SEQ Stabling Program Woombye CRG May 2016 Project update May 2016 Construction activities underway: Drainage (Culvert) Earthworks Installation of electrical conduits Concrete foundations for overhead line equipment (OHLE)


slide-1
SLIDE 1

SEQ Stabling Program Woombye CRG – May 2016

slide-2
SLIDE 2

Project update – May 2016 Construction activities underway:

  • Drainage (Culvert)
  • Earthworks
  • Installation of electrical conduits
  • Concrete foundations for overhead line

equipment (OHLE)

  • Works pad for turn-out install
  • Removal of decommissioned power pole
slide-3
SLIDE 3

Culvert works

slide-4
SLIDE 4

Culvert works – install 4 x 2100 pipes

slide-5
SLIDE 5

Culvert works – install 4 x 2100 pipes

slide-6
SLIDE 6

Culvert backfill

slide-7
SLIDE 7

Drilling for OHLE foundations

slide-8
SLIDE 8

Formwork for OHLE foundation

slide-9
SLIDE 9

OHLE foundations

slide-10
SLIDE 10

UTX conduit install

slide-11
SLIDE 11

Decommissioned power pole removal

slide-12
SLIDE 12

Earthworks

slide-13
SLIDE 13

Earthworks

slide-14
SLIDE 14

Project update – May 2016

Upcoming construction works:

  • Install water and sewerage services
  • Bulk earthworks continuing
  • During QR’s pre-scheduled track closure over

4-5 June, CPB will undertake works to:

  • Install the new turn-out for the facility
  • OHLE works – including standing masts
  • Signal works
slide-15
SLIDE 15

Project update – May 2016

Upcoming construction works:

  • Security fence - footings and install
  • Capping - import and placement
  • Access road and car park
  • Track install