Snowdens Mill/Falling Creek Stream Restoration Public Meeting - - PowerPoint PPT Presentation

snowdens mill falling creek
SMART_READER_LITE
LIVE PREVIEW

Snowdens Mill/Falling Creek Stream Restoration Public Meeting - - PowerPoint PPT Presentation

Snowdens Mill/Falling Creek Stream Restoration Public Meeting December 5, 2017 Introductions Beth Forbes, PE Project Manager, Montgomery County DEP/JV Miranda Reid Watershed Planner, Montgomery County DEP Lucia Noya, PE


slide-1
SLIDE 1

Snowdens Mill/Falling Creek

Public Meeting December 5, 2017

Stream Restoration

slide-2
SLIDE 2

Introductions

 Beth Forbes, PE

 Project Manager, Montgomery County DEP/JV

 Miranda Reid

 Watershed Planner, Montgomery County DEP

 Lucia Noya, PE

 Project Manager, Rummel, Klepper & Kahl, LLP (RK&K)

 Jason Coleman, PE

 Project Designer, Rummel, Klepper & Kahl, LLP (RK&K)

slide-3
SLIDE 3

Today’s Agenda

 Watershed Management Overview  Project Background  Existing Conditions  Restoration Goals and Approach  Construction: What to Expect  Project Schedule and Next Steps

slide-4
SLIDE 4

Sources of Water

 About 97% is salt water  About 2% is frozen  Only 1% is available for drinking water

 Country – 57% surface water  Maryland – 74% surface water

 Potential for greater impacts from runoff in Maryland

Sources of Water

Salt Frozen Drinking

slide-5
SLIDE 5

District of Columbia

Impervious: Not allowing water to soak through the ground

 500 sq. miles  Over 1,000,000 people

 Second only to Baltimore City within Maryland in average people per square mile  184 languages spoken

 About 12% impervious surface overall

 About the size of Washington DC

 Over 1,500 miles of streams  Two major river basins:

 Potomac  Patuxent

 Eight local watersheds

Montgomery County, MD

slide-6
SLIDE 6

 A watershed is an area from which the water above and below ground drains to the same place.  Different scales of watersheds:

 Chesapeake Bay  Eight local watersheds (Anacostia)  Smaller Tributary (Paint Branch)  Neighborhood (to a storm drain)

What is a Watershed?

slide-7
SLIDE 7

Anacostia Watershed

slide-8
SLIDE 8

Paint Branch Watershed

 Paint Branch is a Class III Stream

 Growth and propagation of brown trout

 Special Protection Area (SPA)

 High-quality or unusually sensitive water resources or environmental features  Resources threatened by land use changes (such as development) unless special protective measures are taken  Developers must follow strict requirements to reduce threat to water resources and environmental features

Upper Paint Branch SPA

slide-9
SLIDE 9

Paint Branch Watershed

 Paint Branch is a Class III Stream

 Growth and propagation of brown trout

 Special Protection Area (SPA)

 High-quality or unusually sensitive water resources or environmental features  Resources threatened by land use changes (such as development) unless special protective measures are taken  Developers must follow strict requirements to reduce threat to water resources and environmental features

slide-10
SLIDE 10

Water that does not soak into the ground becomes surface runoff. This runoff flows

  • ver hard surfaces like rooftops,

driveways and parking lots collecting potential contaminants and flows:

  • Directly into streams
  • Into storm drain pipes, eventually leading to

streams

  • Into stormwater management facilities, then

streams

Two Major Issues: Volume/Timing of Runoff Water Quality

What is Runoff?

slide-11
SLIDE 11

Land Use Change

slide-12
SLIDE 12

Historic Aerial - 1951

slide-13
SLIDE 13

Historic Aerial - 1970

slide-14
SLIDE 14

Historic Aerial - 1979

slide-15
SLIDE 15

Historic Aerial - 1993

slide-16
SLIDE 16

Historic Aerial - 2017

slide-17
SLIDE 17

Historic Aerial - 2017

slide-18
SLIDE 18

Runoff

Philadelphia Water Department

slide-19
SLIDE 19

Urban vs. Forested Watersheds

 Urban Mercer Creek

 Streamflow increases more quickly  Higher Peak Flow  Lower Baseflow  Flash Floods  Increased Erosion

 Forested Newaukum Creek

 Lower peak flow – slower to rise  Higher base flow during periods

  • f no rain  Supports fish

USGS

slide-20
SLIDE 20

Watershed 101

Impervious Surface Impacts to Streams

Stream in a watershed with 8% impervious cover. Stream in a watershed with 20% impervious cover. Stream in a watershed with 30% impervious cover.

slide-21
SLIDE 21

What is the County Doing to Protect Streams?

 Must meet regulatory requirements

 Federal Clean Water Act permit program  MS4 permit – Municipal Separate Storm Sewer System

 Applies to all large and medium Maryland jurisdictions  County Programs

 Restore our streams and watersheds

 Add runoff management

 Meet water quality protection goals

 Reduce pollutants entering streams

 Education and engage stakeholders

 Individual actions make a difference

 Focus on watershed with greatest impacts

slide-22
SLIDE 22

Project Selection

 Located in a key watershed (Middle Potomac-Anacostia- Occoquan, tributaries within the Paint Branch Watershed) for stream restoration  Erosion of banks threatening utilities and natural resources  History of previous point repairs  Opportunity for water quality and ecological improvements  Countywide Stream Protection Strategy and Lower Paint branch Watershed Study  Anacostia River Watershed impaired for bacteria, PCBs, trash and debris, excess nitrogen and phosphorus, low dissolved

  • xygen, and excess sediment
slide-23
SLIDE 23

Project Site

slide-24
SLIDE 24

Lower Falling Creek Reach

slide-25
SLIDE 25

Existing Conditions

Typical conditions of Falling Creek channel in lower reach downstream of Falling Creek Ct.

slide-26
SLIDE 26

Existing Conditions

Routine erosion of channel banks and under floodplain root zone. Trees will eventually fall into the stream.

slide-27
SLIDE 27

Existing Conditions

Eroded stream banks, debris, and invasive plants in Lower Falling Creek Reach

slide-28
SLIDE 28

Existing Conditions

Channel migration to valley hill slope causing tree fall in lower section of Falling Creek (downstream

  • f Falling Creek Court).
slide-29
SLIDE 29

Restoration Goals

 Minimize natural resources impacts  Improve aquatic & fish habitat  Improve water quality  Bed and bank stabilization  Remove non-native invasive plants (vines/shrubs) within the stream LOD

slide-30
SLIDE 30

Restoration Approach

 Snowdens Mill and Upper Falling Creek

 Raise the existing stream bed elevation such that flood flows leave channel more-frequently to spread energy across floodplain  Realign a portion of the channel in Snowdens Middle Reach (upstream

  • f Serpentine Way) to prevent future erosion and tree fall

Create wetlands and wildlife habitat in abandoned channel

 Lower Falling Creek

 Lower floodplain elevations such that flood flows leave channel more- frequently to spread energy across floodplain  Create riparian wetlands in the lowered floodplain that are highly- connected to groundwater

slide-31
SLIDE 31

Stream Restoration Design

(12)- Falling Creek Lower Reach

slide-32
SLIDE 32

Riffle/Pool Sequence

slide-33
SLIDE 33

Log Grade Control

slide-34
SLIDE 34

Rock Ramp

slide-35
SLIDE 35

Woody Debris/Wildlife Habitat

slide-36
SLIDE 36

Integrated Stream and Wetland System

slide-37
SLIDE 37

Live Staking

slide-38
SLIDE 38

Plantings

slide-39
SLIDE 39

Reforestation

slide-40
SLIDE 40

Construction Entrances

During Construction After Construction

EXAMPLE

slide-41
SLIDE 41

Construction

What to expect

 Duration

 Approximately 6-12 months for each stream reach/area  Class III Stream Closure Period – Oct 1-April 30

 Construction Hours

 Monday through Friday, 7 AM-4 PM

 Safety

 Open sides of site will be fenced with orange construction safety fence to separate construction from residents

 Traffic

 Minor impacts to traffic from entering and exiting construction traffic and contractor parking during the day

 Noise

 Contractor is required to comply with Montgomery County Noise Ordinance – site elevation will help alleviate noise pollution

 Sediment

 Contractor is required to comply with Montgomery County Sediment Control Permit and not track onto roads

slide-42
SLIDE 42

Restoration Monitoring

 County monitoring to evaluate whether project goals are achieved will continue five years after project completion.

 In-stream Habitat  Aquatic Insects  Fisheries

slide-43
SLIDE 43

Project Schedule

 Public Meetings – December 5, 2017 / January 23, 2018  Final Design Plans – Fall 2018  Construction – Spring 2019 – Fall 2020  Cost – estimated $5,432,000 million financed by MCDEP CIP Program using funds generated through Water Quality Protection Charge

slide-44
SLIDE 44

Next Steps

 Design Completion  Permitting  Construction

slide-45
SLIDE 45

Questions?

For more information: Miranda Reid 240-773-0802 Miranda.Reid@montgomerycountymd.gov https://www.montgomerycountymd.gov/water/ restoration/snowdens-mill-falling-creek.html