Casablanca Tangier High Speed Line Project Mohammed, SMOUNI - - PowerPoint PPT Presentation

casablanca tangier
SMART_READER_LITE
LIVE PREVIEW

Casablanca Tangier High Speed Line Project Mohammed, SMOUNI - - PowerPoint PPT Presentation

Casablanca Tangier High Speed Line Project Mohammed, SMOUNI Director Of Development, ONCF, Morocco 8 July, Session: Customers, 4 E CONTENT 1- Master Plan for HSL of Morocco 2- Casablanca Tangier HSL Project 3- The Project Progress 4-


slide-1
SLIDE 1

Casablanca – Tangier High Speed Line Project

Mohammed, SMOUNI Director Of Development, ONCF, Morocco 8 July, Session: Customers, 4 E

slide-2
SLIDE 2

CONTENT

1- Master Plan for HSL of Morocco 2- Casablanca – Tangier HSL Project 3- The Project Progress 4- The Project Planning 5-The Project Cost 6- Film of the project

2 Mohammed, SMOUNI - Director of Development, ONCF, Morocco – July 8 - Session: Customers, 4 E

slide-3
SLIDE 3

3 Mohammed, SMOUNI - Director of Development, ONCF, Morocco – July 8 - Session: Customers, 4 E

1- MASTER PLAN FOR HSL OF MOROCCO

Atlantic Line Maghreb Line

  • Length

: 1 500 Km

  • Dates of Opérations : 2010 – 2035
  • Infrastructure costs : 10 billions €
  • Passengers Traffic : 133 millions
  • Travel time

: - 3 to 4 times

  • Road Safety

: - 550 fatalities

  • 6000 injured/year
  • Air Pollution

: -21000 T CO2/year

  • Greenhouse Effect : -800 000 T CO2/year
  • TRI

: 8,5%

3

slide-4
SLIDE 4

Tanger-Kenitra

The 1st Phase of the Master Plan of the HSL

4 Mohammed, SMOUNI - Director of Development, ONCF, Morocco – July 8 - Session: Customers, 4 E

2- CASABLANCA – TANGIER HSL PROJECT

Objective:

  • Connect the two major economic poles
  • f

the Kingdom Casablanca and Tangier;

  • Provide high-level services;
  • Reduction of travel time at :
  • 2h10 instead of 4h45 between

Casablanca and Tangier,

  • 1h20 instead of 3h45 between the

Capital Rabat and Tangier.

slide-5
SLIDE 5

5 Mohammed, SMOUNI - Director of Development, ONCF, Morocco – July 8 - Session: Customers, 4 E

Consistency:

An Integrated Project which includes:

  • Design and construction of 200 km of new HSL between Tangier and Kenitra dedicated

to passengers traffic at a maximum speed of 350 km/h

  • Construction of 2 bases of works and renew of 2 terminal facilities;
  • Acquisition of Rolling Stock and the construction of the maintenance workshop;
  • Operating Preparation (Commercial Operating, maintenance of infrastrcutre and the

rolling stock, testing and commissionning,…);

  • Preparation of the Commercial Offer (onboard services, …).

2- CASABLANCA – TANGIER HSL PROJECT

slide-6
SLIDE 6

6

  • October 2007

: Protocol of Understanding between Morocco and France

  • March 2008

: Setting up of the HSL Project Team

  • April 2009

: Agreement with SNCF to assist ONCF

  • September 2009 : Declaration of Public Utility of the Project
  • July 2010

: Environmental acceptation by the CNEI (Comité National d’Etude d’Impact)

  • December 2010

: Completion of the financing Signature of the contract of trains purchase with Alstom

  • September 2011 : Official launch of the construction
  • April 2013

: Signature of the Contracts of the Design/Construction of the railway equipments

  • January 2015

: Signature of the protocol for Creation of a JV (ONCF – SNCF) for the maintenance of high speed trains

  • April 2015

: Creation of the Railway Training Institute as a JV (ONCF – SNCF)

