
- Statement(s) regarding removal / failure to complete an
assigned contract
- Statements of Disclosure (Conflict of Interest)
- Signed Amendment(s) acknowledgement
SLIDE 10
- Relevant project experience, qualifications, and
availability of the:
– Lead Design Consultant Firm – Lead Design Consultant Project Manager – Lead Contracting Firm – Lead Contractor Project Manager – Select Key Team Leaders
- Suitability to provide services for project
- Past performance
- Shortlist 3-5 highest qualified teams
Anticipated SOQ Evaluation Criteria
SLIDE 11 Tentative Schedule
- a. GDOT issues Public Notice Advertisement (PNA)
12/12/2018
- b. Industry Forum – GDOT Rooms 401/402
1/10/2019 11:00 AM
- c. Industry one-on-one meetings– GDOT Rooms 408/409*
1/10/2019 1:00 PM – 5:00 PM
- d. GDOT issues Request for Qualifications (RFQ)
1/25/2019
- e. Deadline for the submission of written questions
2/15/2019 5:00 PM
- f. Deadline for submission of Statement of Qualifications
(SOQ) 2/28/2019 2:00 PM
- g. GDOT issues the Notice to Finalists
3/29/2019
- h. GDOT issues Request for Proposals (RFP) to the Finalists
4/19/2019
- i. Receipt of Price Proposals and Technical Proposals from
Finalists 7/25/2019 2:00 PM
- j. GDOT letting (opening of Price Proposals)
8/16/2019 10:00 AM
SLIDE 12 SR 247/Pio Nono Avenue and CR 5813/College Street Bridges
- ver Norfolk Southern Railway
Project Specifics
January 10, 2019
Matthew Fowler, Program Manager
January 10, 2019
Matthew Fowler, Program Manager
SLIDE 13 Project Overview
- Port expansion & NSRR double stacking
- Two separate crossings, one RFP
, one contract
- Design-Build Delivery (2-phase Best Value)
- State funded
- Increase both vertical clearances by June
2020
SLIDE 14
SR 247/Pio Nono Avenue Project Location
SLIDE 15
SR 247/Pio Nono Avenue Project Location
SLIDE 16
SR 247/Pio Nono Avenue Project Location
SLIDE 17
SR 247/Pio Nono Avenue Project Location
SLIDE 18 Project Overview – SR 247/Pio Nono Avenue
- SR 247/Pio Nono Avenue over NSRR
- Increase clearance between bottom of beam and
top of rail to minimum 21’-0”
- Total project length approx. 0.16 mile
- Staged construction to maintain traffic – approx.
3-4 week closure
- Construction within existing Right-of-Way and
GDOT-acquired easements
SLIDE 19 Existing Proposed
Year Constructed 1977 Sufficiency Rating 73.6 Span Length 1 @ 65’ 1 @ 65’ Lanes 4 @ 11’ to 12’ 4 @ 11’ to 12’ Shoulder (each direction) 2’-0” 2’-0” Sidewalk (each direction) 5’-0” 5’-0”
Bridge Information – SR 247/Pio Nono Avenue
*same deck footprint
SLIDE 20
Proposed Typical Sections
SLIDE 21
CR 5813/College Street Project Location
SLIDE 22
CR 5813/College Street Project Location
SLIDE 23
CR 5813/College Street Project Location
SLIDE 24
CR 5813/College Street Project Location
SLIDE 25 Project Overview – CR 5813/College Street
- CR 5813/College Street over NSRR
- Replacement of the complete bridge
- Total project length approx. 600 feet
- Road closed during construction (approx. 6+
months); detour approx. 1.3 miles
- Construction within existing Right-of-Way and
GDOT-acquired easements
- Provide bridge length for future track
SLIDE 26 Existing Proposed
Year Constructed Mid to late 19th century Sufficiency Rating N/A Span Length Arch <20’ 1 @ 65’ Lanes 2 @ 12’ 2 @ 11’ Combination Shoulder/Bike Lane (each direction) N/A 6’-6” Sidewalk (each direction) Varies 5’ to 10’ 8’
Project Overview – CR 5813/College Street
*similar deck footprint
SLIDE 27
Proposed Typical Sections
SLIDE 28 Anticipated Area Classes for Lead Design Consultant
3.02 Two-Lane or Multi-Lane Urban Roadway Design
4.01(a) Minor Bridge Design
SLIDE 29 Anticipated Area Classes for DB Team Members
Number Area Class
1.06(a) NEPA 1.06(b) History 1.06(c) Air Quality 1.06(d) Noise 1.06(e) Ecology 1.06(f) Archaeology 1.07 Attitude, Opinion, and Community Value Studies (Public Involvement) 3.02 Two-Lane or Multi-Lane Urban Roadway Design 3.07 Traffic Operations Design 3.10 Utility Coordination 3.12 Hydraulic and Hydrological Studies (Roadway) 3.15 Highway and Outdoor Lighting 4.01(a) or 4.01(b) Minor Bridge Design or Minor Bridge Design - CONDITIONAL 4.04 Hydraulic and Hydrological Studies (Bridges) 5.01 Land Surveying 5.02 Engineering Surveying 5.03 Geodetic Surveying 5.08 Overhead/Subsurface Utility Engineering (SUE) 6.02 Bridge Foundation Studies 6.05 Hazardous Waste Site Assessment Studies 9.01 Erosion, Sedimentation, and Pollution Control Plan 9.03 Field Inspection for Erosion Control
SLIDE 30 Risks and Mitigation Strategies
Risk Mitigations for RFP
Geotechnical
- Provide boring logs/samples (College St.)
- Additional information for historical arch deconstruction
(College St.)
