SH 358 IMPROVEMENTS Corpus Christi District Updated October 2018 - PowerPoint PPT Presentation

SH 358 IMPROVEMENTS Corpus Christi District Updated October 2018 SH 358 Improvements Corpus Christi District All dates & schedules are subject to change Updated October 2018 Project Overview Length: 15 miles Total cost: $49.96


  1. SH 358 IMPROVEMENTS Corpus Christi District Updated October 2018 SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018

  2. Project Overview  Length: 15 miles  Total cost: $49.96 million  Mainlane improvements from north of Leopard Street to east of Flour Bluff Drive: – Install new lighting – Install Intelligent Transportation Systems (ITS), including traffic cameras  Eastbound mainlane and frontage road improvements from Ayers Street to Nile Drive: – Reconstruct center median barrier – Widen freeway to improve capacity and mobility – Reverse ramps – Improve signal timing SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 2

  3. Project Phases and Timeline The project is being constructed in 10 phases*: Phase 1 January 2018 – June 2018 Phase 2 March 2018 – Spring 2019 Phase 3 Fall 2018 – Summer 2019 Phase 4 Spring 2019 – Summer 2020 Phase 5 Summer 2020 * This schedule is subject to change. Phase 6 Summer 2020 – Spring 2021 ITS and eastbound frontage road signal improvements Phases 7-10 Spring 2021 – Fall 2021 from north of Leopard Street to east of Flour Bluff Drive will be made throughout project duration. SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 3

  4. Construction Sequencing – Phase 1 Overview  Construct new temporary mainlane center median barrier from Ayers Street to Airline Road  Widen eastbound frontage road and construct sidewalks between Ayers Street and Kostoryz Road Crews begin work to reconstruct the mainlane center median barrier. TxDOT Photo SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 4

  5. Phase 1 – Mainlanes Between Ayers Street and Airline Road  Remove existing center median barrier Off-peak lane closures are required as the existing center median barrier is replaced  Reconstruct inside shoulders and add with a temporary barrier and the inside temporary center median barrier shoulders are reconstructed.  Purpose: – Accommodate future eastbound mainlane traffic shifts and permanent center median barrier  Closures required: – Various off-peak eastbound and westbound mainlane closures SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 5

  6. Phase 1 – Eastbound Frontage Road near Richter Street  Widen eastbound frontage road near future Kostoryz Road/Carroll Lane off-ramp: – Add new sidewalks and curbs/gutters – Add 3rd eastbound lane on frontage road east of Richter Street  Purpose: – Accommodate future relocated off-ramp  Required closures: – Off-peak closures of outside eastbound frontage road lane – Temporary closures of Richter Street SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 6

  7. Construction Sequencing – Phase 2 Overview  Construct new eastbound off-ramp and remove existing off-ramp serving Kostoryz Road and Carroll Lane Relocated EB off-  Widen eastbound frontage road and ramp to Kostoryz Rd/ Carroll Ln construct sidewalks in segments: – Between Kostoryz Road and Weber Road – Between Weber Road and Everhart Road – Between Everhart Road and South Staples Street – Near Airline Road SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 7

  8. Phase 2 – Eastbound Off-Ramp to Kostoryz Road/Carroll Lane  Relocate eastbound off-ramp serving Kostoryz Road and Carroll Lane: – Build new off-ramp near Richter Street, west of existing off-ramp – Improve drainage along frontage road Existing Kostoryz Rd/ New Kostoryz Rd/ Carroll Ln off-ramp – Permanently close existing off-ramp Carroll Ln off-ramp to be built  Purpose: farther west – Improve safety and mobility for eastbound mainlane and frontage road drivers approaching the Kostoryz Road intersection.  Anticipated closures: – Off-peak closures of inside eastbound frontage road lane SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 8

