SEQ Stabling Program Woombye CRG March 2016 Project update - - - PowerPoint PPT Presentation

seq stabling program woombye crg march 2016 project
SMART_READER_LITE
LIVE PREVIEW

SEQ Stabling Program Woombye CRG March 2016 Project update - - - PowerPoint PPT Presentation

SEQ Stabling Program Woombye CRG March 2016 Project update - February 2016 Ecological studies to identify if any tusked frog and/or platypus were present No tusked frogs or platypuses were located within the project boundary


slide-1
SLIDE 1

SEQ Stabling Program Woombye CRG – March 2016

slide-2
SLIDE 2

Project update - February 2016

  • Ecological studies to identify if any tusked frog

and/or platypus were present

  • No tusked frogs or platypuses were located

within the project boundary

  • Vegetation removal along the North Coast rail

line during Queensland Rail’s scheduled track closure (6 and 7 February 2016)

slide-3
SLIDE 3
  • A fauna spotter was onsite during the clearing
  • Relocation of a blue-tongue lizard and green

tree snake

  • Mulching works
  • Install erosion and sediment controls
  • Use of machinery such as excavators,

mulching unit, front-end loaders and elevated working platform

slide-4
SLIDE 4

Vegetation removal works

slide-5
SLIDE 5
slide-6
SLIDE 6
slide-7
SLIDE 7
slide-8
SLIDE 8
slide-9
SLIDE 9

Project update – February 2016

  • Replacement of the site compound generator

with a quieter unit

  • Removal of top soil
  • Bulk earthworks including:

Grading and leveling the construction area Transporting material using haulage trucks.

slide-10
SLIDE 10

New generator and environmental control

slide-11
SLIDE 11

Removal of topsoil and bulk earthworks

slide-12
SLIDE 12
slide-13
SLIDE 13
slide-14
SLIDE 14
slide-15
SLIDE 15
slide-16
SLIDE 16
slide-17
SLIDE 17

Project update – February 2016

  • Use of machinery such as excavators, a

padfoot roller, grader, scrapers and haulage trucks.

slide-18
SLIDE 18

Padfoot roller

slide-19
SLIDE 19

Project update - March 2016 Upcoming construction works includes:

  • Ongoing earthworks to grade and level the

construction area

  • Installing drainage.