VT 14 East Montpelier Bridge Project Informational Meeting
February 22, 2017
VT 14 East Montpelier Bridge Project Informational Meeting - - PowerPoint PPT Presentation
VT 14 East Montpelier Bridge Project Informational Meeting February 22, 2017 Welcome & Introductions VTrans Mark Sargent, Project Manager Wayne Symonds, Structures Program Manager Chris Barker, Resident Construction Engineer
February 22, 2017
Project Consultant - Design
Project Consultant – Outreach & Communications
Winooski River in village of East Montpelier
in vicinity of the bridge
signal
setting:
What have we done to lay the ground work for a successful project?
Utility companies relocating
Utility companies relocating
Ride/Slide Concept
during the day, because we could take advantage of the period when VT 14 was closed to work when the traffic is simplified. With US 2 work at night, there is less advantage. Prefabricated Temporary Bridge
to traffic in spring 2018
Summer-Fall 2017 2018 Spring 2019
Summer-Fall 2017 2018 Spring 2019
CONSTRUCT TEMPORARY DETOUR
Summer-Fall 2017 2018 Spring 2019
Summer-Fall 2017 2018 Spring 2019
TEMPORARY BRIDGE IN PLACE, BUT NOT OPEN TO TRAFFIC
Summer-Fall 2017 2018 Spring 2019
Summer-Fall 2017 2018 Spring 2019
Summer-Fall 2017 2018 Spring 2019
Summer-Fall 2017 2018 Spring 2019
Summer-Fall 2017 2018 Spring 2019
Summer-Fall 2017 2018 Spring 2019
Summer-Fall 2017 2018 Spring 2019
Pre-cast concrete pier caps, for accelerated construction
Summer-Fall 2017 2018 Spring 2019
Summer-Fall 2017 2018 Spring 2019
Summer-Fall 2017 2018 Spring 2019 Erection of steel beams, may require closure of the temporary bridge for a few days.
Summer-Fall 2017 2018 Spring 2019 Pre-cast concrete deck panels, built off site in advance, the contractor may elect to close the temporary bridge for a few days to complete this work.
Summer-Fall 2017 2018 Spring 2019 Additional work on VT 14 south
completed in 2018. This may be done during bridge construction,
Summer-Fall 2017 2018 Spring 2019
Detour route
Summer-Fall 2017 2018 Spring 2019
Summer-Fall 2017 2018 Spring 2019
Summer-Fall 2017 2018 Spring 2019
Summer-Fall 2017 2018 Spring 2019 Final Conditions - 2019
proposes 24 hour staffing of the fire department in order to maintain response times.
coordinate with EMFD and EMES to give priority to Emergency Response in the work zone.
travelers and businesses during construction
methods
maintenance structure
flow.
temporary bridge on VT 14 and the accelerated schedule will minimize the burden on travelers and businesses.
maintenance materials including weathering steel and stainless reinforcement
deck which reduces maintenance.
improve the longevity of the pavement.