Atlantic Street Bridge Project CTDOT Project Nos. 135-326 (Phase 1) - - PowerPoint PPT Presentation

atlantic street bridge project
SMART_READER_LITE
LIVE PREVIEW

Atlantic Street Bridge Project CTDOT Project Nos. 135-326 (Phase 1) - - PowerPoint PPT Presentation

Atlantic Street Bridge Project CTDOT Project Nos. 135-326 (Phase 1) & 135-301 (Phase 2) Reconstruction of Atlantic Street & Metro-North RR Bridge Replacement | City of Stamford www.AtlanticStreetBridge.com Atlantic Street Bridge Project


slide-1
SLIDE 1

Atlantic Street Bridge Project

CTDOT Project Nos. 135-326 (Phase 1) & 135-301 (Phase 2)

Reconstruction of Atlantic Street & Metro-North RR Bridge Replacement | City of Stamford www.AtlanticStreetBridge.com

slide-2
SLIDE 2

Atlantic Street Bridge Project

Presentation to: April 10, 2018

slide-3
SLIDE 3

Agenda

  • Introduction
  • Phase 1 Construction Progress Update
  • Phase 2 Construction Information
  • Schedule Update
  • Questions and Answers
slide-4
SLIDE 4

Connecticut Department of Transportation

Phase 1 Project Team

CTDOT District 3 Office:

Domenic LaRosa, P.E.

  • District Engineer

Matthew Cleary, P.E.

  • Asst District Engineer

James Pelletier Jr., P.E. - Supervising Engineer Paul Ezigbo

  • Project Engineer

Louis Eveno

  • Chief Inspector
slide-5
SLIDE 5

Phase 1 Contract Information

  • State Project No.: 135-326
  • Owner: Connecticut Dept. of Transportation
  • Inspector: Connecticut Dept. of Transportation
  • Contractor: Yonkers Contracting Company
  • Original Contract Value: $ 33,881,217
  • Current Contract Value: $36,317,496
  • Notice to Proceed: February 8, 2016
  • Contract Completion Date: June 30, 2018
slide-6
SLIDE 6

Phase 1 Project Elements

  • Utility Corridor (Pipe Jacking)
  • Reconfigure I-95 NB Exit 8 Off-Ramp
  • New Ramp Bridge over Atlantic Street
  • Contaminated Soil Management
  • Sanitary Sewer Relocation
  • Drainage along South State and Canal
  • Minor Track Level Work (Catenary 370B)
slide-7
SLIDE 7

Utility Relocations

  • Eversource Energy & Frontier Communications
  • Extensive Coordination
  • Sequential Operation
  • No State Financial Participation
  • Estimated Completion: December 2018
slide-8
SLIDE 8

Pre-Construction Conditions

slide-9
SLIDE 9

Proposed Construction

slide-10
SLIDE 10

Proposed Conditions

slide-11
SLIDE 11

Phase 1 Construction Progress

Exit 8 Off Ramp Wall 102 South State St

slide-12
SLIDE 12

Phase 1 Construction Progress

Wall 107 Manhattan St Wall 103 South State St

slide-13
SLIDE 13

Upcoming Local Impacts

  • Drainage Crossings on Atlantic and Canal St

(Ongoing)

  • Paving – South State St, Exit 8 Off Ramp and

I-95 NB Right Shoulder (04/16/2018)

  • Wall 107 Construction on Manhattan St

(05/07/2018)

slide-14
SLIDE 14

Connecticut Department of Transportation

Phase 2 Project Team

CTDOT District 3A Office:

Domenic LaRosa, P.E.

  • District Engineer

Dean Cerasoli, P.E.

  • Assistant District Engineer

John Antonucci, P.E.

  • Supervising Engineer

Mohammad Masoud

  • Project Engineer

HAKS, Inc. (Construction Engineering & Inspection): Kevin Conroy, P.E.

  • Resident Engineer
slide-15
SLIDE 15

Phase 2 Contract Information

  • State Project Nos.: 135-301 & 301-163
  • Owner: Connecticut Dept. of Transportation
  • Inspector: HAKS
  • Contractor: Halmar International
  • Contract Value: $ 74,846,308
  • Notice to Proceed: August 28, 2017
  • Contract Completion Date: November 30, 2020
slide-16
SLIDE 16

Phase 2 Project Elements

  • Railroad Bridge Replacement (ABC)
  • Widening and Lowering of Atlantic Street
  • Streetscaping and Multimodal Enhancements
  • Railroad Catenary Replacements
  • New Track 7 (New Canaan Branch Line)
  • Northern Passenger Platform Extension
slide-17
SLIDE 17

Phase 2 Major Activities

2018

– Installation of Temporary Railroad “Jump Spans” – Off-site Construction of New Bridge Superstructure Components

2019

  • Construct New Bridge Abutments & Center Pier (Feb - June)
  • Roll-In & Installation of New Superstructure (6/28 – 7/8)
  • Remove Jump Spans
  • Demolish Portions of Existing Bridge
  • Install New Superstructure Sections
  • Restore Rail Operations
  • Final Roadway Lowering and Reconstruction (7/9 – 9/7)

2020

  • Track 7 Construction and Passenger Platform Extension
slide-18
SLIDE 18

Traffic Impacts During Phase 2

  • Continued Temporary Lane Closures

(Atlantic Street, South State Street)

  • Temporary Detours during Jump Span

Installation and Roll-In Period (Atlantic St, Dock St, South State St)

  • Approx. 6 Month Closure of Atlantic Street

to Install Center Pier and Complete Roadway Lowering

slide-19
SLIDE 19

Public Outreach During Construction

  • Project Website

www.atlanticstreetbridge.com

  • Social Media Presence
  • Mailing List / Email Blasts
  • News Releases
  • Public Informational Meetings
  • Consistent Coordination with City,

MNRR & Stakeholders

slide-20
SLIDE 20

Current Schedule

ACTIVITY DATE

START OF PHASE 1 JUNE 2016 BEGIN UTILITY RELOCATIONS SPRING 2017 START OF PHASE 2 FALL 2017 PHASE 1 COMPLETE JUNE 2018 UTILITIES COMPLETE DECEMBER 2018 ATLANTIC STREET CLOSED FEBRUARY 2019 INSTALL NEW BRIDGE JUNE 27 – JULY 8, 2019 REOPEN ATLANTIC STREET SEPTEMBER 2019 PHASE 2 COMPLETE SUMMER 2020

slide-21
SLIDE 21

Pre-Construction Conditions

slide-22
SLIDE 22

Proposed Conditions

slide-23
SLIDE 23

Existing Railroad Bridge

slide-24
SLIDE 24

Proposed Railroad Bridge

slide-25
SLIDE 25

THANK YOU…

FOR YOUR TIME AND ATTENTION QUESTIONS ARE WELCOMED

slide-26
SLIDE 26

Additional Considerations

  • Multimodal Accommodations
  • Provides for Future Bike Lanes
  • Beautification
  • Use of Concrete Form Liner
  • Incorporation of City Streetscape

Standards

  • Preservation
  • Salvage of Existing Brownstone
  • Partial Funding of South End Historic

Neighborhood Preservation Plan