Atlantic Street Bridge Project CTDOT Project Nos. 135-326 (Phase 1) & 135-301 (Phase 2) Reconstruction of Atlantic Street & Metro-North RR Bridge Replacement | City of Stamford www.AtlanticStreetBridge.com Atlantic Street Bridge Project


  1. Atlantic Street Bridge Project CTDOT Project Nos. 135-326 (Phase 1) & 135-301 (Phase 2) Reconstruction of Atlantic Street & Metro-North RR Bridge Replacement | City of Stamford www.AtlanticStreetBridge.com

  2. Atlantic Street Bridge Project Presentation to: April 10, 2018

  3. Agenda • Introduction • Phase 1 Construction Progress Update • Phase 2 Construction Information • Schedule Update • Questions and Answers

  4. Connecticut Department of Transportation Phase 1 Project Team CTDOT District 3 Office: Domenic LaRosa, P.E. - District Engineer Matthew Cleary, P.E. - Asst District Engineer James Pelletier Jr., P.E. - Supervising Engineer Paul Ezigbo - Project Engineer Louis Eveno - Chief Inspector

  5. Phase 1 Contract Information • State Project No.: 135-326 • Owner: Connecticut Dept. of Transportation • Inspector: Connecticut Dept. of Transportation • Contractor: Yonkers Contracting Company • Original Contract Value: $ 33,881,217 • Current Contract Value: $36,317,496 • Notice to Proceed: February 8, 2016 • Contract Completion Date: June 30, 2018

  6. Phase 1 Project Elements • Utility Corridor (Pipe Jacking) • Reconfigure I-95 NB Exit 8 Off-Ramp • New Ramp Bridge over Atlantic Street • Contaminated Soil Management • Sanitary Sewer Relocation • Drainage along South State and Canal • Minor Track Level Work (Catenary 370B)

  7. Utility Relocations • Eversource Energy & Frontier Communications - Extensive Coordination - Sequential Operation - No State Financial Participation - Estimated Completion: December 2018

  8. Pre-Construction Conditions

  9. Proposed Construction

  10. Proposed Conditions

  11. Phase 1 Construction Progress Exit 8 Off Ramp Wall 102 South State St

  12. Phase 1 Construction Progress Wall 107 Wall 103 Manhattan St South State St

  13. Upcoming Local Impacts • Drainage Crossings on Atlantic and Canal St (Ongoing) • Paving – South State St, Exit 8 Off Ramp and I-95 NB Right Shoulder (04/16/2018) • Wall 107 Construction on Manhattan St (05/07/2018)

  14. Connecticut Department of Transportation Phase 2 Project Team CTDOT District 3A Office: Domenic LaRosa, P.E. - District Engineer Dean Cerasoli, P.E. - Assistant District Engineer John Antonucci, P.E. - Supervising Engineer Mohammad Masoud - Project Engineer HAKS, Inc. (Construction Engineering & Inspection): Kevin Conroy , P.E. - Resident Engineer

  15. Phase 2 Contract Information • State Project Nos.: 135-301 & 301-163 • Owner: Connecticut Dept. of Transportation • Inspector: HAKS • Contractor: Halmar International • Contract Value: $ 74,846,308 • Notice to Proceed: August 28, 2017 • Contract Completion Date: November 30, 2020

  16. Phase 2 Project Elements • Railroad Bridge Replacement (ABC) • Widening and Lowering of Atlantic Street • Streetscaping and Multimodal Enhancements • Railroad Catenary Replacements • New Track 7 (New Canaan Branch Line) • Northern Passenger Platform Extension

  17. Phase 2 Major Activities 2018 – Installation of Temporary Railroad “Jump Spans” – Off-site Construction of New Bridge Superstructure Components 2019 - Construct New Bridge Abutments & Center Pier (Feb - June) - Roll-In & Installation of New Superstructure (6/28 – 7/8) Remove Jump Spans • Demolish Portions of Existing Bridge • Install New Superstructure Sections • Restore Rail Operations • - Final Roadway Lowering and Reconstruction (7/9 – 9/7) 2020 - Track 7 Construction and Passenger Platform Extension

  18. Traffic Impacts During Phase 2 • Continued Temporary Lane Closures (Atlantic Street, South State Street) • Temporary Detours during Jump Span Installation and Roll-In Period (Atlantic St, Dock St, South State St) • Approx. 6 Month Closure of Atlantic Street to Install Center Pier and Complete Roadway Lowering

  19. Public Outreach During Construction • Project Website www.atlanticstreetbridge.com • Social Media Presence • Mailing List / Email Blasts • News Releases • Public Informational Meetings • Consistent Coordination with City, MNRR & Stakeholders

  20. Current Schedule ACTIVITY DATE START OF PHASE 1 JUNE 2016 BEGIN UTILITY RELOCATIONS SPRING 2017 START OF PHASE 2 FALL 2017 PHASE 1 COMPLETE JUNE 2018 UTILITIES COMPLETE DECEMBER 2018 ATLANTIC STREET CLOSED FEBRUARY 2019 INSTALL NEW BRIDGE JUNE 27 – JULY 8, 2019 REOPEN ATLANTIC STREET SEPTEMBER 2019 PHASE 2 COMPLETE SUMMER 2020

  21. Pre-Construction Conditions

  22. Proposed Conditions

  23. Existing Railroad Bridge

  24. Proposed Railroad Bridge

  25. THANK YOU… FOR YOUR TIME AND ATTENTION QUESTIONS ARE WELCOMED

  26. Additional Considerations • Multimodal Accommodations • Provides for Future Bike Lanes • Beautification • Use of Concrete Form Liner • Incorporation of City Streetscape Standards • Preservation • Salvage of Existing Brownstone • Partial Funding of South End Historic Neighborhood Preservation Plan

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.