site c site c clean ener clean energy pr y project oject
play

Site C Site C Clean Ener Clean Energy Pr y Project oject - PowerPoint PPT Presentation

Site C Site C Clean Ener Clean Energy Pr y Project oject Regional Community Liaison Committee Project Briefing March 11, 2020 Div Diver erting the ting the Peace eace Riv River er Chris Hatton Project Manager, Main Civil Works -


  1. Site C Site C Clean Ener Clean Energy Pr y Project oject Regional Community Liaison Committee Project Briefing March 11, 2020

  2. Div Diver erting the ting the Peace eace Riv River er Chris Hatton Project Manager, Main Civil Works - Diversion

  3. Pr Pres esen enta tation tion over erview view • What is river diversion? • Stages of the river diversion process • Cofferdams • Diversion Tunnels • Debris Management Structures • Flow Management • Questions/discussion 3 March 11, 2020 Regional Community Liaison Committee Meeting

  4. Wha hat t is is riv river er div diver ersion sion? And how do we do it? • River diversion is a construction phase of the Site C project • Lasts approximately three years • Involves temporarily redirecting the flow of the Peace River to support the construction of the Site C dam • Two major processes make up the act of diversion: • 1. Divert river flow (rockfill berm) • 2. Seal off river channel (upstream and downstream cofferdams) 4 March 11, 2020 Regional Community Liaison Committee Meeting

  5. 5

  6. 6 March 11, 2020 Regional Community Liaison Committee Meeting

  7. 7

  8. 8

  9. 9

  10. Riv River er div diver ersion sion tu tunn nnels els • The two large tunnels approximately 750 metres long and 11 metres in diameter • Located on the north bank of the Peace River • Tunnels will have the capacity to pass 3,000 cubic metres of water per second (combined) 10 March 11, 2020 Regional Community Liaison Committee Meeting

  11. Tun unne nels: ls: de design sign, , sa safet ety, , an and mon d monitor itoring ing • Tunnel Stats: • Concrete is up to 2m thick at the inlet and reduces to 0.4m thick at the outlet • Extremely smooth “F4” finish on the concrete liner • Quality is paramount – through inspections and stringent repair requirements • Tunnels are designed to pass debris up to 10m in length 11 March 11, 2020 Regional Community Liaison Committee Meeting

  12. 12

  13. 13

  14. 14

  15. 15

  16. 16

  17. 17

  18. 18

  19. 19

  20. 20

  21. 21

  22. 22

  23. 23

  24. 24

  25. 25

  26. 26

  27. 27

  28. 28

  29. 29

  30. Co Coffer erda dam m sa safet ety, , st stability bility, , an and mo d monit nitor oring ing • Design • Follows all Canadian Dam Association guidelines for dam safety design, check, and independent review • Design is reviewed and approved by the provincial Dam Safety Engineer, as well as BC Hydro’s internal Dam Safety Team • Monitoring • Continuous monitoring of instruments for the entire diversion process • Weekly visual inspections • Bi-Annual Dam Safety Engineer inspections 30 March 11, 2020 Regional Community Liaison Committee Meeting

  31. Site C Site C – Peace Riv eace River er Flo low w Man Management gement Chris Hatton March 11, 2020 Regional Community Liaison Committee Meeting

  32. Wil illi list ston on 20 2020 20 op oper eration tions s for orec ecas ast • During 2020, the Williston Reservoir is forecast to operate at levels near, or above, those observed during 2019. • BC Hydro will continue to operate Williston Reservoir to avoid drafting below 2150 ft (655.3 m) under most conditions. • BC Hydro will manage its requirements within existing Peace Water Use Plan (WUP) operation limits. • BC Hydro will continue to update and meet with First Nations, local government, and public regularly to share information and receive feedback. 32 March 11, 2020 Regional Community Liaison Committee Meeting

  33. Wil illi liston ston Oper Operations in tions in pr prep ep for or Site C Site C d div iver ersion sion • During 2020, Williston Reservoir will fill no higher than 2200 ft (5 ft below full pool), unless filling above this level is necessary to protect the Site C diversion works. • During Sept-Oct 2020, Peace River discharges will be held very low during a critical construction period for the diversion dams. • After the diversion dams are completed (Nov. 2020), Peace River discharges will return to higher (more normal) winter values. 33 March 11, 2020 Regional Community Liaison Committee Meeting

  34. Site Site C C co coffer erda dams: ms: 20 2021 21-24 24 • By 15 Nov 2020, cofferdams will be high enough to manage the “full turbine” discharge from GMS/PCN through the winter months (2020-21) • By spring 2021, cofferdams will be constructed to their full design height (433.9 m) able to manage the 200-yr return period local inflow event with GMS/PCN reduced to minimum discharge • BCH will continue to operate Williston Reservoir with its Storage Reservation Curve and 5-ft buffer until 2023-24 34 March 11, 2020 Regional Community Liaison Committee Meeting