  • June 2015

: Arrival of the first Train at the Port of Tangier

2-1 Key Dates of the Project

Mohammed, SMOUNI - Director of Development, ONCF, Morocco – July 8 - Session: Customers, 4 E 6

slide-7
SLIDE 7

REGULATORY

7

2.2- The Main Project Constraints and Challenges

Mohammed, SMOUNI - Director of Development, ONCF, Morocco – July 8 - Session: Customers, 4 E

  • Development of technical

standards (seismic, hydraulic, cross winds, ...) for local context;

  • Commercial

Operating authorization

TECHNICAL MANAGERIAL

  • Exceptional topographical

and geotechnical

  • Seismic, climatic
  • Capitalizing
  • n

the management

  • f

the project and transfer of knowledge

  • Change

Management

(training for the maintenance and operating)

  • Management of more than

100 identified major interfaces

slide-8
SLIDE 8

8

2.3- The specifities of the project

  • Land

: 1800 Hectares (360 of forest)

  • Reforestation : 2100 Hectares 6 times of the
  • used superficies of forests
  • Volume of earthworks: 67 millions m3
  • Cuttings

: 65 m deep

  • Embankments : 35 m High
  • Borrowed Materials : 12 millions m3
  • Viaducts

: 12 of a total length of 10 Km

  • The longest viaduct : 3,5 Km long
  • Piles

: 100 Km total length (depth may reach : 70m)

  • Structure

: 1,5 per km

8 Mohammed, SMOUNI - Director of Development, ONCF, Morocco – July 8 - Session: Customers, 4 E

  • Soil

Reinforcement Technics: Stone Columns, Rigid Inclusion Columns, vertical drains

  • Seismic Protection: merlons, anti

seismic benches

  • GSM-R occupies a 4 MHz wide

range of E-GSM (Uplink: 889 -

893 MHz and downlink: 934 - 938 MHz)

slide-9
SLIDE 9

9

  • 10 trains and 46 trucks per day to transport ballast during 24 months
  • 6 trains per week to transport rails and turnouts during12 months
  • 20 locomotives of 3000 HP to ensure trains to the worksites
  • 300 ballast wagons
  • 200 flat wagons for transporting other materials

9

2.4- Logistics

Mohammed, SMOUNI - Director of Development, ONCF, Morocco – July 8 - Session: Customers, 4 E

slide-10
SLIDE 10

10

  • 1 Technical Assistance (SNCF)
  • 2 Project Engineers as an association of French and Moroccan Engineering Offices :

Systra (France) + CID=Team Maroc + Systra Maroc (Morocco) Egis Rail (France) + NOVEC (Morocco)

  • 8 lots of earthworks and 5 lots of viaducts
  • 4 Designers/Constructors of railway equipments:
  • Track, Catenaries and Bases of Works
  • Signaling System
  • Sub-stations/Energy
  • GSM-R
  • 1 Designer/Builder of High Speed Trains:
  • 1 Designer/Constructor of the Maintenance Center

10 Mohammed, SMOUNI - Director of Development, ONCF, Morocco – July 8 - Session: Customers, 4 E

2.5- Key Stakeholders

slide-11
SLIDE 11

99% 65% 88% 31% 55% 80%

By the e

Global Progress

70%

3- THE PROJECT PROGRESS

11 Mohammed, SMOUNI - Director of Development, ONCF, Morocco – July 8 - Session: Customers, 4 E

Land Rolling Stock Maintenance Workshop Preparation of Operations Railway Equipments Civil Engineering

slide-12
SLIDE 12

12

3.1- Maintenance Workshop

COMPOSITION

  • Area of 14 hectares including 20 000

m2 of buildings

  • Capacity : 30 train sets
  • Tracks and catenary : 14 tracks of 10

Km as a total length,

  • Signaling System : 1 computerized

interlocking post

12

PROGRESS

  • On June 29th 2015, the elements
  • f the first train are received.
  • The assembling of the train set is

in progress.

