Project Mill Creek Overview of project and use of NEC3 contracts - - PowerPoint PPT Presentation

project mill creek
SMART_READER_LITE
LIVE PREVIEW

Project Mill Creek Overview of project and use of NEC3 contracts - - PowerPoint PPT Presentation

Project Mill Creek Overview of project and use of NEC3 contracts Overview Why harness wind energy in New Zealand? How does Mill Creek fit into the New Zealand wind regime? Overview of the Mill Creek site Key sections of work scope


slide-1
SLIDE 1

Project Mill Creek

Overview of project and use of NEC3 contracts

slide-2
SLIDE 2

MERIDIAN ENERGY LIMITED

Overview

  • Why harness wind energy in New Zealand?
  • How does Mill Creek fit into the New Zealand wind regime?
  • Overview of the Mill Creek site
  • Key sections of work scope – a picture walk through
  • Forms of contract
  • Experiences
slide-3
SLIDE 3

MERIDIAN ENERGY LIMITED

World wind resource map (source: Riso National Laboratory, Denmark)

slide-4
SLIDE 4

MERIDIAN ENERGY LIMITED

Executive Summary

slide-5
SLIDE 5

MERIDIAN ENERGY LIMITED

Mill Creek Site Overview

  • 26 turbines to the north of

Wellington.

  • 60MW of capacity,

generating around 238GWh per annum, or enough for 30,000 homes.

  • Budget of circa $174m.
  • 30 months of scheduled

work, accumulating in 370,000 hours worked.

  • Around 1,400 contractors

inducted to site.

  • No Lost Time Incidents.
slide-6
SLIDE 6

MERIDIAN ENERGY LIMITED

slide-7
SLIDE 7

MERIDIAN ENERGY LIMITED

slide-8
SLIDE 8

MERIDIAN ENERGY LIMITED

slide-9
SLIDE 9

MERIDIAN ENERGY LIMITED

Site roads

slide-10
SLIDE 10

MERIDIAN ENERGY LIMITED

slide-11
SLIDE 11

MERIDIAN ENERGY LIMITED

slide-12
SLIDE 12

MERIDIAN ENERGY LIMITED

Switching station

slide-13
SLIDE 13

MERIDIAN ENERGY LIMITED

Transmission line

slide-14
SLIDE 14

MERIDIAN ENERGY LIMITED

Turbine supply

slide-15
SLIDE 15

MERIDIAN ENERGY LIMITED

Turbine supply

slide-16
SLIDE 16

MERIDIAN ENERGY LIMITED

Appendix

slide-17
SLIDE 17

MERIDIAN ENERGY LIMITED

Turbine supply

slide-18
SLIDE 18

MERIDIAN ENERGY LIMITED

Forms of contract

  • 17 major contracts used to deliver the project.
  • 11, of which were forms of NEC3, ranging from professional services for

engineering design, through to supply variants for large procurement items and:

  • ECC Option A (priced contract with activity schedule) for transmission

line construction and electrical balance of works.

  • ECC Option C (target contract with activity schedule) for extensive civil

works, including, internal and external roads, turbines foundations and hard stands.

  • We have yet to use the NEC3 form of contract for the turbine supply and

installation work stream in NZ, but did use it for turbine supply for our Mt Mercer site in Victoria, Australia.

slide-19
SLIDE 19

MERIDIAN ENERGY LIMITED

Experiences

Pros

  • The emphasis on early warning and implication for the contractor if they don’t

is probably the single biggest advantage over other forms of contract.

  • Also if you do have a dispute, the mechanics and logic for resolving it are

already well defined and help parties reach agreement earlier than using other forms of contract. Look out for:

  • Contractors that are insufficiently staffed to perform the regular reporting

requirements and forward estimates. Especially when there are numerous sub contractors reporting to the main contractor.