atlantic street bridge project
play

Atlantic Street Bridge Project CTDOT Project Nos. 1 3 5 -3 0 1 - PowerPoint PPT Presentation

Atlantic Street Bridge Project CTDOT Project Nos. 1 3 5 -3 0 1 & 3 0 1 -1 6 3 ( Phase 2 ) Reconstruction of Atlantic Street & Metro North RR Bridge Replacement | Track & Station Infrastructure Improvements City of Stamford


  1. Atlantic Street Bridge Project CTDOT Project Nos. 1 3 5 -3 0 1 & 3 0 1 -1 6 3 ( Phase 2 ) Reconstruction of Atlantic Street & Metro ‐ North RR Bridge Replacement | Track & Station Infrastructure Improvements City of Stamford www.AtlanticStreetBridge.com

  2. Public Outreach Social Media Outlets Regular Updates: on the web: http://atlanticstreetbridge.com on Facebook: atlanticstreetbridge on Twitter: @Atlantic_Street Sign up for Email Announcements on the Website Email: info@atlanticstreetbridge.com

  3. CONNECTICUT DOT PROJECT TEAM CTDOT District 3A Office: Domenic LaRosa, P.E. ‐ District Engineer Dean Cerasoli, P.E. ‐ Assistant District Engineer John Antonucci, P.E. ‐ Supervising Engineer Mohammad Masoud ‐ Project Engineer HAKS Engineers P.C. (Construction Engineering & Inspection): Kevin Conroy, P.E. ‐ Resident Engineer

  4. Contract Information State Project Nos.: 135 ‐ 301 & 301 ‐ 163 Owner: Connecticut Dept. of Transportation Inspector: HAKS Engineers Contractor: Halmar International Contract Value: $ 74,846,308 Pre ‐ Construction Started: August 28, 2017 Contract Completion Date: November 30, 2020

  5. Combined Contract 135-301/301-163 EXISTING METRO NORTH BRIDGE OVER ATLANTIC STREET

  6. Combined Contract 135-301/301-163 PROPOSED CONSTRUCTION

  7. Combined Contract 135-301/301-163 Replace 1 MNR Bridge 5 3 Extended 2 Platform Track #7 `` 3 Construction 1 Catenary 4 Replacement Lowering 2 5 Roadway 5 4

  8. Additional Considerations • Multimodal Accommodations • Provides for Future Bike Lanes • Beautification • Use of Concrete Form Liner • Incorporation of City Streetscape Standards • Salvage of Existing Brownstone for Future City Use

  9. Jump Span Installation and Abutments JUMP SPANS & TEMPORARY SUPPORTS

  10. Bridge Roll-in: Begin June 28, 2019 PRE- DEMOLITION

  11. Bridge Roll-in: June 28-July 8, 2019 PRE ROLL-IN TRACKS 2 & 4

  12. Bridge Roll-in: June 28-July 8, 2019 TRACKS 2 & 4 RETURNED TO SERVICE

  13. Bridge Roll-in Completed: July 8, 2019 STAGE 2 BRIDGE ROLL-IN COMPLETED

  14. Bridge, Platform and Track #7 Complete: November 2020 PLATFORM & TRACK 7 COMPLETED

  15. Animation

  16. Current Schedule ACTI VI TY DATE JUMP SPAN INSTALLATION FALL 2018 ATLANTIC STREET CLOSED FEBRUARY 2019 CENTER PIER CONSTRUCTION FEBRUARY ‐ JUNE 2019 NEW BRIDGE ROLL ‐ IN JUNE 28 – JULY 8, 2019 LOWER ATLANTIC STREET JULY ‐ SEPTEMBER 2019 REOPEN ATLANTIC STREET SEPTEMBER 2019 PHASE 2 COMPLETE NOVEMBER 2020

  17. Traffic Patterns During Phase 2 • Temporary Lane Closures (Atlantic Street, South State Street – Similar to Phase 1 Project) • Temporary Detours during Bridge Demolition and Roll ‐ In Period (Atlantic St, Dock St, South State St) • Approx. 6 Month Closure of Atlantic Street to Install Center Pier and Complete Roadway Lowering

  18. Stage 1B (Center Pier Construction): February - June 2019 Road Closures: • Atlantic Street (Dock St to S. State St) Detours: • Washington Blvd • Henry Street • Dock Street • Canal Street • N. & S. State Streets

  19. Stage 1B (Center Pier Construction): February - June 2019 Road Closures: • Atlantic Street (Dock St to S. State St) Detours: • Washington Blvd • Henry Street • Dock Street • Canal Street • N. & S. State Streets

  20. Stages 2 & 3: June 28 th – September 9 th , 2019 Road Closures: • Manhattan Street (access to Atlantic) • South State Street (btw Guernsey Avenue & Exit 8 NB off-ramp) – Station only access from Washington Blvd. • Atlantic Street (btw Dock St & N. State St) • Dock Street (btw Atlantic St & John Street) • Atlantic Street (btw S. State St & Dock St) Detours: • Guernsey Avenue (closed to SB traffic from N. State St) Washington Blvd • Washington Blvd, Henry St. to Canal St.

  21. Stages 2 & 3: June 28 th – September 9 th , 2019 Road Closures: • Manhattan Street (access to Atlantic) • South State Street (btw Guernsey Avenue & Exit 8 NB off-ramp) – Station only access from Washington Blvd. • Atlantic Street (btw Dock St & N. State St) • Dock Street (btw Atlantic St & John Street) • Atlantic Street (btw S. State St & Dock St) Detours: • Guernsey Avenue (closed to SB traffic from N. State St) Washington Blvd • Washington Blvd, Henry St. to Canal St.

  22. Pedestrian Detour of Atlantic Street: June - September 2019 Sidewalk Closures: • Atlantic Street (btw N. or S. State St & Dock St) Detours: • Guernsey Avenue • Xing over Tracks via Station • Station Place • Access to S. State Street until Stage 2 (June 2019)

  23. Pedestrian Detour of Atlantic Street: June - September 2019 Sidewalk Closures: • Atlantic Street (btw N. or S. State St & Dock St) Detours: • Guernsey Avenue • Xing over Tracks via Station • Station Place • Access to S. State Street until Stage 2 (June 2019)

  24. THANK YOU!!! Regular Updates: on the web: http://atlanticstreetbridge.com on Facebook: atlanticstreetbridge on Twitter: @Atlantic_Street Sign up for Email Announcements on the Website Email: info@atlanticstreetbridge.com Project Signage in Station and Downtown Regular Public Meetings Flyers and Bulletins

  25. Atlantic Street Bridge Project CTDOT Project Nos. 1 3 5 -3 0 1 & 3 0 1 -1 6 3 ( Phase 2 ) Reconstruction of Atlantic Street & Metro ‐ North RR Bridge Replacement | Track & Station Infrastructure Improvements City of Stamford www.AtlanticStreetBridge.com

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend