SLIDE 1 Atlantic Street Bridge Project
CTDOT Project Nos. 135-326 (Phase 1) & 135-301 (Phase 2)
Reconstruction of Atlantic Street & Metro-North RR Bridge Replacement | City of Stamford www.AtlanticStreetBridge.com
SLIDE 2
Atlantic Street Bridge Project
Presentation to: April 10, 2018
SLIDE 3 Agenda
- Introduction
- Phase 1 Construction Progress Update
- Phase 2 Construction Information
- Schedule Update
- Questions and Answers
SLIDE 4 Connecticut Department of Transportation
Phase 1 Project Team
CTDOT District 3 Office:
Domenic LaRosa, P.E.
Matthew Cleary, P.E.
James Pelletier Jr., P.E. - Supervising Engineer Paul Ezigbo
Louis Eveno
SLIDE 5 Phase 1 Contract Information
- State Project No.: 135-326
- Owner: Connecticut Dept. of Transportation
- Inspector: Connecticut Dept. of Transportation
- Contractor: Yonkers Contracting Company
- Original Contract Value: $ 33,881,217
- Current Contract Value: $36,317,496
- Notice to Proceed: February 8, 2016
- Contract Completion Date: June 30, 2018
SLIDE 6 Phase 1 Project Elements
- Utility Corridor (Pipe Jacking)
- Reconfigure I-95 NB Exit 8 Off-Ramp
- New Ramp Bridge over Atlantic Street
- Contaminated Soil Management
- Sanitary Sewer Relocation
- Drainage along South State and Canal
- Minor Track Level Work (Catenary 370B)
SLIDE 7 Utility Relocations
- Eversource Energy & Frontier Communications
- Extensive Coordination
- Sequential Operation
- No State Financial Participation
- Estimated Completion: December 2018
SLIDE 8
Pre-Construction Conditions
SLIDE 9
Proposed Construction
SLIDE 10
Proposed Conditions
SLIDE 11
Phase 1 Construction Progress
Exit 8 Off Ramp Wall 102 South State St
SLIDE 12
Phase 1 Construction Progress
Wall 107 Manhattan St Wall 103 South State St
SLIDE 13 Upcoming Local Impacts
- Drainage Crossings on Atlantic and Canal St
(Ongoing)
- Paving – South State St, Exit 8 Off Ramp and
I-95 NB Right Shoulder (04/16/2018)
- Wall 107 Construction on Manhattan St
(05/07/2018)
SLIDE 14 Connecticut Department of Transportation
Phase 2 Project Team
CTDOT District 3A Office:
Domenic LaRosa, P.E.
Dean Cerasoli, P.E.
- Assistant District Engineer
John Antonucci, P.E.
Mohammad Masoud
HAKS, Inc. (Construction Engineering & Inspection): Kevin Conroy, P.E.
SLIDE 15 Phase 2 Contract Information
- State Project Nos.: 135-301 & 301-163
- Owner: Connecticut Dept. of Transportation
- Inspector: HAKS
- Contractor: Halmar International
- Contract Value: $ 74,846,308
- Notice to Proceed: August 28, 2017
- Contract Completion Date: November 30, 2020
SLIDE 16 Phase 2 Project Elements
- Railroad Bridge Replacement (ABC)
- Widening and Lowering of Atlantic Street
- Streetscaping and Multimodal Enhancements
- Railroad Catenary Replacements
- New Track 7 (New Canaan Branch Line)
- Northern Passenger Platform Extension
SLIDE 17 Phase 2 Major Activities
2018
– Installation of Temporary Railroad “Jump Spans” – Off-site Construction of New Bridge Superstructure Components
2019
- Construct New Bridge Abutments & Center Pier (Feb - June)
- Roll-In & Installation of New Superstructure (6/28 – 7/8)
- Remove Jump Spans
- Demolish Portions of Existing Bridge
- Install New Superstructure Sections
- Restore Rail Operations
- Final Roadway Lowering and Reconstruction (7/9 – 9/7)
2020
- Track 7 Construction and Passenger Platform Extension
SLIDE 18 Traffic Impacts During Phase 2
- Continued Temporary Lane Closures
(Atlantic Street, South State Street)
- Temporary Detours during Jump Span
Installation and Roll-In Period (Atlantic St, Dock St, South State St)
- Approx. 6 Month Closure of Atlantic Street
to Install Center Pier and Complete Roadway Lowering
SLIDE 19 Public Outreach During Construction
www.atlanticstreetbridge.com
- Social Media Presence
- Mailing List / Email Blasts
- News Releases
- Public Informational Meetings
- Consistent Coordination with City,
MNRR & Stakeholders
SLIDE 20 Current Schedule
ACTIVITY DATE
START OF PHASE 1 JUNE 2016 BEGIN UTILITY RELOCATIONS SPRING 2017 START OF PHASE 2 FALL 2017 PHASE 1 COMPLETE JUNE 2018 UTILITIES COMPLETE DECEMBER 2018 ATLANTIC STREET CLOSED FEBRUARY 2019 INSTALL NEW BRIDGE JUNE 27 – JULY 8, 2019 REOPEN ATLANTIC STREET SEPTEMBER 2019 PHASE 2 COMPLETE SUMMER 2020
SLIDE 21
Pre-Construction Conditions
SLIDE 22
Proposed Conditions
SLIDE 23
Existing Railroad Bridge
SLIDE 24
Proposed Railroad Bridge
SLIDE 25
THANK YOU…
FOR YOUR TIME AND ATTENTION QUESTIONS ARE WELCOMED
SLIDE 26 Additional Considerations
- Multimodal Accommodations
- Provides for Future Bike Lanes
- Beautification
- Use of Concrete Form Liner
- Incorporation of City Streetscape
Standards
- Preservation
- Salvage of Existing Brownstone
- Partial Funding of South End Historic
Neighborhood Preservation Plan