- No Geotechnical information provided at Pio Nono Ave.
due to no substructure Survey Database
Environmental
- Very limited ecological resources
- Historical commitments to be included in RFP
Design Exception/ Design Variance
- Approved known instances of DE/DV
SLIDE 31 Risks and Mitigation Strategies
Risk Mitigations for RFP
Detour Traffic
- Ongoing outreach with stakeholders
- Advanced detour notifications
NSRR Outreach
- Early coordination for bridge demolition and construction
Overall Contract & Milestone Durations
- Establish reasonable durations in order to complete all of
the Work
- Best Value schedule requirements
Utilities
- Possible early gas line relocation (Pio Nono Ave.)
- Anticipate not all utilities will be relocated
- SUE QL-B
- Early coordination with utility owners
- Executed MOUs
SLIDE 32 Design-Build Team Roles and Responsibilities
- Utility coordination and relocation
- Bridge and Roadway design
- Schedule development/management
- Geotechnical reports
- Permit and mitigation costs
- Maintain traffic, traffic control, and
construction signage
- Increase both vertical clearances by June
2020
SLIDE 33 GDOT Roles and Responsibilities
- Review of DB Team submittals
- Environmental Special Studies/GEPA
preparation and approval
- Potential early gas line relocation
- Construction Oversight/CEI
- Material Testing will be provided by OMAT
- CEI performed by Moreland Altobelli
SLIDE 34 Anticipated Procurement Process
Two Phase Best Value Phase I - Request for Qualifications (RFQ)
- Georgia Procurement Registry (GPR)
- Restriction on communications
- Shortlisted Proposers advance to Phase II
Phase II - Request for Proposals (RFP)
- GDOT DB secure SharePoint Site
- Administrative, Technical and Price Proposals
- GDOT awards to the highest combined score of the
Technical and Price Proposals
SLIDE 35 Anticipated Procurement Process
Phase II - Request for Proposals (RFP)
- Issue RFP – April 19, 2019
- Posted on GDOT DB secure SharePoint site
- Includes Reference Information Documents (RIDs)
- Submit questions to OID Contracting Officer
- Administrative, Technical and Price Proposals
- Due to GDOT by July 25, 2019
- Price Proposal in separate package
- GDOT evaluates Administrative and Technical
Proposals
- Price Proposals opened on August 16, 2019
SLIDE 36 Anticipated RFP Best Value Selection Criteria
Technical Proposal - 35%
- Technical Score is based on 350 maximum total
points.
- Evaluation Criteria may include:
- Detailed Project Schedule / Milestone Deadlines
- Project Management and Approach / Stakeholder and Public
Involvement
- Technical Approach / Construction Staging
Price Proposal - 65%
- The Price Proposal Score is based on 650 maximum
total points.
SLIDE 37 Anticipated RFP Best Value Selection Criteria
Technical Proposal – 350 points
- Detailed Project Schedule / Milestone Deadlines (175
points)
- Contract duration
- Closure at Pio Nono Ave
- Opening at College St
- Project Management and Approach / Stakeholder and
Public Involvement (50 points)
- Technical Approach / Construction Staging (125 points)
- Construction techniques
- Utility Relocations/Avoidance
- Design & Construction Interface
*significant LDs for not meeting milestone dates
SLIDE 38 Anticipated Stipulated Fee
- $30,000 approved stipulated fee
- Table 1.2 of the Design-Build Manual:
Design-Build Estimated Contract Value Best Value Two Phase Low Bid (Shortlist) Two Phase Low Bid (all qualified) One Phase Low Bid
≥$50M (Greater than or equal to $50M) 0.2 % Minimum 0.2 % Recommended 0.1 % Minimum 0.2 % Recommended 0.0 % Minimum 0.1 % Recommended No Stipulated Fee <$50M (Less than $50M) 0.2 % Minimum 0.4 % Recommended 0.1 % Minimum 0.2 % Recommended 0.0 % Minimum 0.1 % Recommended No Stipulated Fee
SLIDE 39 Stipulated Fee Requirements
In exchange for a Stipulated Fee, Proposers must turn over to GDOT all project related information collected and prepared during the preparation of the price and technical proposal. This may include, but is not limited to:
- Approved Alternative Technical Concepts (ATC)
- Revised plan layouts
- Geotechnical data
- CAD files
- Detailed project schedule
- Record of correspondence with agencies
This information will be provided to the awarded Design-Build Team. GDOT will also have the ability to negotiate approved ATCs from unsuccessful Proposers into the awarded Design-Build Team’s contract to obtain additional value or cost savings for GDOT.
SLIDE 40 Tentative Schedule
- a. GDOT issues Public Notice Advertisement (PNA)
12/12/2018
- b. Industry Forum – GDOT Rooms 401/402
1/10/2019 11:00 AM
- c. Industry one-on-one meetings– GDOT Rooms 408/409*
1/10/2019 1:00 PM – 5:00 PM
- d. GDOT issues Request for Qualifications (RFQ)
1/25/2019
- e. Deadline for the submission of written questions
2/15/2019 5:00 PM
- f. Deadline for submission of Statement of Qualifications
(SOQ) 2/28/2019 2:00 PM
- g. GDOT issues the Notice to Finalists
3/29/2019
- h. GDOT issues Request for Proposals (RFP) to the Finalists
4/19/2019
- i. Receipt of Price Proposals and Technical Proposals from
Finalists 7/25/2019 2:00 PM
- j. GDOT letting (opening of Price Proposals)
8/16/2019 10:00 AM
SLIDE 41
Questions?
GDOT Design-Build Webpage http://www.dot.ga.gov/PS/Innovative/DesignBuild GDOT Design-Build SharePoint Site http://mydocs.dot.ga.gov/info/designbuild/default.aspx References:
During project procurement, all proposer questions shall be submitted to the Department via email: MaconNSBridges@dot.ga.gov