Site C Site C Clean Ener Clean Energy Pr y Project oject - - PowerPoint PPT Presentation

site c site c clean ener clean energy pr y project oject
SMART_READER_LITE
LIVE PREVIEW

Site C Site C Clean Ener Clean Energy Pr y Project oject - - PowerPoint PPT Presentation

Site C Site C Clean Ener Clean Energy Pr y Project oject Regional Community Liaison Committee Project Briefing March 11, 2020 Div Diver erting the ting the Peace eace Riv River er Chris Hatton Project Manager, Main Civil Works -


slide-1
SLIDE 1

Regional Community Liaison Committee Project Briefing

March 11, 2020

Site C Site C Clean Ener Clean Energy Pr y Project

  • ject
slide-2
SLIDE 2

Chris Hatton Project Manager, Main Civil Works - Diversion

Div Diver erting the ting the Peace eace Riv River er

slide-3
SLIDE 3
  • What is river diversion?
  • Stages of the river diversion process
  • Cofferdams
  • Diversion Tunnels
  • Debris Management Structures
  • Flow Management
  • Questions/discussion

Pr Pres esen enta tation tion over erview view

March 11, 2020 Regional Community Liaison Committee Meeting 3

slide-4
SLIDE 4
  • River diversion is a construction phase of the Site C project
  • Lasts approximately three years
  • Involves temporarily redirecting the flow of the Peace River to support the

construction of the Site C dam

  • Two major processes make up the act of diversion:
  • 1. Divert river flow (rockfill berm)
  • 2. Seal off river channel (upstream and downstream cofferdams)

Wha hat t is is riv river er div diver ersion sion?

And how do we do it?

4 March 11, 2020 Regional Community Liaison Committee Meeting

slide-5
SLIDE 5

5

slide-6
SLIDE 6

6 March 11, 2020 Regional Community Liaison Committee Meeting

slide-7
SLIDE 7

7

slide-8
SLIDE 8

8

slide-9
SLIDE 9

9

slide-10
SLIDE 10
  • The two large tunnels

approximately 750 metres long and 11 metres in diameter

  • Located on the north bank of the

Peace River

  • Tunnels will have the capacity to

pass 3,000 cubic metres of water per second (combined)

Riv River er div diver ersion sion tu tunn nnels els

10 March 11, 2020 Regional Community Liaison Committee Meeting

slide-11
SLIDE 11
  • Tunnel Stats:
  • Concrete is up to 2m thick at the inlet and reduces to 0.4m thick

at the outlet

  • Extremely smooth “F4” finish on the concrete liner
  • Quality is paramount – through inspections and stringent

repair requirements

  • Tunnels are designed to pass debris up to 10m in length

Tun unne nels: ls: de design sign, , sa safet ety, , an and mon d monitor itoring ing

11 March 11, 2020 Regional Community Liaison Committee Meeting

slide-12
SLIDE 12

12

slide-13
SLIDE 13

13

slide-14
SLIDE 14

14

slide-15
SLIDE 15

15

slide-16
SLIDE 16

16

slide-17
SLIDE 17

17

slide-18
SLIDE 18

18

slide-19
SLIDE 19

19

slide-20
SLIDE 20

20

slide-21
SLIDE 21

21

slide-22
SLIDE 22

22

slide-23
SLIDE 23

23

slide-24
SLIDE 24

24

slide-25
SLIDE 25

25

slide-26
SLIDE 26

26

slide-27
SLIDE 27

27

slide-28
SLIDE 28

28

slide-29
SLIDE 29

29

slide-30
SLIDE 30
  • Design
  • Follows all Canadian Dam Association guidelines for dam safety

design, check, and independent review

  • Design is reviewed and approved by the provincial Dam Safety

Engineer, as well as BC Hydro’s internal Dam Safety Team

  • Monitoring
  • Continuous monitoring of instruments for the entire diversion

process

  • Weekly visual inspections
  • Bi-Annual Dam Safety Engineer inspections

Co Coffer erda dam m sa safet ety, , st stability bility, , an and mo d monit nitor

  • ring

ing

30 March 11, 2020 Regional Community Liaison Committee Meeting

slide-31
SLIDE 31

Site C Site C – Peace Riv eace River er Flo low w Man Management gement

Chris Hatton

March 11, 2020 Regional Community Liaison Committee Meeting

slide-32
SLIDE 32
  • During 2020, the Williston Reservoir is forecast to
  • perate at levels near, or above, those observed

during 2019.

