SLIDE 1 Atlantic Street Bridge Project
CTDOT Project Nos. 1 3 5 -3 0 1 & 3 0 1 -1 6 3 ( Phase 2 )
Reconstruction of Atlantic Street & Metro‐North RR Bridge Replacement | Track & Station Infrastructure Improvements City of Stamford www.AtlanticStreetBridge.com
SLIDE 2 Public Outreach Social Media Outlets
Regular Updates:
- n the web: http://atlanticstreetbridge.com
- n Facebook: atlanticstreetbridge
- n Twitter: @Atlantic_Street
Sign up for Email Announcements on the Website Email: info@atlanticstreetbridge.com
SLIDE 3
CONNECTICUT DOT PROJECT TEAM
CTDOT District 3A Office: Domenic LaRosa, P.E. ‐ District Engineer Dean Cerasoli, P.E. ‐ Assistant District Engineer John Antonucci, P.E. ‐ Supervising Engineer Mohammad Masoud ‐ Project Engineer HAKS Engineers P.C. (Construction Engineering & Inspection): Kevin Conroy, P.E. ‐ Resident Engineer
SLIDE 4
Contract Information
State Project Nos.: 135‐301 & 301‐163 Owner: Connecticut Dept. of Transportation Inspector: HAKS Engineers Contractor: Halmar International Contract Value: $ 74,846,308 Pre‐Construction Started: August 28, 2017 Contract Completion Date: November 30, 2020
SLIDE 5
Combined Contract 135-301/301-163
EXISTING METRO NORTH BRIDGE OVER ATLANTIC STREET
SLIDE 6
Combined Contract 135-301/301-163
PROPOSED CONSTRUCTION
SLIDE 7 Combined Contract 135-301/301-163
Replace MNR Bridge Extended Platform Track #7 Construction Catenary Replacement Lowering Roadway
2 3 4 5
``
1 2 3 4 5 5 1
SLIDE 8 Additional Considerations
- Multimodal Accommodations
- Provides for Future Bike Lanes
- Beautification
- Use of Concrete Form Liner
- Incorporation of City Streetscape Standards
- Salvage of Existing Brownstone for Future City Use
SLIDE 9 Jump Span Installation and Abutments
JUMP SPANS & TEMPORARY SUPPORTS
SLIDE 10 Bridge Roll-in: Begin June 28, 2019
PRE- DEMOLITION
SLIDE 11 Bridge Roll-in: June 28-July 8, 2019
PRE ROLL-IN TRACKS 2 & 4
SLIDE 12 Bridge Roll-in: June 28-July 8, 2019
TRACKS 2 & 4 RETURNED TO SERVICE
SLIDE 13 Bridge Roll-in Completed: July 8, 2019
STAGE 2 BRIDGE ROLL-IN COMPLETED
SLIDE 14 Bridge, Platform and Track #7 Complete: November 2020
PLATFORM & TRACK 7 COMPLETED
SLIDE 15
Animation
SLIDE 16
Current Schedule
ACTI VI TY DATE
JUMP SPAN INSTALLATION FALL 2018 ATLANTIC STREET CLOSED FEBRUARY 2019 CENTER PIER CONSTRUCTION FEBRUARY‐JUNE 2019 NEW BRIDGE ROLL‐IN JUNE 28 – JULY 8, 2019 LOWER ATLANTIC STREET JULY ‐ SEPTEMBER 2019 REOPEN ATLANTIC STREET SEPTEMBER 2019 PHASE 2 COMPLETE NOVEMBER 2020
SLIDE 17 Traffic Patterns During Phase 2
(Atlantic Street, South State Street – Similar to Phase 1 Project)
- Temporary Detours during Bridge Demolition and Roll‐In Period
(Atlantic St, Dock St, South State St)
- Approx. 6 Month Closure of Atlantic Street to Install Center Pier and Complete
Roadway Lowering
SLIDE 18 Stage 1B (Center Pier Construction): February - June 2019
Road Closures:
(Dock St to S. State St) Detours:
- Washington Blvd
- Henry Street
- Dock Street
- Canal Street
- N. & S. State Streets
SLIDE 19 Stage 1B (Center Pier Construction): February - June 2019
Road Closures:
(Dock St to S. State St) Detours:
- Washington Blvd
- Henry Street
- Dock Street
- Canal Street
- N. & S. State Streets
SLIDE 20 Stages 2 & 3: June 28th – September 9th, 2019
Road Closures:
- Manhattan Street (access to Atlantic)
- South State Street (btw Guernsey Avenue
& Exit 8 NB off-ramp) – Station only access from Washington Blvd.
- Atlantic Street (btw Dock St & N. State St)
- Dock Street (btw Atlantic St & John Street)
- Atlantic Street (btw S. State St & Dock St)
Detours:
- Guernsey Avenue (closed to SB traffic
from N. State St) Washington Blvd
- Washington Blvd, Henry St. to Canal St.
SLIDE 21 Stages 2 & 3: June 28th – September 9th, 2019
Road Closures:
- Manhattan Street (access to Atlantic)
- South State Street (btw Guernsey Avenue
& Exit 8 NB off-ramp) – Station only access from Washington Blvd.
- Atlantic Street (btw Dock St & N. State St)
- Dock Street (btw Atlantic St & John Street)
- Atlantic Street (btw S. State St & Dock St)
Detours:
- Guernsey Avenue (closed to SB traffic
from N. State St) Washington Blvd
- Washington Blvd, Henry St. to Canal St.
SLIDE 22 Pedestrian Detour of Atlantic Street: June - September 2019
Sidewalk Closures:
- Atlantic Street (btw N. or S.
State St & Dock St) Detours:
- Guernsey Avenue
- Xing over Tracks via Station
- Station Place
- Access to S. State Street until
Stage 2 (June 2019)
SLIDE 23 Pedestrian Detour of Atlantic Street: June - September 2019
Sidewalk Closures:
- Atlantic Street (btw N. or S.
State St & Dock St) Detours:
- Guernsey Avenue
- Xing over Tracks via Station
- Station Place
- Access to S. State Street until
Stage 2 (June 2019)
SLIDE 24 THANK YOU!!!
Regular Updates:
- n the web: http://atlanticstreetbridge.com
- n Facebook: atlanticstreetbridge
- n Twitter: @Atlantic_Street
Sign up for Email Announcements on the Website Email: info@atlanticstreetbridge.com Project Signage in Station and Downtown Regular Public Meetings Flyers and Bulletins
SLIDE 25 Atlantic Street Bridge Project
CTDOT Project Nos. 1 3 5 -3 0 1 & 3 0 1 -1 6 3 ( Phase 2 )
Reconstruction of Atlantic Street & Metro‐North RR Bridge Replacement | Track & Station Infrastructure Improvements City of Stamford www.AtlanticStreetBridge.com