SEPTA Public Open House FY 2018 Capital Budget Development January - - PowerPoint PPT Presentation
SEPTA Public Open House FY 2018 Capital Budget Development January - - PowerPoint PPT Presentation
SEPTA Public Open House FY 2018 Capital Budget Development January 24, 2017 SEPTA Public Open House FY 2018 Capital Budget Development January 24, 2017 FY 2017 Capital Budget and 12 Year Capital Program Funding Outlook Rebuilding
FY 2018 Capital Budget Development January 24, 2017
- FY 2017 Capital Budget and 12‐Year Capital Program
- Funding Outlook
- “Rebuilding the System” Capital Program
- Schedule of Key Activities
SEPTA Public Open House
FY 2017 Capital Budget
FY 2017 Capital Budget and FY 2017‐2028 Capital Program
Funding Outlook State Funding for SEPTA ($M)
Funding Outlook Federal Formula Funding for SEPTA ($M)
http://www.septa.org/rebuilding/
- Construction contracts awarded since January 2014: 97
- Open contracts: 70 (Amount totals $430.1 M)
- Closed contracts: 27 (Amount totals $43.2 M)
Fern Rock Carhouse/Washer Roof Chestnut Hill West Bridge 0.35
- Rt. 102 Woodlawn Avenue Track
Rebuilding the System
Doylestown Substation Media Cut (Resilience Program) Morton Substation Lenni Substation RRD Stone Arch Bridges (9) Crum Creek Viaduct
Recent Accomplishments
Recent Accomplishments
- Rt. 102 Grade Crossings
35th & Allegheny Bus Loop Allegheny Garage Fire Suppression Midvale Bus Washer Woodland Shop Roof 69th Street Retaining Wall
- Rebuilding the System
Capital Projects
- SEPTA Key
- Vehicle Acquisitions
- Financial Obligations
- Debt Service
- Leases / PRIIA
FY 2018 Capital Budget Development
Bridge Program
Norristown High Speed Line Bridge 0.15 Media‐Elwyn Line (3) Viaducts – Cobbs Creek, Ridley Creek, Darby Creek (Nearing Completion) Stone Arch Bridges – Phase II Woodland Avenue Bridge
Communications & Signals
- Rt. 101/102 Positive Train Control
Radio Interoperability
Real‐Time Information and Audio Visual Public Address (AVPA)
30th to Arsenal Catenary, Signals & ROW
Maintenance Facility Improvements
103 Victory Avenue Facility Improvements Frazer Rail Shop and Yard Upgrade Southern Garage Stormwater Management and Paving Frontier Garage Roof, Washer and Paving
The Future of Fare Payment
Service Restorations Elwyn to Wawa Rail Service
Wawa Station Rendering Rehabilitate/Replace Bridges Right of Way/Track Work Restoration of Regional Rail service from Elwyn to Wawa
Stations, Loops and Parking Parking Program
Lansdale Area Improvements 69th Street Transportation Center Parking Garage Gwynedd Valley Station Conshohocken Station & Parking
Stations / Accessibility – Regional Rail
Levittown
In Construction
Yardley
In Construction
Secane
In Construction
Lawndale Paoli
In Construction
Villanova
In Construction
Exton
In Construction
Ardmore
Stations / Accessibility ‐ Transit
Arrott Transportation Center (In Construction) 5th Street / Independence Hall Station 40th Street Station (In Construction) Susquehanna‐ Dauphin Tasker‐Morris Wissahickon Transportation Center
City Hall / 15th Street Station
City Hall Station 15th Street Station
Center City Concourses
Phase 1 Conceptual Rendering Construction In Progress (L‐R): Oculus, Corridor 6, Macy’s Lobby Concourse Map
Phase 2 (In Design) Phase 4 (In Design) Elevator Escalator Escalators Phase 1 (In Construction)
15th St Escalators
Substation & Power Program
Jenkintown Substation
Multimodal Substation Design and Equipment Purchase (Photo: Bethayres)
Wayne Junction Static Frequency Converters (SFC) #1‐4 Ambler Substation
Track and Right‐of‐Way Program
Norristown High Speed Line (NHSL) Tie Replacement & Continuous Welded Rail Trolley Tunnel Track Improvements
New Buses
25 40‐Ft. Electric Buses Contract awarded pending; delivery in 2017‐2018 Manufacturer: Proterra 525 40‐Ft. Hybrid Buses Contract awarded 2016; delivery in 2017‐2021 Manufacturer: New Flyer 35 New Flyer 30‐Foot Buses Contract awarded 2015; delivery in 2016‐2017 Manufacturer: New Flyer 232 Paratransit Vehicles Contract awarded 2015; delivery in 2015‐2017 Manufacturer: Shephard Bros. Inc.
New Rail Vehicles ‐ Current
15 Electric Locomotives Contract awarded 2015 Delivery in 2018 Manufacturer: Siemens 45 Multi‐Level Rail Cars Contract award expected 2017 Delivery in 2020‐2021
Low Floor Trolleys Delivery schedule TBD Ongoing Preliminary Efforts:
- Track Clearances Study
- Bridge Capacity Analysis
- Traction Power Capacity Analysis
- Streetscape Definition w/DVRPC
New Rail Vehicles ‐ Future
Electric‐Multiple Unit Railroad Passenger Cars To replace Silverliner IV fleet Delivery schedule TBD
Image: A.W. Beldan (via Transit Toronto Collection, 2015)
Meetings with Stakeholders
- Dec. 2016 – Jan. 2017
Open House on Budget and Program
- Jan. 24, 2017
Develop Budget Proposal
- Jan. – March 2017
Presentations to Stakeholders March 2017 Public Hearing Notice Published March 2017 Posting of Proposed Capital Budget & Program March 2017 Public Hearings on Capital Budget & Program April 26, 2017 Board Approval of Capital Budget & Program May 25, 2017
FY 2018 Capital Budget Development Schedule of Key Activities