  • BC Hydro will continue to operate Williston Reservoir

to avoid drafting below 2150 ft (655.3 m) under most conditions.

  • BC Hydro will manage its requirements within existing

Peace Water Use Plan (WUP) operation limits.

  • BC Hydro will continue to update and meet with First

Nations, local government, and public regularly to share information and receive feedback.

Wil illi list ston

  • n 20

2020 20 op

  • per

eration tions s for

  • rec

ecas ast

32 March 11, 2020 Regional Community Liaison Committee Meeting

slide-33
SLIDE 33
  • During 2020, Williston Reservoir will fill no higher than

2200 ft (5 ft below full pool), unless filling above this level is necessary to protect the Site C diversion works.

  • During Sept-Oct 2020, Peace River discharges will be

held very low during a critical construction period for the diversion dams.

  • After the diversion dams are completed (Nov. 2020),

Peace River discharges will return to higher (more normal) winter values.

Wil illi liston ston Oper Operations in tions in pr prep ep for

  • r Site C

Site C d div iver ersion sion

33 March 11, 2020 Regional Community Liaison Committee Meeting

slide-34
SLIDE 34
  • By 15 Nov 2020, cofferdams will be high enough to

manage the “full turbine” discharge from GMS/PCN through the winter months (2020-21)

  • By spring 2021, cofferdams will be constructed to their

full design height (433.9 m) able to manage the 200-yr return period local inflow event with GMS/PCN reduced to minimum discharge

  • BCH will continue to operate Williston Reservoir with its

Storage Reservation Curve and 5-ft buffer until 2023-24

Site Site C C co coffer erda dams: ms: 20 2021 21-24 24

34 March 11, 2020 Regional Community Liaison Committee Meeting

slide-35
SLIDE 35
  • Site C local basin (downstream of Peace Canyon) is not

regulated

  • Halfway River is the biggest tributary in this basin.

Moberly River is also a significant tributary.

  • Most severe local inflow events are associated with

rainfall systems that travel NW from the Gulf of Mexico into the Peace River basin … very infrequent, and hard to predict the location & amount of rainfall

  • We should have at least 3 days notice of high flows

(and high forebay levels) at Site C.

Site Site C C loc local al ba basin sin

35 March 11, 2020 Regional Community Liaison Committee Meeting

slide-36
SLIDE 36

36

Con Constr structio uction n upda update te

On Dam Site Construction Update

slide-37
SLIDE 37

37

Con Constr structio uction n upda update te

On Dam Site Construction Update

  • 2020 Spring/Summer Schedule
  • Left Bank
  • Worker accommodation lodge expansion
  • 85th Avenue Industrial Lands & till conveyor
  • Diversion tunnels, portal structures, fish passage
  • Cofferdams
  • Core trench & earthfill dam
  • Right Bank
  • Powerhouse concrete placement
  • Powerhouse structural steel placement
  • Penstock installation
  • Dam Buttress RCC placement (planned for 2020)
  • Rip Rap Stockpiling (at Septimus)
slide-38
SLIDE 38

38

Con Constr structio uction n upda update te

On Dam Site Summary Schedule: 2020

Construction Activity Anticipated Schedule Diversion Tunnels ready for diversion Q3 2018 to Q3 2020 Assemble Till Conveyor Q4 2018 to Q3 2019 Left Bank Dam Grout & Fill Q3 2019 to Q4 2021 Crusher & Aggregate Production Q1 2017 to Q3 2023 Spillway RCC Q2 2019 to Q4 2019 Powerhouse Concrete Q3 2018 to Q4 2022 Penstock Q2 2019 to Q3 2022 Infrastructure Upgrades Ongoing *All major construction activities *To be completed by Q4 2024

slide-39
SLIDE 39

Le Left Ba ft Bank nk

39

slide-40
SLIDE 40

40

ATCO Two Rivers Lodge Phase 2 Expansion

slide-41
SLIDE 41

Till Till co convey eyor

  • r sy

syst stem em

41

slide-42
SLIDE 42

42

Left Bank Conveyor feeds the Hopper to Stockpile Aggregate

slide-43
SLIDE 43

43

Left Bank: Diversion Tunnels and Portals

slide-44
SLIDE 44

Le Left Ban ft Bank k – Inlet Inlet Por

  • rta

tals ls

44

slide-45
SLIDE 45

45

Left Bank – Diversion Tunnel Outlet Portals & Temporary Fishway

slide-46
SLIDE 46

Tem empo porar ary y Ups Upstr trea eam m Fish Fishway ay (TUF) (TUF)

14 14

Project Stats CIPC:

  • Previous update 88%
  • CIPC 89% completed
  • Entrance – 100%
  • Fish lock – 100%
  • Fish ladder – 81%
  • Pump station – 100%

Mechanical:

  • Mechanical tasks continue
slide-47
SLIDE 47

47

slide-48
SLIDE 48

48

Powerhouse, intakes and Service Bay

slide-49
SLIDE 49

Powerh erhou

  • use

se – Str Struc uctur tural Stee al Steel l Er Erec ection tion

49

slide-50
SLIDE 50

Power erho hous use e – Str Struc uctu tural al Pou

  • ur

50

slide-51
SLIDE 51

51

Right Bank: Spillway

RCC Placement Complete – winter cladding in place

slide-52
SLIDE 52

Pen enst stoc

  • ck

k As Asse semb mbly

52

slide-53
SLIDE 53

53

Constr Constructio uction n upda update te

Pen ensto stock f k for

  • r Unit

Units s 1, 2 and 1, 2 and 3 3

slide-54
SLIDE 54

54

Dry Creek

Off Dam Site Construction Update

Of Off D Dam am Site Site Co Cons nstr truc uctio tion n Up Upda date te

Farrell Creek

54

slide-55
SLIDE 55

55

Con Constr structio uction n upda update te

Of Off D Dam am Site Site Con Const struc uction tion Upd Update te

  • Transmission Work
  • Highway 29 realignment
  • Hudson’s Hope Shoreline Protection
  • Reservoir clearing work
slide-56
SLIDE 56

56

Tran ansmission smission Wor

  • rk: Site

k: Site C Sub C Subst station tion

slide-57
SLIDE 57

Sou South th Ban Bank k Sub Sub-Sta Station tion

57

Control Building – Cable Stripping P&C relay testing & NERC hardening

slide-58
SLIDE 58

58

Trans ansmis missi sion

  • n wor
  • rk:

k: Trans ansmis missi sion

  • n lines

lines

slide-59
SLIDE 59

Highw Highway ay 29 29 r rea eali lign gnmen ment t loca location tions

59

slide-60
SLIDE 60

60

Highway 29 Construction Timeline

slide-61
SLIDE 61

61

Halfway River site preparation

September 21, 2019

Highway 29 realignment – Cache Creek East

slide-62
SLIDE 62

62

Hi High ghway ay 29 29 Rea eali lign gnmen ment t - Cac Cache he Cr Cree eek W k West est

slide-63
SLIDE 63

Hi High ghway ay 29 29 Rea eali lign gnmen ment t – Half Halfway ay Ri River er

63 63

slide-64
SLIDE 64

Por

  • rta

tage ge Mou Mount ntain ain Qu Quar arry

64

slide-65
SLIDE 65

Hudson’s Hope shoreline protection

65

slide-66
SLIDE 66

Rese eservoir

  • ir clear

learing w ing wor

  • rk

66

Cur Current ent clearing w learing wor

  • rk:

k:

  • Sou

South Ban Bank, , East Eastern Reser servoir ir

  • Peace Islan

Islands, s, Mid iddle le Reser servoir ir

  • Ca

Cache Cr Creek t to Peace Islan Islands, s, Mid iddle le Reser eservoir

  • ir

Reservoir Clearing

South Bank, Eastern Reservoir

Green pile burning Debris Management

slide-67
SLIDE 67

67

Reservoir clearing: Work plan for winter 2020

Peace Islands Phase 1&2 Cache Creek to Peace Islands South Bank Eastern Reservoir Moberly waste wood disposal

slide-68
SLIDE 68

EA EAC Amendments and C Amendments and Pr Prog

  • gram

am Upda Updates tes

Nancy Pepper Community and Social Mitigation Manager

slide-69
SLIDE 69

Mitiga Mitigation tion Upda Update te

slide-70
SLIDE 70

Pea eace ce Riv River er bo boate ter r co commu mmunic nicatio tion n up upda date tes s – Travelli elling ng Do Downs wnstr trea eam

70

slide-71
SLIDE 71

Pea eace ce Riv River er bo boate ter r co commu mmunic nicatio tion n up upda date tes s – Travelli elling ng Ups Upstr trea eam

71

slide-72
SLIDE 72

72

BC BC Hy Hydr dro

  • Pea

eace ce Ag Agricultur ricultural al Comp Compen ensa sation tion Fund Fund

2nd Funding Intake Update

slide-73
SLIDE 73

73

BC BC Hy Hydr dro

  • GO F

GO Fun und

14th Funding Intake Update North Peace Gymnastics Association

  • Special Abilities Program (June 2019)
slide-74
SLIDE 74

Dave Hunter Senior Environmental Coordinator

Peace eace Riv River er Methylmer Methylmercur cury y Upda Update te

slide-75
SLIDE 75
  • Mercury 101
  • Site C Requirements: Methylmercury Monitoring Program
  • Work with health agencies and Indigenous groups to

monitor and communicate results

Pr Pres esen enta tation tion over erview view

75

slide-76
SLIDE 76

Mer Mercu cury y in in Fish Fish

76

Traditional foods at a WMFN camp

slide-77
SLIDE 77

0.0 0.1 0.2 0.3 0.4 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40

Year After Impoundment Mercury (mg/kg ww)

Baseline Rise after flooding Gradual decrease Peak New baseline

Years after impoundment

Hypothetical trajectory: fish mercury levels in a new reservoir (the “reservoir effect’)

77

slide-78
SLIDE 78

Comp Compar arison ison of

  • f Me

Meth thylmer ylmercu cury y Le Levels els in in Fish Fish

78

Data for retail fish (sold in restaurants and grocery stores) are from Health Canada (2007) and Lowenstein et. Al. (2010) Note: * Refer to Health Canada consumption guidance for retail canned albcore tuna and fresh bigeye tuna.

slide-79
SLIDE 79

Site Site C C - Req equir uireme ement nts

79

slide-80
SLIDE 80

Wha hat t Inf Infor

  • rma

matio tion n Will ill Be Be Collect Collected ed?

MMP

Monitoring Program Fish Tissue Samples Indigenous Community Program Fish Tissue Samples Fish Consumption Information

80

slide-81
SLIDE 81

MMP Imp MMP Impleme lement ntatio tion- Ex Existin isting g Fish Fish Pr Prog

  • gram

ams

81

slide-82
SLIDE 82

MMP Monitoring Locations

0 5 45 120 280 Kilometers Downstream from Site C Dam

Monitoring Program Included within Indigenous Community Program

82

slide-83
SLIDE 83

MMP Imp MMP Impleme lement ntatio tion n – Ind Indige igeno nous us Gr Grou

  • up

p an and d Hea Health lth Aut utho hority rity In Involv

  • lveme

ement nt

83

slide-84
SLIDE 84
  • “Reservoir Effect” – temporary increase in mercury levels
  • Work with health agencies and Indigenous groups to

monitor and communicate results

Summa Summary

84

slide-85
SLIDE 85

85

Con Constr structio uction n upda update te

Jobs and business opportunities

slide-86
SLIDE 86

Emplo Employme yment nt st statist tistics ics

  • Site C jobs posted to WorkBC / Employment Connections (Fort St. John) website; all

contractors listed on Site C website.

  • BC Hydro requires all major contractors to report employment information.
  • Total of 4,359 workers in January 2020; 3,198 from B.C (73%). Total of 676 workers

from PRRD (19%).

86

Site C Employment Statistics – January 2020 # of Total Workers # of BC Primary Residents % of BC Workers Construction and Environmental Contractors

3,613 2,511 69%

Engineers and Project Team

746 687 92%

Total Workforce

4,359 3,198 73%

slide-87
SLIDE 87

Site C Site C job jobs sna s snapsh pshot (J

  • t (Jan

anua uary 20 y 2020 20)

87

slide-88
SLIDE 88

20 2019 19 Q4 Q4 Region gional al Bus Busines iness s Par articipa ticipation tion

Companies engaged by BC Hydro and Site C contractors to provide goods & services in relation to Site C construction between October – December 2019

88

Community Number of Businesses Community Number of Businesses Cecil Lake 1 Pouce Coupe 2 Charlie Lake 19 Prince George 30 Chetwynd 27 Rolla 1 Dawson Creek 32 Rose Prairie 2 Fort Nelson 2 Taylor 8 Fort St. John 360 Tumbler Ridge 3 Hudson’s Hope 5 Wonowon 1 Moberly Lake 13 Total 506

slide-89
SLIDE 89