Scanners in Period 4 and 11 of the PSB Federico Roncarolo BE-BI - - PowerPoint PPT Presentation

scanners in period 4 and 11 of the psb
SMART_READER_LITE
LIVE PREVIEW

Scanners in Period 4 and 11 of the PSB Federico Roncarolo BE-BI - - PowerPoint PPT Presentation

SPACE RESERVATION REQUEST EDMS n. 1506932 New SEM Grid Monitor and New Fast Wire Scanners in Period 4 and 11 of the PSB Federico Roncarolo BE-BI Paolo Magagnin BE-BI Exis isting sit situation Section 4L1 Section 11L1 These two sectors


slide-1
SLIDE 1

Federico Roncarolo BE-BI Paolo Magagnin BE-BI

SPACE RESERVATION REQUEST

EDMS n. 1506932

New SEM Grid Monitor and New Fast Wire Scanners in Period 4 and 11 of the PSB

slide-2
SLIDE 2

Exis isting sit situation

Section 4L1 Section 11L1 These two sectors have been chosen to house:

  • 1 SEM Grid Monitor
  • 8 fast Wire Scanners
slide-3
SLIDE 3

In Introductio ion

1 SEM Grid Monitor:

  • Turn by turn profile

measurement at the PSB injection requested by BE-OP

  • Measurements in ring 3 only will

be sufficient for characterising the PSB injection mismatch

  • Sector 4L1 identified as suitable

location. Section 4L1 Section 11L1 SEM 8 Fast wire Scanners:

  • Horizontal and vertical

simultaneous scans  Two different section required

  • Sectors 4L1 and 11L1 identified as

suitable

  • BWS prototype: section 4L1 ring 3

B W S B W S B W S

slide-4
SLIDE 4

Tim imescale

1 SEM Grid Monitor:

  • YETS 2017 – 2018: SEM Grid

installation Section 4L1 Section 11L1 SEM 8 Fast wire Scanners:

  • YETS 2016 – 2017: BWS prototype

installation

  • LS2: 7 BWS installation

B W S B W S B W S

slide-5
SLIDE 5

Reason for r change

1 SEM Grid Monitor: Essential for turn by turn profile measurement Section 4L1 Section 11L1 SEM 8 Fast wire Scanners:

  • Standardisation and reliability

improvement of CERN’s Wire Scanners

  • BWS prototype: performance

evaluation before series production

B W S B W S B W S

slide-6
SLIDE 6

Detailed description – se section 4L 4L1

  • 1 horizontal and 1 vertical BWS required for each ring  horizontal BWS installed in

section 4L1 (1 per ring)

  • Longitudinal available space in 4L1 ring 3 for the installations of the SEM Grid +

BWS: 1200 mm

  • Preliminary BWS design with a longitudinal dimension of 450 mm, leaving sufficient

space for the SEM Grid.

  • New mechanical design of the SEM Grid due to the limited vertical space for the

presence of the other beam pipe: not started yet.

slide-7
SLIDE 7

Detailed description – se section 11 11L1

  • Vertical BWS installed in section 11L1 (1 per ring)
  • Additional pumping capability will be evaluated after the vacuum qualification of

the components and assemblies.

  • Not cooling foreseen on BWS due to RF heating

B W S B W S

slide-8
SLIDE 8

Conclusions

  • The ECR will be written in the first semester of 2016, and will include also the

SEM Grid if the design will be already started

  • Investigation of radiation issues will be included in the ECR (radiation dose

planning).