West Virginia Ave Public Works Campus 2 nd Public Open House October - PowerPoint PPT Presentation

West Virginia Ave Public Works Campus 2 nd Public Open House October 15, 2015 West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House Open House Agenda Welcome + Introduction Opening Remarks OP Director Eric


  1. West Virginia Ave Public Works Campus 2 nd Public Open House October 15, 2015 West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  2. Open House Agenda • Welcome + Introduction • Opening Remarks – OP Director Eric Shaw • Project Presentation – Tracy Gabriel, DC Office of Planning – Andrea Limauro, DC Office of Planning – Steve Campbell, Department of General Services • Gallery Walk – Ward 5 Works Study Findings – DPW: Existing Conditions and Needs – The Future Campus West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  3. Campus Plan Scope & Schedule Phase 1 : Existing Conditions Analysis Phase 2 : DPW Assessment (Spaces and Operations) Phase 3 : Development of Design Options Phase 4 : Master Plan Final Report Final Report Schedule 2 1 3 4 Nov. Feb. June We Are Here West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  4. 1 Opening Remarks West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  5. 2 Project Background West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  6. Project Background – Ward 5 Works West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  7. Project Background – Ward 5 Industrial Land DPW Campus Site West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  8. Project Purpose Two overarching aspirations for the campus emerged from Ward 5 Works • Improve and optimize the public works operations to be more healthy, sustainable, and effective • Transform public facilities to be anchors for community development and create amenities for nearby residents West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  9. Community and Stakeholder Input • June: 1 st Open House • July: Office Hours • September: Focus Group • October: 2 nd Open House West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  10. 3 Existing Conditions and Needs Analysis West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  11. Neighborhood Context Map Hecht Crummell Land Use DPW Campus West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  12. Neighborhood Context West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  13. South Context West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  14. North Context West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  15. W Virginia Avenue Environmental Context • Buildings – Fair Condition but outdated • Streets – No real transportation or storm water infrastructure on the interior of the campus • Sub-surface Issues – Underground storage tanks – Closed Mt. Olivet Incinerator – Requires more investigation West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  16. Map of Existing Uses West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  17. DPW Functions • Which functions do we expect to move to campus? – All DPW Administrative Offices – Solid Waste Administration & Operations • Additional DPW Staff • Additional Vehicle Parking Storage – Expanded Vehicle Wash Station West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  18. DPW Functions • Which DPW functions do we expect NOT to move to campus? – Trash Transfer Stations – Salt Domes – Commercial Drivers License Course West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  19. Current – Staff and Functions • Existing number of DPW staff on campus : 1100 (>70% District residents) • Functions – Fleet Management Administration – Parking Enforcement Management Administration – Solid Waste Management Administration • Street + Alley Cleaning Division West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  20. Future – Staff and Functions • Existing number of DPW staff on campus : 1100 • Proposed number of DPW staff on campus: 1370 • Functions – Fleet Management Administration – Parking Enforcement Management Administration – Solid Waste Management Administration • Street + Alley Cleaning Division • Solid Waste Education and Enforcement Program • Nuisance – Graffiti Removal – All Administration West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  21. Parking/Vehicle Storage • On-site parking for all fleet and personal vehicles • Incorporating transportation management strategies and best practices to minimize personal vehicle use West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  22. Community Input and the Future Campus What we heard from the community Design Excellence • Clean, update & optimize vehicle operations Sustainability • Maximize green and sustainable design on campus • Increase use of alternative (green) fuels Connectivity / Safety • Minimize traffic and parking impacts on community • Beautify streetscape on W Virginia Ave NE and make safer • Use the campus to reconnect disconnected community Retail / Small Businesses / Commercial / Flex • Create community- serving retail, space for local “makers” and innovative businesses on W Virginia Ave NE Parks / Open Space / Community Space • Set aside space for community rooms and job training • Provide public/civic open space West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  23. 4 Future Campus West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  24. Project Purpose Vision Statement Transform the campus at West Virginia Ave NE into a model of sustainable public works operations and a catalyst for community development West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  25. DPW Program Guidance West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  26. DPW Campus Concepts – DPW Program A D B A C B C D D West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  27. Community Feedback – Retail / Small Businesses / Commercial / Flex “ Mom and Pop ” “Retail that caters to the community” “Businesses that create jobs” “Job training” “Community Space/Rooms” West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  28. DPW Campus Concepts – Retail / Small Businesses / Commercial / Flex A C B B A C West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  29. Community Feedback – Design Excellence “Inviting streetscape” “Gateway into the community” “A water feature or art” “Great architecture” “Pedestrian and active” West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  30. DPW Campus Concepts – Design Excellence A A B B C B A C West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  31. Community Feedback – Connectivity+ Safety “Really, really critical for the long term development of Ivy City…is the connectivity ” “Bring some light into the community” West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  32. DPW Campus Concepts – Connectivity + Safety A B C West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  33. Community Feedback – Parks / Open Space + Greening “We are very interested in seeing green space in Ivy City” “..looking for a more friendly type of [public space in our] community. We have children. They need some type of rec time or recreation space.” West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

  34. DPW Campus Concepts – Open Space + Greening Potential Greening Opportunities West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House West Virginia Avenue Public Works Campus Master Plan 2 nd Public Open House

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.