  9. Phase 2 – Eastbound Frontage Road Between Kostoryz Road and Weber Road  Widen eastbound frontage road near existing ramps adjacent to Cosner Drive and Wilkinson Drive: – Add new sidewalks and curbs/gutters – Add 3rd eastbound lane on frontage road east of Wilkinson Drive  Purpose: Accommodate future ramp reversal and widened eastbound mainlanes  Anticipated closures: – Off-peak closures of outside eastbound frontage road lane – Potential temporary closures: • Cosner Drive and Wilkinson Drive • Driveways (e.g. Bethel, Sames) Existing ramps near Cosner Dr • Additional closures across eastbound frontage road and Wilkinson Dr near Wilkinson Drive for drainage pipe installation SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 9

  10. Phase 2 – Eastbound Frontage Road Between Weber Road and Everhart Road  Widen eastbound frontage road near existing ramps adjacent to Oakhurst Drive and Embassy Drive: – Add new sidewalks and curbs/gutters – Extend 3rd eastbound lane on frontage road to/from freeway ramps  Purpose: Accommodate future ramp reversal and widened eastbound mainlanes  Anticipated closures: – Off-peak closures of outside eastbound frontage road lane – Potential temporary closures: • Oakhurst Drive and Embassy Drive • Most driveways (e.g. La Playa, Cesar Chavez, Academy) Existing ramps • Some closures across eastbound frontage road near both Oakhurst Drive and Embassy Drive for drainage pipe near Oakhurst Dr installation and Embassy Dr – Permanent closure of one redundant driveway east of Embassy Drive SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 10

  11. Phase 2 – Eastbound Frontage Road Between Everhart and South Staples  Widen eastbound frontage road near existing ramps adjacent to the Academy store and Moore Plaza shopping center: – Add new sidewalks and curbs/gutters – Extend 3rd eastbound lane on frontage road to/from freeway ramps  Purpose: Accommodate future ramp reversal and widened eastbound mainlanes  Anticipated Closures: – Off-peak closures of outside eastbound frontage Existing ramps road lane as needed near the Academy store and Moore – Potential temporary closures: Plaza shopping • Blanche Moore Drive center • Driveways (e.g. On the Border, Romano’s) • Some closures across eastbound frontage road near both Blanche Moore Drive and the Academy store for drainage pipe installation SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 11

  12. Phase 2 – Eastbound Frontage Road near Airline Road  Widen and improve eastbound frontage road near existing Airline Road on-ramp: – Add new sidewalks and curbs/gutters – Add new inlets and pipe to improve drainage at Airline Road intersection  Purpose: Increase eastbound frontage road capacity and improve safety near Airline Road  Anticipated closures: – Off-peak closure of outside eastbound frontage road lane as needed – Potential temporary closures: • Across eastbound frontage road near Golden Corral restaurant for drainage pipe installation • Across all lanes of eastbound frontage road and Airline Road intersection SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 12

  13. Construction Sequencing – Phase 3 Overview  Widen eastbound mainlane bridges to four lanes at Kostoryz Road and Carroll Lane  Widen eastbound mainlanes and reconstruct median between the eastbound mainlanes and frontage road from Everhart Road to South Staples Street  Widen eastbound frontage road and construct sidewalks between South Staples Street and Airline Road SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 13

  14. Phase 3 – Eastbound Mainlane Bridge at Kostoryz Road  Widen eastbound mainlane bridge at An additional lane will be built Kostoryz Road on the eastbound mainlane bridges at Kostoryz, Carroll,  Purpose: Accommodate four mainlanes Weber, Everhart, and Staples.  Anticipated closures and detours: – Off-peak closures of Kostoryz Road intersection – Potential temporary closure of westbound-to- eastbound turnaround under bridge – Potential temporary detours of Kostoryz Road/frontage road traffic to adjacent intersections and turnarounds SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 14

  15. Phase 3 – Eastbound Mainlane Bridge at Carroll Lane  Widen eastbound mainlane bridge at Carroll Lane  Purpose: Accommodate four mainlanes and prepare for Weber Road off-ramp relocation  Anticipated closures and detours: – Potential off-peak closure of Carroll Lane intersection – Potential temporary closure of westbound-to- eastbound turnaround under bridge – Potential temporary detours of Carroll Lane/ frontage road traffic to adjacent intersections and turnarounds SH 358 Improvements – Corpus Christi District All dates & schedules are subject to change Updated October 2018 15

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.