Regional Community Liaison Committee Project Briefing
March 11, 2020
Site C Site C Clean Ener Clean Energy Pr y Project
- ject
Site C Site C Clean Ener Clean Energy Pr y Project oject - - PowerPoint PPT Presentation
Site C Site C Clean Ener Clean Energy Pr y Project oject Regional Community Liaison Committee Project Briefing March 11, 2020 Div Diver erting the ting the Peace eace Riv River er Chris Hatton Project Manager, Main Civil Works -
Regional Community Liaison Committee Project Briefing
March 11, 2020
Chris Hatton Project Manager, Main Civil Works - Diversion
March 11, 2020 Regional Community Liaison Committee Meeting 3
construction of the Site C dam
And how do we do it?
4 March 11, 2020 Regional Community Liaison Committee Meeting
5
6 March 11, 2020 Regional Community Liaison Committee Meeting
7
8
9
approximately 750 metres long and 11 metres in diameter
Peace River
pass 3,000 cubic metres of water per second (combined)
10 March 11, 2020 Regional Community Liaison Committee Meeting
at the outlet
repair requirements
11 March 11, 2020 Regional Community Liaison Committee Meeting
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
design, check, and independent review
Engineer, as well as BC Hydro’s internal Dam Safety Team
process
30 March 11, 2020 Regional Community Liaison Committee Meeting
Chris Hatton
March 11, 2020 Regional Community Liaison Committee Meeting
during 2019.
to avoid drafting below 2150 ft (655.3 m) under most conditions.
Peace Water Use Plan (WUP) operation limits.
Nations, local government, and public regularly to share information and receive feedback.
32 March 11, 2020 Regional Community Liaison Committee Meeting
2200 ft (5 ft below full pool), unless filling above this level is necessary to protect the Site C diversion works.
held very low during a critical construction period for the diversion dams.
Peace River discharges will return to higher (more normal) winter values.
Wil illi liston ston Oper Operations in tions in pr prep ep for
Site C d div iver ersion sion
33 March 11, 2020 Regional Community Liaison Committee Meeting
manage the “full turbine” discharge from GMS/PCN through the winter months (2020-21)
full design height (433.9 m) able to manage the 200-yr return period local inflow event with GMS/PCN reduced to minimum discharge
Storage Reservation Curve and 5-ft buffer until 2023-24
34 March 11, 2020 Regional Community Liaison Committee Meeting
regulated
Moberly River is also a significant tributary.
rainfall systems that travel NW from the Gulf of Mexico into the Peace River basin … very infrequent, and hard to predict the location & amount of rainfall
(and high forebay levels) at Site C.
35 March 11, 2020 Regional Community Liaison Committee Meeting
36
37
38
Construction Activity Anticipated Schedule Diversion Tunnels ready for diversion Q3 2018 to Q3 2020 Assemble Till Conveyor Q4 2018 to Q3 2019 Left Bank Dam Grout & Fill Q3 2019 to Q4 2021 Crusher & Aggregate Production Q1 2017 to Q3 2023 Spillway RCC Q2 2019 to Q4 2019 Powerhouse Concrete Q3 2018 to Q4 2022 Penstock Q2 2019 to Q3 2022 Infrastructure Upgrades Ongoing *All major construction activities *To be completed by Q4 2024
39
40
ATCO Two Rivers Lodge Phase 2 Expansion
41
42
Left Bank Conveyor feeds the Hopper to Stockpile Aggregate
43
44
45
Left Bank – Diversion Tunnel Outlet Portals & Temporary Fishway
14 14
Project Stats CIPC:
Mechanical:
47
48
Powerh erhou
se – Str Struc uctur tural Stee al Steel l Er Erec ection tion
49
50
51
RCC Placement Complete – winter cladding in place
52
53
Pen ensto stock f k for
Units s 1, 2 and 1, 2 and 3 3
54
Dry Creek
Off Dam Site Construction Update
Farrell Creek
54
55
56
57
Control Building – Cable Stripping P&C relay testing & NERC hardening
58
59
60
Highway 29 Construction Timeline
61
Halfway River site preparation
September 21, 2019
Highway 29 realignment – Cache Creek East
62
Hi High ghway ay 29 29 Rea eali lign gnmen ment t - Cac Cache he Cr Cree eek W k West est
Hi High ghway ay 29 29 Rea eali lign gnmen ment t – Half Halfway ay Ri River er
63 63
64
65
Rese eservoir
learing w ing wor
66
Cur Current ent clearing w learing wor
k:
South Ban Bank, , East Eastern Reser servoir ir
Islands, s, Mid iddle le Reser servoir ir
Cache Cr Creek t to Peace Islan Islands, s, Mid iddle le Reser eservoir
Reservoir Clearing
South Bank, Eastern Reservoir
Green pile burning Debris Management
67
Reservoir clearing: Work plan for winter 2020
Peace Islands Phase 1&2 Cache Creek to Peace Islands South Bank Eastern Reservoir Moberly waste wood disposal
Nancy Pepper Community and Social Mitigation Manager
70
71
72
eace ce Ag Agricultur ricultural al Comp Compen ensa sation tion Fund Fund
2nd Funding Intake Update
73
BC BC Hy Hydr dro
14th Funding Intake Update North Peace Gymnastics Association
Dave Hunter Senior Environmental Coordinator
monitor and communicate results
75
76
Traditional foods at a WMFN camp
0.0 0.1 0.2 0.3 0.4 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40
Year After Impoundment Mercury (mg/kg ww)
Baseline Rise after flooding Gradual decrease Peak New baseline
Years after impoundment
Hypothetical trajectory: fish mercury levels in a new reservoir (the “reservoir effect’)
77
78
Data for retail fish (sold in restaurants and grocery stores) are from Health Canada (2007) and Lowenstein et. Al. (2010) Note: * Refer to Health Canada consumption guidance for retail canned albcore tuna and fresh bigeye tuna.
79
Monitoring Program Fish Tissue Samples Indigenous Community Program Fish Tissue Samples Fish Consumption Information
80
81
0 5 45 120 280 Kilometers Downstream from Site C Dam
Monitoring Program Included within Indigenous Community Program
82
83
monitor and communicate results
84
85
Jobs and business opportunities
contractors listed on Site C website.
from PRRD (19%).
86
Site C Employment Statistics – January 2020 # of Total Workers # of BC Primary Residents % of BC Workers Construction and Environmental Contractors
3,613 2,511 69%
Engineers and Project Team
746 687 92%
Total Workforce
4,359 3,198 73%
Site C Site C job jobs sna s snapsh pshot (J
anua uary 20 y 2020 20)
87
Companies engaged by BC Hydro and Site C contractors to provide goods & services in relation to Site C construction between October – December 2019
88
Community Number of Businesses Community Number of Businesses Cecil Lake 1 Pouce Coupe 2 Charlie Lake 19 Prince George 30 Chetwynd 27 Rolla 1 Dawson Creek 32 Rose Prairie 2 Fort Nelson 2 Taylor 8 Fort St. John 360 Tumbler Ridge 3 Hudson’s Hope 5 Wonowon 1 Moberly Lake 13 Total 506