SIDC (XBID) Update 18 th MESC Meeting ENTSO-E, Brussels 17.09.2019 - - PowerPoint PPT Presentation
SIDC (XBID) Update 18 th MESC Meeting ENTSO-E, Brussels 17.09.2019 - - PowerPoint PPT Presentation
SIDC (XBID) Update 18 th MESC Meeting ENTSO-E, Brussels 17.09.2019 SIDC Headlines on Progress 2 nd Wave Go-Live on target for November but risk Deployment of Release 2.0 on target for end October remains User The Acceptance
2nd Wave Go-Live on target for November but risk remains Future Development progresses
SIDC – Headlines on Progress
2 Deployment of Release 2.0 on target for end October Roadmap
XBID successfully transitioned to SIDC
- User
Acceptance Testing, UAT, has been successful and delivered to plan. Final phase is now underway (Performance Testing)
- Release 2.0 delivers increased Order Book
Depth of 100 (up from 31)
- Also delivers Enhanced Shipper for 2nd Wave
Go-Live
- The Proof of Concept for Losses on DC Cables
is underway (expected to complete in November)
- Pilot of Agile Development agreed with DBAG
and approach is being discussed
- Scope of Release 3.0 ongoing – list to be
aligned with 2020 Budget - discussions ongoing.
- The
final phase
- f
Local Implementation Project testing is underway
- Pre-launch Event is scheduled for 1st October.
Invitations issued/participants are registered
- Risks on 2nd Wave include Transit Shipping
(see separate slides), MPLS connections and technical readiness
- Roadmap developed with circa 130 items
covering geographic extension, usability and functional development
- Research
& Development workshop with NRAs scheduled for 26th September
- Early discussions on Intraday Auctions and
governance
SIDC key figures – performance monitoring – example
3
10,000 20,000 30,000 40,000 50,000 60,000 70,000 80,000 90,000 100,000 100,000 200,000 300,000 400,000 500,000 600,000 700,000 800,000 900,000 1,000,000 2018-06-12 2018-06-18 2018-06-24 2018-07-01 2018-07-07 2018-07-13 2018-07-19 2018-07-25 2018-07-31 2018-08-06 2018-08-12 2018-08-18 2018-08-24 2018-08-30 2018-09-05 2018-09-11 2018-09-17 2018-09-23 2018-09-29 2018-10-05 2018-10-11 2018-10-17 2018-10-23 2018-10-29 2018-11-04 2018-11-10 2018-11-16 2018-11-22 2018-11-28 2018-12-04 2018-12-10 2018-12-16 2018-12-22 2018-12-28 2019-01-03 2019-01-09 2019-01-15 2019-01-21 2019-01-27 2019-02-02 2019-02-08 2019-02-14 2019-02-20 2019-02-26 2019-03-04 2019-03-10 2019-03-16 2019-03-22 2019-03-28 2019-04-03 2019-04-09 2019-04-15 2019-04-21 2019-04-27 2019-05-03 2019-05-09 2019-05-15 2019-05-21 2019-05-27 2019-06-02 2019-06-08 2019-06-14 2019-06-20 2019-06-26
Trades
Order Transactions / Trades
Realistic Test Scenario 3A<=400k Realistic Test Scenario <=50k
The figure shows daily Orders Transactions (Order events) and Trades since the first complete day of trading (13 June 2018). The maximum order transactions peak (~862k) was produced on 26 June 2019. The trades also reached a peak in that month (~85k on 7 June). Over 20 million trades have been completed since the 1st go-live
Note: Realistic Test Scenarios have been run and SLAs agreed to ensure effective contractual frameworks as the Intraday Market grows Orders Transactions
2nd Wave Go-Live – “Transit” Shipping (1/2)
4
- The 2nd Wave Go-Live is scheduled for November 2019 with 7 countries – Bulgaria, Croatia,
Czech Republic, Hungary, Poland, Romania & Slovenia (subject to successful testing) in two Local Implementation Projects (LIPs). See Appendix for parties involved.
- In comparison to the 1st Wave, the 2nd Wave shipping arrangements introduce a more complex
topology for SIDC which could not be fully considered when the Shipping Module was initially developed for the 1st Wave Go-Live.
- In order to deal with this 2nd wave complexity - a role of the preferred shipper has been
- established. This means that in the MNAs (Multi NEMO Arrangements) areas, “preferred” shipping
agent from amongst the two NEMO/CCP/Shipping agents currently active* in these MNA areas needs to be appointed by each NEMO/CCP.
- The preferred shipper role deals with “transit shipping activities“ (shipping of the energy through
delivery areas where the trade has neither source nor sink). Transit in non-MNA areas does not need any selection as the non-MNA NEMO/CCP active in each area assures this activity (or nominates another entity to provide it, e.g. shipping agents) to all other NEMOs/CCPs.
- The arrangements and agreement regarding “Transit” Shipping through MNA areas is key for the
success of the 2nd Wave
*At the current time EPEX SPOT/ECC and EMCO/NordPool could be active NEMOs in all MNA areas and TGE is only active in the Polish MNA area. EXAA is not operational in XBID.
2nd Wave Go-Live – “Transit” Shipping (2/2)
5
- A selection process for the provision of “Transit” Shipping in MNA areas has been jointly prepared (to
ensure consistency) by the non-MNA NEMOs
- The corresponding Request for Offer (RfO) was sent to EMCO and EPEX/ECC on 14th August, together
with the defined Terms.
- Responses were received by 11th September and the final selection decision is due to be made on 18th
- September. This will be followed by final negotiations, a Lock-In if needed, NRA approvals (where
needed) and incorporation in bilateral agreements.
- The timeline is challenging in order to secure the 2nd wave go-live scheduled for 19th November 2019.
- If timely agreement is not reached through this process, then a Transit Shipper will be appointed for an
interim period of up to 6 months. The above RfO included the request for the potential providers to detail the costs for 3 and 6 months under direct assignment of the Transit Shipper role. This is designed to mitigate the risk on the 2nd wave go-live if the above selection process does not deliver in time.
- TGE, the Polish NEMO, is separately running a selection process for the selection of their Preferred
Shipper and also requested a response from EMCO and ECC by 11th September.
- Transit Shipping is being monitored very closely by the Transit Shipping Group and the SIDC Intraday
Steering Committee.
- Other risks to the 2nd wave go-live include the Nomination system in Poland, some NEMOs’ connection
to the MPLS (communication channel) for back office activities, and completion of testing.
15 16
LIP Participants Foreseen allocation AT-CZ, AT-SI, AT-HU, BG- RO, CZ-DE, CZ-PL, DE-PL, HR-SI, HR-HU, HU-RO NEMOs: BSP, Cropex, EPEX, HUPX, IBEX, Nord Pool, OPCOM, OTE TSOs: 50Hertz, APG, CEPS, ELES, ESO, HOPS, MAVIR, PSE, Transelectrica, TTG
- Implicit
- Implicit &