SEQ Stabling Program Woombye CRG July 2016 Project update July 2016 Construction activities underway: Drainage and culverts Earthworks Capping placement Security fence footings Installing of electrical conduits


slide-1
SLIDE 1

SEQ Stabling Program Woombye CRG – July 2016

slide-2
SLIDE 2

Project update – July 2016 Construction activities underway:

  • Drainage and culverts
  • Earthworks
  • Capping placement
  • Security fence footings
  • Installing of electrical conduits
  • Concrete foundations for overhead line

equipment (OHLE) and signals

slide-3
SLIDE 3

Culvert outfall - west

slide-4
SLIDE 4

Culvert backfill

slide-5
SLIDE 5

OHLE foundations

slide-6
SLIDE 6

OHLE footing concrete pour

slide-7
SLIDE 7

Security fence footing formwork

slide-8
SLIDE 8

Security fence footing formwork

slide-9
SLIDE 9

Site overview looking north

slide-10
SLIDE 10

Security fence panels

slide-11
SLIDE 11

Earthworks

slide-12
SLIDE 12

Earthworks

slide-13
SLIDE 13

Earthworks

slide-14
SLIDE 14

Earthworks

slide-15
SLIDE 15

Turnout rail construction

slide-16
SLIDE 16

Turnout rail construction

slide-17
SLIDE 17

Project update – July 2016

Upcoming construction activities:

  • Security fence – footings, posts and panels
  • Capping import and placement
  • Access road and car park works
  • Inground services including hydraulics
  • Track install – rescheduled due to weather