Seismic Evaluation of Grouted Splice Sleeve Connections for - - PowerPoint PPT Presentation

seismic evaluation of grouted splice sleeve connections
SMART_READER_LITE
LIVE PREVIEW

Seismic Evaluation of Grouted Splice Sleeve Connections for - - PowerPoint PPT Presentation

Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast Concrete Bridge Piers Chris P. Pantelides, PhD, PE, SE M.J. Ameli, PhD Candidate Saratoga Springs, NY April 2015 Accelerated Bridge Construction ABC Connections


slide-1
SLIDE 1

Seismic Evaluation of Grouted Splice Sleeve Connections for Reinforced Precast Concrete Bridge Piers

Chris P. Pantelides, PhD, PE, SE M.J. Ameli, PhD Candidate Saratoga Springs, NY April 2015

slide-2
SLIDE 2

Introduction

2

Accelerated Bridge Construction

ABC Connections Modified for High-Seismic Regions Khaleghi et al. (2012) Utah Transit Authority (2012)

slide-3
SLIDE 3

Introduction

3

GGSS FGSS

slide-4
SLIDE 4

Air Tests

4

GGSS FGSS

slide-5
SLIDE 5

Air Tests

5

  • Rebar fracture
  • 169%fy on average
  • Type 2 (Building)
  • FMC (Bridge)
  • Pull-out failure
  • 145%fy on average
  • Type 1 (Building)
  • FMC (Bridge)

fy = 76 ksi

FGSS GGSS

slide-6
SLIDE 6

Tests

6

  • Prototype bridges in Utah considered
  • Capacity-based design procedure
  • AASHTO LRFD and AASHTO Seismic for detailing
  • Sectional and Pushover analyses conducted

  • GGSS

FGSS

slide-7
SLIDE 7

Half-Scale Tests

7

slide-8
SLIDE 8

Construction of Specimens

1 2 3 4

8

slide-9
SLIDE 9

Half-Scale Tests/GGSS-1 Construction

9

slide-10
SLIDE 10

Half-Scale Tests/GGSS-2 Construction

10

slide-11
SLIDE 11

Half-Scale Tests/GGSS-3 Construction

11

slide-12
SLIDE 12

Half-Scale Tests/GGSS-CIP Construction

12

slide-13
SLIDE 13

Half-Scale Test/FGSS-1 Construction

13

slide-14
SLIDE 14

Half-Scale Test/FGSS-2 Construction

14

slide-15
SLIDE 15

Half-Scale Test/FGSS-CIP Construction

15

slide-16
SLIDE 16

Test Procedure

16

GGSS-2 Construction and Installation

POT#1 Strain Gauges String Potentiometers LVDTs

slide-17
SLIDE 17

Test Procedure

17

GGSS-2 Construction and Installation

  • 12
  • 10
  • 8
  • 6
  • 4
  • 2

2 4 6 8 10 12 2 4 6 8 10 12 14 16 18 20 22

Drift (%) Cycles

slide-18
SLIDE 18

Test Results

18

Column-to-Footing Connections: Hysteretic Response

GGSS-2 GGSS-3 GGSS-CIP

GGSS-1

slide-19
SLIDE 19

Test Results/GGSS-2

19

Column-to-Footing Connections: Observations

slide-20
SLIDE 20

Test Results/GGSS-3

20

Column-to-Footing Connections: Observations

@ 3% Drift @ 6% Drift (Peak) @ 8% Drift

slide-21
SLIDE 21

Test Results

21

Column-to-Footing Connections: Comparison Column-to-Footing Connections: Curvature Profile

GGSS-2 GGSS-3

slide-22
SLIDE 22

Test Results

22

Column-to-Cap Beam Connections: Hysteretic Response

FGSS-1 FGSS-2 FGSS-CIP

slide-23
SLIDE 23

Test Results/FGSS-1

23

slide-24
SLIDE 24

Test Results/FGSS-2

24

slide-25
SLIDE 25

Test Results

25

Column-to-Cap Beam Connections: Comparison Column-to-Cap Beam Connections: Curvature Profile

FGSS-1 FGSS-2

slide-26
SLIDE 26

26

Repairability  CFRP composite doughnut with headed steel bars

slide-27
SLIDE 27

27

Repairability  CFRP composite doughnut with headed steel bars

Repaired specimen performed as good or better than the precast GSS specimen

18% larger ultimate load capacity 18% larger ultimate displacement capacity 5% larger displacement ductility 15% larger energy dissipation capacity at 6% drift ratio

GSS

slide-28
SLIDE 28

Conclusions

28

Column-to-Cap Beam Connections [FGSS] Column-to-Footing Connections [GGSS] General Findings

  • Desirable ductile performance of the CIP specimens
  • Failure of CIP specimens was rebar fracture due to low cycle fatigue
  • Localized damage for precast specimens with GSS in column base
  • Similar damage state, strength capacity, curvature distribution, and hysteretic

performance to CIP specimens when GSS located in footing or cap beam, BUT different termination point and displacement ductility capacity for all precast specimens

  • Repairable ABC Connections
  • Failure of all precast specimens due to premature rebar fracture
  • Improved displacement ductility capacity when GGSS in the footing – harder to build
  • Superior displacement ductility capacity when debonding implemented
  • Pull-out failure for FGSS-1 due to excessive bond-slip
  • Pull-out failure and premature rebar fracture occurred for FGSS-2
  • Improved overall performance when FGSS located in the cap beam – harder to build
slide-29
SLIDE 29

29

  • University of Utah
  • Joel Parks
  • Dylan Brown
  • Prof. Lawrence D. Reaveley
  • Mark Bryant
  • Utah Department of Transportation
  • Carmen Swanwick
  • Joshua Sletten
  • New York State Department of Transportation
  • Harry White
  • Texas Department of Transportation
  • Mountain Plains Consortium
  • NMB Splice Sleeve North America & Erico

Acknowledgements