Mohammed, SMOUNI - Director of Development, ONCF, Morocco – July 8 - Session: Customers, 4 E

slide-13
SLIDE 13

13

3.2- High speed trains

COMPOSITION

  • 12 Trains dual power 25 KV AC, DC

3KV capable of operating at 320km/h

  • 200 meters long: 2 motor units

flanking a stretch of 8 double-deck cars (533 seats)

13

PROGRESS

  • The two pre-production trains are

under testing;

  • The
  • ther

trains are being manufactured with an overall progress

  • f 62%

Motrice 2 2nd CL Cafeteria 2nd CL 2nd CL 2nd CL 1st CL 1st CL 2nd CL Motrice 1 Mohammed, SMOUNI - Director of Development, ONCF, Morocco – July 8 - Session: Customers, 4 E

slide-14
SLIDE 14

14

3.3- Stations

14

Cost:

150 M€

CASA VOYAGEURS

Superficies: 8300 m² - 2 yrs of construction

TANGIER

Superficies: 7900 m² - 2 yrs of construction

RABAT AGDAL

Superficies: 23000 m² - 2 yrs of construction

KENITRA

Superficies: 8300 m² - 2 yrs of construction

Mohammed, SMOUNI - Director of Development, ONCF, Morocco – July 8 - Session: Customers, 4 E

slide-15
SLIDE 15

15

  • Elaboration of all rules books related to the High Speed
  • Training of the HST drivers and the Traffic Controllers
  • Creation of the JV (ONCF – SNCF) to maintain the HS Trains
  • Setting up in progress of the Maintenance of the Infrastucture
  • Testing and Commissioning Process
  • Definition of all services offered onboard
  • Design of a new Information System for Ticketing

15

3.4- Operating preparation

Mohammed, SMOUNI - Director of Development, ONCF, Morocco – July 8 - Session: Customers, 4 E

slide-16
SLIDE 16

3.5- The key figures

16 Mohammed, SMOUNI - Director of Development, ONCF, Morocco – July 8 - Session: Customers, 4 E

Length : 200 Km Track : 800 Km of rail (48 000 T) Catenary 25KV : 400 Km

2 Power substations 12 Viaducts: (total length 10 Km) Piles: 100 Km Total Length Concrete Sleepers : 700 000 units

1 Traffic Control Center based in Rabat

67 M m3 of Cutting & Embankments 12 M m3 of Borrowed Materials 1,6 millions Tonnes of ballast 12 High Speed Trains 4 Stations

slide-17
SLIDE 17

17

March-12

2010 2011 2012 2013 2014 2015 2016 2017 2018

Dec.-16

CIVIL ENGINEERING

Dec.-17 Apr.-10

MAINTENANCE WORKSHOP

May-10

RAILWAY EQUIPMENTS

Dec.-16

LANDS

Dec.-15 May-09 Dec.-10 Feb.-18 Dec.-10

4- PROJECT PLANNING

ROLLING STOCK OPERATING’S PREPARATION

Commercial Operating - 1st semester 2018

Testing on CL, Oct.- 15 Train Assembling, July 15 Overall Site Acceptance, Dec.- 17

17

Start of works, Déc.-15

Mohammed, SMOUNI - Director of Development, ONCF, Morocco – July 8 - Session: Customers, 4 E

slide-18
SLIDE 18

18

5- PROJECT COST

  • Initial Cost

: 1,8 billions €:

  • Studies and Project Management :250 M€
  • Infrastructure

:650 M€

  • Railway Equipment

:500 M€

  • Rolling Stock

: 400 M€

  • The final cost will be 10 to 15% more than the initial cost
  • the Unit Cost will reach 8,5 M€ / Km ( railway stations and

rolling stock not included)

18 Mohammed, SMOUNI - Director of Development, ONCF, Morocco – July 8 - Session: Customers, 4 E

slide-19
SLIDE 19

Building the First Africa’s High Speed Line

19

Casablanca – Tangier HSL Project

19 Mohammed, SMOUNI - Director of Development, ONCF, Morocco – July 8 - Session: Customers, 4 E

slide-20
SLIDE 20

FILM

slide-21
SLIDE 21

...Thank you

for your kind attention