Solar Energy Generation from a Technical and Economic Perspective
GEON Group
Sharam Roghani – GM OMAN, May 2th, 2018
Solar Energy Generation from a Technical and Economic Perspective - - PowerPoint PPT Presentation
Solar Energy Generation from a Technical and Economic Perspective GEON Group Sharam Roghani GM OMAN, May 2 th , 2018 2. Introduction of GEON Group GEON Group was established by Sharam Roghani in 2012 Management Sharam Roghani Selected
Sharam Roghani – GM OMAN, May 2th, 2018
Author: Sharam Roghani 2
5
Sharam Roghani
CEO GEON Group
Vitae
VISPIRON AG Business Development
Lead Engineer BMW Safety Systems
BMW Crash Management Ferchau Design Engineer
Selected References
Over 30 MW installed photovoltaic plant capacity since 2008 Tautenhain, Germany Completed in 2012 Capacity 10 MW Osterweddingen, Germany Completed in 2012 Capacity 1.6 MW Gotha, Germany Completed in 2012 Capacity 1.5 MW Frankfurt Oder, Germany Completed in 2011 Capacity 1.5 MW Landsberg, Germany Completed in 2011 Capacity 1.2 MW Hildburghausen, Germany Completed in 2011 Capacity 5.5 MW
Management
10 MW photovoltaic plant, Tautenhain, Germany, 2012
Establishment of GEON Group in 2012 Objective: Project development in renewable energy sector
Development of 120 MW PV Plant in Iran ü PPA was signed in 2017 Ø Next steps: Ø Project funding Ø EPC contracting
02/05/18
The mechanics of solar energy projects that work
3 Author: Sharam Roghani
Energy source Converting technology Measurement Feed into grid Earning money
Earning money by converting sun-power to electricity!
02/05/18
The mechanics of solar energy projects that work
4 Author: Sharam Roghani
02/05/18
The mechanics of solar energy projects that work
5 Author: Sharam Roghani
02/05/18
6 Author: Sharam Roghani
Investment Photovoltaic PV-Tracker CSP Ø Tax Ø Custom
The mechanics of solar energy projects that work
02/05/18
The mechanics of solar energy projects that work
7 Author: Sharam Roghani
02/05/18
The mechanics of solar energy projects that work
8 Author: Sharam Roghani
Ø Renewable Energy Strategy Ø PPA (bankability) Ø Fed in tariff (yes/No) Ø Currency (volatility/stability) Ø Payment duration (years) Ø Government Payment Guaranty Ø Profitability / Amortization / Capital Mix Ø Grid Infrastructure Ø Grid capacity Ø Grid connection Ø Electrical post to be erected? Ø Access to land Ø Cost of land Ø Bankable land contracts Ø Administrative support for project developer Ø Tax / Custom regulatory Financial Equity Ø Expected ROI
Ø Amortization
Ø Capital mix Ø Risk analysis Debt Ø Interest rate Ø Capital mix Ø Structuring costs
Influences
cost of capital
Financial
Legal
02/05/18
The mechanics of solar energy projects that work
9 Author: Sharam Roghani
02/05/18
10 Author: Sharam Roghani
Operating & Maintenance Photovoltaic PV-Tracker CSP Ø No mechanical parts! Ø Low maintenance costs Ø Low operating costs Ø Tracker based on mechanical components! Ø A lot of mechanical components
The mechanics of solar energy projects that work
02/05/18
The mechanics of solar energy projects that work
11 Author: Sharam Roghani
02/05/18
12 Author: Sharam Roghani
Irradiation [kWh/kWp] Capacity [kWh] Yield [kWh]
Yield
Example: 2.000 kWh/kWp X 1000 kWh = 2.000.000 kWh/year
Efficient technologies and designs for desert regions
02/05/18
The long term perspective
13 Author: Sharam Roghani
Demand Peak over the year
Source: OETC
Insulation pattern over the year
Example Fahud, 1987-1992; Source: AER, 2008
Electricity Production in 2016
Source: AERO annual report 2016
Source: OPWP, 2014
Ø Demand-Peak match insulation–Peak Ø By installing renewable capacities, cut
02/05/18
CSP and PV (including regional reference projects)
14 Author: Sharam Roghani
Noor I
02/05/18
Author: Sharam Roghani 15
02/05/18
GEON Group GmbH & Co. KG Sharam Roghani – General Manager Neubruch Straße 12F D-85774 Unterföhring Mobil: +49 (0) 171 757 3 757 Email: sharam.roghani@geongroup.de Homepage: www.geongroup.de