  35. Site C Site C loc local al ba basin sin • Site C local basin (downstream of Peace Canyon) is not regulated • Halfway River is the biggest tributary in this basin. Moberly River is also a significant tributary. • Most severe local inflow events are associated with rainfall systems that travel NW from the Gulf of Mexico into the Peace River basin … very infrequent, and hard to predict the location & amount of rainfall • We should have at least 3 days notice of high flows (and high forebay levels) at Site C. 35 March 11, 2020 Regional Community Liaison Committee Meeting

  36. On Dam Site Construction Update Con Constr structio uction n upda update te 36

  37. On Dam Site Construction Update • 2020 Spring/Summer Schedule • Left Bank • Worker accommodation lodge expansion Con Constr structio uction n upda update te 85 th Avenue Industrial Lands & till conveyor • • Diversion tunnels, portal structures, fish passage • Cofferdams • Core trench & earthfill dam • Right Bank • Powerhouse concrete placement • Powerhouse structural steel placement • Penstock installation • Dam Buttress RCC placement (planned for 2020) • Rip Rap Stockpiling (at Septimus) 37

  38. On Dam Site Summary Schedule: 2020 Construction Activity Anticipated Schedule Diversion Tunnels ready for diversion Q3 2018 to Q3 2020 Con Constr structio uction n upda update te Assemble Till Conveyor Q4 2018 to Q3 2019 Left Bank Dam Grout & Fill Q3 2019 to Q4 2021 Crusher & Aggregate Production Q1 2017 to Q3 2023 Spillway RCC Q2 2019 to Q4 2019 Powerhouse Concrete Q3 2018 to Q4 2022 Penstock Q2 2019 to Q3 2022 Infrastructure Upgrades Ongoing *All major construction activities *To be completed by Q4 2024 38

  39. Le Left Ba ft Bank nk 39

  40. ATCO Two Rivers Lodge Phase 2 Expansion 40

  41. Till Till co convey eyor or sy syst stem em 41

  42. Left Bank Conveyor feeds the Hopper to Stockpile Aggregate 42

  43. Left Bank: Diversion Tunnels and Portals 43

  44. Le Left Ban ft Bank k – Inlet Inlet Por orta tals ls 44

  45. Left Bank – Diversion Tunnel Outlet Portals & Temporary Fishway 45

  46. Tem empo porar ary y Ups Upstr trea eam m Fish Fishway ay (TUF) (TUF) Project Stats CIPC: • Previous update 88% • CIPC 89% completed • Entrance – 100% • Fish lock – 100% • Fish ladder – 81% • Pump station – 100% Mechanical: • Mechanical tasks continue 14 14

  47. 47

  48. Powerhouse, intakes and Service Bay 48

  49. Powerh erhou ouse se – Str Struc uctur tural Stee al Steel l Er Erec ection tion 49

  50. Power erho hous use e – Str Struc uctu tural al Pou our 50

  51. Right Bank: Spillway RCC Placement Complete – winter cladding in place 51

  52. Pen enst stoc ock k As Asse semb mbly 52

  53. Pen ensto stock f k for or Unit Units s 1, 2 and 1, 2 and 3 3 Constr Constructio uction n upda update te 53

  54. Of Off D Dam am Site Site Co Cons nstr truc uctio tion n Up Upda date te Off Dam Site Construction Update Farrell Creek Dry Creek 54 54

  55. Of Off D Dam am Site Site Con Const struc uction tion Upd Update te • Transmission Work • Highway 29 realignment Constr Con structio uction n upda update te • Hudson’s Hope Shoreline Protection • Reservoir clearing work 55

  56. Tran ansmission smission Wor ork: Site k: Site C Sub C Subst station tion 56

  57. Sou South th Ban Bank k Sub Sub-Sta Station tion P&C relay testing & NERC hardening Control Building – Cable Stripping 57

  58. Trans ansmis missi sion on wor ork: k: Trans ansmis missi sion on lines lines 58

  59. Highw Highway ay 29 29 r rea eali lign gnmen ment t loca location tions 59

  60. Highway 29 Construction Timeline 60

  61. Highway 29 realignment – Cache Creek East Halfway River site preparation September 21, 2019 61

  62. Hi High ghway ay 29 29 Rea eali lign gnmen ment t - Cac Cache he Cr Cree eek W k West est 62

  63. Hi High ghway ay 29 29 Rea eali lign gnmen ment t – Half Halfway ay Ri River er 63 63

  64. Por orta tage ge Mou Mount ntain ain Qu Quar arry 64

  65. Hudson’s Hope shoreline protection 65

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend