project mill creek
play

Project Mill Creek Overview of project and use of NEC3 contracts - PowerPoint PPT Presentation

Project Mill Creek Overview of project and use of NEC3 contracts Overview Why harness wind energy in New Zealand? How does Mill Creek fit into the New Zealand wind regime? Overview of the Mill Creek site Key sections of work scope


  1. Project Mill Creek Overview of project and use of NEC3 contracts

  2. Overview • Why harness wind energy in New Zealand? • How does Mill Creek fit into the New Zealand wind regime? • Overview of the Mill Creek site • Key sections of work scope – a picture walk through • Forms of contract • Experiences MERIDIAN ENERGY LIMITED

  3. World wind resource map (source: Riso National Laboratory, Denmark) MERIDIAN ENERGY LIMITED

  4. Executive Summary MERIDIAN ENERGY LIMITED

  5. Mill Creek Site Overview • 26 turbines to the north of Wellington. • 60MW of capacity, generating around 238GWh per annum, or enough for 30,000 homes. • Budget of circa $174m. • 30 months of scheduled work, accumulating in 370,000 hours worked. • Around 1,400 contractors inducted to site. • No Lost Time Incidents. MERIDIAN ENERGY LIMITED

  6. MERIDIAN ENERGY LIMITED

  7. MERIDIAN ENERGY LIMITED

  8. MERIDIAN ENERGY LIMITED

  9. Site roads MERIDIAN ENERGY LIMITED

  10. MERIDIAN ENERGY LIMITED

  11. MERIDIAN ENERGY LIMITED

  12. Switching station MERIDIAN ENERGY LIMITED

  13. Transmission line MERIDIAN ENERGY LIMITED

  14. Turbine supply MERIDIAN ENERGY LIMITED

  15. Turbine supply MERIDIAN ENERGY LIMITED

  16. Appendix MERIDIAN ENERGY LIMITED

  17. Turbine supply MERIDIAN ENERGY LIMITED

  18. Forms of contract • 17 major contracts used to deliver the project. • 11, of which were forms of NEC3, ranging from professional services for engineering design, through to supply variants for large procurement items and: • ECC Option A (priced contract with activity schedule) for transmission line construction and electrical balance of works. • ECC Option C (target contract with activity schedule) for extensive civil works, including, internal and external roads, turbines foundations and hard stands. • We have yet to use the NEC3 form of contract for the turbine supply and installation work stream in NZ, but did use it for turbine supply for our Mt Mercer site in Victoria, Australia. MERIDIAN ENERGY LIMITED

  19. Experiences Pros - The emphasis on early warning and implication for the contractor if they don’t is probably the single biggest advantage over other forms of contract. - Also if you do have a dispute, the mechanics and logic for resolving it are already well defined and help parties reach agreement earlier than using other forms of contract. Look out for: - Contractors that are insufficiently staffed to perform the regular reporting requirements and forward estimates. Especially when there are numerous sub contractors reporting to the main contractor. MERIDIAN ENERGY LIMITED

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend